Union Properties PJSC v Trinkler & Partners Ltd & Ors (Claimants; Variation Application - Security for Costs) [2024] ADGMCFI 0004 (09 May 2024)
The application to vary the March Order was refused because the proposed bank guarantee did not provide adequate security for both claimants, and there was insufficient evidence that a satisfactory guarantee could be promptly provided. The claimants had not justified their non-compliance, particularly as they could have paid into court. However, in the interests of justice and the overriding objective, the claimants were granted a final 14-day extension to provide security by payment into court (or other form agreed by the Twelfth Defendant).
- Citation
- [2024] ADGMCFI 0004
- Parties
- First Claimant/applicant: Union Properties P.J.S.C.; Second Claimant/applicant: UPP Capital Investment Co. L.L.C.; First Defendant/respondent: Trinkler & Partners Ltd; Second Defendant/respondent: Thomas Pierre Trinkler; Third Defendant/respondent: Patrick Albert Held; Fourth Defendant/respondent: First Fund Management Limited; Fifth Defendant/respondent: Jorg Klar; Sixth Defendant/respondent: Paresh Chandrasen Khiara; Seventh Defendant/respondent: Amna Hasan Ali Saleh Alhammadi; Eighth Defendant/respondent: Dahi Yousef Ahmed Abdulla Almansoori; Ninth Defendant: Naser Butti Omair Yousef Almheiri; Tenth Defendant/respondent: Khalifa Hasan Ali Saleh Alhammadi; Eleventh Defendant/respondent: Stefan Dubach; Twelfth Defendant/respondent: Ahmed Yousef Abdulla Hussain Khouri; Thirteenth Defendant/respondent: Hassan Ashoor Al Mulla; Fourteenth Respondent: Blue Rock Investments L.L.C; Fifteenth Respondent: Dana Middle East Investment L.L.C; Sixteenth Respondent: Mohamed Hasan Ali Saleh Alhammadi; Seventeenth Respondent: Island Falcon Property Management L.L.C; Eighteenth Respondent: Island Falcon Investments L.L.C; Nineteenth Respondent: Texture Global Investment Limited
- Jurisdiction
- United Arab Emirates
- Judgment Date
- 09 May 2024
- Procedural Posture
- Civil (commercial Fraud, Security for Costs) / Interlocutory Application to Vary Order and for Extension of Time
- Outcome
- Application to vary the March Order refused; extension of time granted for provision of security by payment into court.
- Legal Topics
- Security for Costs, Variation of Court Orders, Relief From Sanctions, Bank Guarantees, Non Compliance With Court Orders
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Union Properties P.J.S.C.
First Claimant/applicant
UPP Capital Investment Co. L.L.C.
Second Claimant/applicant
Trinkler & Partners Ltd
First Defendant/respondent
Thomas Pierre Trinkler
Second Defendant/respondent
Patrick Albert Held
Third Defendant/respondent
First Fund Management Limited
Fourth Defendant/respondent
Jorg Klar
Fifth Defendant/respondent
Paresh Chandrasen Khiara
Sixth Defendant/respondent
Amna Hasan Ali Saleh Alhammadi
Seventh Defendant/respondent
Dahi Yousef Ahmed Abdulla Almansoori
Eighth Defendant/respondent
Naser Butti Omair Yousef Almheiri
Ninth Defendant
Khalifa Hasan Ali Saleh Alhammadi
Tenth Defendant/respondent
Stefan Dubach
Eleventh Defendant/respondent
Ahmed Yousef Abdulla Hussain Khouri
Twelfth Defendant/respondent
Hassan Ashoor Al Mulla
Thirteenth Defendant/respondent
Blue Rock Investments L.L.C
Fourteenth Respondent
Dana Middle East Investment L.L.C
Fifteenth Respondent
Mohamed Hasan Ali Saleh Alhammadi
Sixteenth Respondent
Island Falcon Property Management L.L.C
Seventeenth Respondent
Island Falcon Investments L.L.C
Eighteenth Respondent
Texture Global Investment Limited
Nineteenth Respondent
Procedural Posture
Civil (commercial Fraud, Security for Costs) / Interlocutory Application to Vary Order and for Extension of Time
Legal Issues
- 1 Whether the claimants should be granted a variation of the March Order regarding security for costs.
- 2 Whether the form of bank guarantee proposed by the claimants provides adequate security.
- 3 Whether the claimants should be relieved from the consequences of non-compliance with the March Order.
Ratio Decidendi
The application to vary the March Order was refused because the proposed bank guarantee did not provide adequate security for both claimants, and there was insufficient evidence that a satisfactory guarantee could be promptly provided. The claimants had not justified their non-compliance, particularly as they could have paid into court. However, in the interests of justice and the overriding objective, the claimants were granted a final 14-day extension to provide security by payment into court (or other form agreed by the Twelfth Defendant).
Court Disposition
Application to vary the March Order refused; extension of time granted for provision of security by payment into court.
Orders
- Application to vary the March Order is refused.
- Claimants granted 14 days from the order to provide security for the Twelfth Defendant's costs by payment into court (or other form agreed by Mr Khouri).
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment