Arabtec Construction LLC v Ultra Fuji International LLC [2007] DIFC CFI 004 (11 February 2009)
Arabtec was entitled to terminate the Sub-Contract due to Ultra Fuji's fundamental non-performance, including repeated delays, defective works, and failure to comply with safety and programme requirements. The contractual and statutory grounds for termination were both available and complementary. Arabtec is entitled to liquidated damages capped at 10% of the Sub-Contract price and refund of overpayments for unperformed works. Ultra Fuji's counterclaims for further payment and damages for equipment left on site are rejected.
- Citation
- [2007] DIFC CFI 004
- Parties
- Claimant/part 20 Defendant: Arabtec Construction LLC; Defendant/part 20 Claimant: Ultra Fuji International LLC
- Jurisdiction
- United Arab Emirates
- Judgment Date
- 11 February 2009
- Procedural Posture
- Civil Construction Dispute / Judgment After Trial
- Outcome
- Judgment for Arabtec Construction LLC
- Legal Topics
- Termination of Contract, Liquidated Damages, Non Performance, Subcontractor Obligations, Payment Disputes
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Arabtec Construction LLC
Claimant/part 20 Defendant
Ultra Fuji International LLC
Defendant/part 20 Claimant
Procedural Posture
Civil Construction Dispute / Judgment After Trial
Legal Issues
- 1 Whether Arabtec was entitled to terminate the Sub-Contract with Ultra Fuji
- 2 Whether Ultra Fuji was entitled to further payment under the Sub-Contract
- 3 Whether Arabtec is entitled to liquidated damages and refund of payments for unperformed works
Ratio Decidendi
Arabtec was entitled to terminate the Sub-Contract due to Ultra Fuji's fundamental non-performance, including repeated delays, defective works, and failure to comply with safety and programme requirements. The contractual and statutory grounds for termination were both available and complementary. Arabtec is entitled to liquidated damages capped at 10% of the Sub-Contract price and refund of overpayments for unperformed works. Ultra Fuji's counterclaims for further payment and damages for equipment left on site are rejected.
Court Disposition
Judgment for Arabtec Construction LLC
Orders
- Ultra Fuji to pay Arabtec AED 2,442,924.78 as refund for unperformed works
- Ultra Fuji to pay Arabtec AED 883,260 as liquidated damages
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment