[2024] UGCA 238

[2024] UGCA 238

The Court of Appeal found that the appellant failed to prove that force majeure events, such as adverse weather and insurgency, rendered contract performance impossible. The evidence showed that issues raised as force majeure were addressed during project meetings and did not prevent the appellant from continuing...

Source-derived case information.

Citation
[2024] UGCA 238
Parties
Appellant: Zzimwe Enterprises, Hardwares & Construction Ltd; Respondent: Attorney General
Court
Court of Appeal of Uganda
Jurisdiction
Uganda
Case Number
Civil Appeal 116 of 2019
Procedural Posture
Civil Appeal / Appeal From High Court Commercial Division Judgment
Outcome
appeal dismissed
Judges
Egonda-Ntende, JA, Mulyagonja, JA, Luswata, JA
Legal Topics
Contract Termination, Force Majeure, Breach of Contract, Damages, Retention of Property
Source Language
en
Commercial and Corporate Civil Procedure Contract Termination Force Majeure Breach of Contract Damages Retention of Property

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 19 Party arguments 2 Amounts and remedies 5
Sign in to unlock

Parties

Zzimwe Enterprises, Hardwares & Construction Ltd

Appellant

Attorney General

Respondent

Procedural Posture

Civil Appeal / Appeal From High Court Commercial Division Judgment

  1. 1 Whether the trial Judge erred in holding that the appellant's claim of non-performance due to force majeure and insurgency was false and unbelievable.
  2. 2 Whether the trial Judge erred in holding that the respondent was justified in retaining the appellant's construction equipment after contract termination.
  3. 3 Whether the trial Judge erred in declining to award special, general, punitive, aggravated, and exemplary damages, as well as interest, to the appellant.

Ratio Decidendi

The Court of Appeal found that the appellant failed to prove that force majeure events, such as adverse weather and insurgency, rendered contract performance impossible. The evidence showed that issues raised as force majeure were addressed during project meetings and did not prevent the appellant from continuing work. The contract expressly provided that, upon termination for contractor default, all materials and equipment on site would become the property of the employer. The appellant did not dispute the termination or provide sufficient evidence to support claims for damages or wrongful retention of equipment. The trial Judge correctly applied the contract terms and legal principles,...

Court Disposition

appeal dismissed

Orders

  • The appeal is dismissed with costs to the respondent both in the Court of Appeal and the High Court.