[2015] UGCommC 80

[2015] UGCommC 80

The court finds that the preliminary objection regarding the Plaintiff's locus standi and privity to the contract cannot be resolved solely on the pleadings and submissions, as there are factual controversies regarding the identity of the Plaintiff and its relationship to the contracts in question. The distinction...

Source-derived case information.

Citation
[2015] UGCommC 80
Parties
Plaintiff: ZTE Corporation; Defendant: Uganda Telecom
Court
Commercial Court of Uganda
Jurisdiction
Uganda
Case Number
HCCS 169 of 2013
Procedural Posture
Civil Suit / Ruling on Preliminary Objection
Outcome
Preliminary objection stayed; to be tried as a preliminary issue with evidence.
Legal Topics
Privity of Contract, Locus Standi, Contractual Breach, Third Party Rights, Authority of Company Officers
Source Language
english
Commercial and Corporate Civil Procedure Privity of Contract Locus Standi Contractual Breach Third Party Rights Authority of Company Officers

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 17 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

ZTE Corporation

Plaintiff

Uganda Telecom

Defendant

Procedural Posture

Civil Suit / Ruling on Preliminary Objection

  1. 1 Whether the Plaintiff has locus standi to bring the suit based on the contract executed between Uganda Telecom and ZTE (H. K) Ltd.
  2. 2 Whether the Plaintiff is privy to the contract and can enforce rights under it.
  3. 3 Whether the repayment agreement executed between Uganda Telecom and ZTE Corporation confers enforceable rights on the Plaintiff.

Ratio Decidendi

The court finds that the preliminary objection regarding the Plaintiff's locus standi and privity to the contract cannot be resolved solely on the pleadings and submissions, as there are factual controversies regarding the identity of the Plaintiff and its relationship to the contracts in question. The distinction between ZTE (H. K) Ltd and ZTE Corporation, and the authority of the signatories to the repayment agreement, require evidence to be adduced. A preliminary objection must be based on uncontested facts, and in this case, the facts are disputed and require clarification through trial. Therefore, the point of law is stayed and will be tried as a preliminary issue with evidence on...

Court Disposition

Preliminary objection stayed; to be tried as a preliminary issue with evidence.

Orders

  • The preliminary objection is stayed and shall be tried as a preliminary issue upon adducing evidence on the identity of the Plaintiff and authority to execute the relevant agreements.
  • Costs of the preliminary objection to abide the outcome of the trial.