The effective date of termination was 5 September 1999, as found by the Tribunal based on unopposed evidence, and the claim was presented within three months of that date; there was no error of law in the Tribunal's decision. The refusal to adjourn the merits hearing was justified as there was no independent reason...

Source-derived case information.

Citation
[2000] UKEAT 735_00_2706
Parties
Appellant: CEX Games Ltd; Respondent: D. M. J. Moore
Jurisdiction
United Kingdom
Judgment Date
27 June 2000
Procedural Posture
Employment Appeal / Interlocutory and Preliminary Appeal
Outcome
Appeal dismissed
Legal Topics
Unfair Dismissal, Limitation Period, Effective Date of Termination, Adjournment of Hearing, Jurisdiction of Employment Tribunal
Employment Law Unfair Dismissal Limitation Period Effective Date of Termination Adjournment of Hearing Jurisdiction of Employment Tribunal

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 3 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

CEX Games Ltd

Appellant

D. M. J. Moore

Respondent

Procedural Posture

Employment Appeal / Interlocutory and Preliminary Appeal

  1. 1 Whether the unfair dismissal claim was presented within the statutory time limit
  2. 2 Whether the Employment Tribunal erred in refusing to adjourn the merits hearing

Ratio Decidendi

The effective date of termination was 5 September 1999, as found by the Tribunal based on unopposed evidence, and the claim was presented within three months of that date; there was no error of law in the Tribunal's decision. The refusal to adjourn the merits hearing was justified as there was no independent reason for adjournment after the preliminary issue was resolved.

Court Disposition

Appeal dismissed

Orders

  • CEX Games Ltd to pay Mr Moore £300 in costs
  • Parties to prepare for the merits hearing on 5 July 2000