Panther Real Estate Development LLC v Modern Executive Systems Contracting LLC [2022] DIFC CA 016 (12 May 2023)
The 42-day detailed claim requirement under Sub-Clause 20.1 is not a condition precedent to entitlement to extension of time; failure to comply may affect the amount awarded but does not bar the claim. The 28-day notice requirement is a strict condition precedent. The 14-day dissatisfaction notice under Sub-Clause 3.5 is a condition precedent to challenging the Engineer’s determination. Time for the 28-day notice runs from when the contractor becomes aware or ought to have become aware of the event or circumstance. The prevention principle does not apply to override clear contractual notice provisions.
- Citation
- [2022] DIFC CA 016
- Parties
- Claimant/respondent/cross Appellant: Panther Real Estate Development LLC; Defendant/appellant: Modern Executive Systems Contracting LLC
- Jurisdiction
- United Arab Emirates
- Judgment Date
- 12 May 2023
- Procedural Posture
- Appeal / Judgment on Appeal From First Instance Decision
- Outcome
- Appeal dismissed; Cross Appeal allowed in part
- Legal Topics
- Extension of Time, Liquidated Damages, FIDIC Contracts, Notice Requirements, Termination of Contract, Performance Guarantees
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Panther Real Estate Development LLC
Claimant/respondent/cross Appellant
Modern Executive Systems Contracting LLC
Defendant/appellant
Procedural Posture
Appeal / Judgment on Appeal From First Instance Decision
Legal Issues
- 1 Whether the 42-day detailed claim requirement under Sub-Clause 20.1 of the FIDIC Conditions is a condition precedent to entitlement to extension of time.
- 2 Whether the 14-day dissatisfaction notice under Sub-Clause 3.5 is a condition precedent to challenging the Engineer’s determination.
- 3 When time begins to run for the 28-day notice requirement under Sub-Clause 20.1.
Ratio Decidendi
The 42-day detailed claim requirement under Sub-Clause 20.1 is not a condition precedent to entitlement to extension of time; failure to comply may affect the amount awarded but does not bar the claim. The 28-day notice requirement is a strict condition precedent. The 14-day dissatisfaction notice under Sub-Clause 3.5 is a condition precedent to challenging the Engineer’s determination. Time for the 28-day notice runs from when the contractor becomes aware or ought to have become aware of the event or circumstance. The prevention principle does not apply to override clear contractual notice provisions.
Court Disposition
Appeal dismissed; Cross Appeal allowed in part
Orders
- Appellant’s Application to amend and rely on supplementary skeleton argument is granted.
- The Appeal by MESC is dismissed.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment