Al Sahel Contracting Co. L.L.C. v E.construct FZ-LLC [2023] DIFC CFI 046 (12 January 2023)

Al Sahel Contracting Co. L.L.C. v E.construct FZ-LLC [2023] DIFC CFI 046 (12 January 2023)

The Claimant's requests were denied because they were not limited in time and did not relate to a narrowly defined category of documents.

Citation
[2023] DIFC CFI 046
Parties
Claimant: Al Sahel Contracting Co. L. L. C.; Defendant: E.construct FZ-LLC
Jurisdiction
United Arab Emirates
Judgment Date
12 January 2023
Procedural Posture
Civil / Interlocutory Application for Document Production Order
Outcome
Claimant's document production requests denied
Legal Topics
Document Production, Discovery, Interlocutory Applications

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 1 Authorities cited 1 Party arguments 2
Sign in to unlock

Parties

Al Sahel Contracting Co. L. L. C.

Claimant

E.construct FZ-LLC

Defendant

Procedural Posture

Civil / Interlocutory Application for Document Production Order

  1. 1 Whether the Claimant's document production requests should be granted under RDC 28.36

Ratio Decidendi

The Claimant's requests were denied because they were not limited in time and did not relate to a narrowly defined category of documents.

Court Disposition

Claimant's document production requests denied

Orders

  • Claimant’s Requests No. 1, 2, 3 and 4 are denied
  • The parties shall have liberty to apply