VII. Lanarkshire Tramways Order [1908] UKHL 1005 (30 April 1908)
The preamble was formally proved by evidence, there being no opposition, and the clauses for extension and additional powers were carried.
- Citation
- [1908] UKHL 1005
- Parties
- Promoter: Lanarkshire Tramways
- Jurisdiction
- United Kingdom
- Judgment Date
- 30 April 1908
- Procedural Posture
- Provisional Order / Order Confirmation
- Outcome
- Order confirmed
- Legal Topics
- Extension of Time for Completion, Compulsory Acquisition of Land, Authority to Run Omnibuses, Issuance of Additional Capital, Borrowing Powers
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Full judgment text Downloadable case file Legal principles 2 Party arguments 2 Amounts and remedies 2
Parties
Lanarkshire Tramways
Promoter
Procedural Posture
Provisional Order / Order Confirmation
Legal Issues
- 1 Whether extension of time for completion of tramways should be granted
- 2 Whether authority for compulsory acquisition of land should be extended
- 3 Whether promoters should be authorised to run omnibuses
Ratio Decidendi
The preamble was formally proved by evidence, there being no opposition, and the clauses for extension and additional powers were carried.
Court Disposition
Order confirmed
Orders
- Extension of time for completion of tramways granted
- Extension for compulsory acquisition of land granted
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment