[2017] UGCommC 253

[2017] UGCommC 253

The court found that the Defendant was liable for delay in handing over the suit property, with compensation due for 17 months of delay, less amounts already paid. The Plaintiff contributed to further delay by undertaking alterations, and is estopped from attributing that period to the Defendant. The Plaintiff...

Source-derived case information.

Citation
[2017] UGCommC 253
Parties
Plaintiff: Zawedde Sandra; Defendant: Kensington Africa Ltd
Court
Commercial Court of Uganda
Jurisdiction
Uganda
Case Number
High Court Civil Suit No 214 of 2012
Procedural Posture
Civil Suit / Judgment
Outcome
Judgment for the Plaintiff in part; orders made for compensation, damages, expert inspection, and costs.
Judges
Alividza, J
Legal Topics
Contract Breach, Misrepresentation, Sale of Land, Delay in Completion, Damages Assessment, Specific Performance
Source Language
en
Commercial and Corporate Land and Property Contract Breach Misrepresentation Sale of Land Delay in Completion Damages Assessment Specific Performance

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 6 Authorities cited 12 Party arguments 2 Amounts and remedies 6
Sign in to unlock

Parties

Zawedde Sandra

Plaintiff

Kensington Africa Ltd

Defendant

Procedural Posture

Civil Suit / Judgment

  1. 1 Whether the Defendant breached the agreement in the respects claimed by the Plaintiff.
  2. 2 Whether the Defendant inordinately delayed to hand over the suit property.
  3. 3 Whether the Defendant discharged its duty to pay compensation to the Plaintiff for delayed hand-over of the suit property.

Ratio Decidendi

The court found that the Defendant was liable for delay in handing over the suit property, with compensation due for 17 months of delay, less amounts already paid. The Plaintiff contributed to further delay by undertaking alterations, and is estopped from attributing that period to the Defendant. The Plaintiff failed to prove, on a balance of probabilities, that the Defendant installed poor quality fittings or exhibited poor workmanship at the time of handover, nor did the Defendant prove the contrary. The Defendant was found guilty of misrepresentation regarding the promise of two car parking spaces, which induced the Plaintiff to enter the contract. The Plaintiff was not entitled to...

Court Disposition

Judgment for the Plaintiff in part; orders made for compensation, damages, expert inspection, and costs.

Orders

  • An independent expert agreed upon by the parties to ascertain the current value and conformity of the property; if below purchase price or not matching sample/show houses, Defendant to reimburse Plaintiff accordingly.
  • Plaintiff entitled to compensation for delay of USD 5,133 with interest at 28% per annum from March 2012 until payment in full.