General Construction Limited (Appellant) v (1) Chue Wing & Co Ltd (2) Ibrahim Cassam & Co Ltd (in Liquidation) (Respondents) (Mauritius)
The appellant failed to prove that the collapse of the crane was caused by an event of force majeure, as cyclones of the relevant intensity were foreseeable in Mauritius and the appellant did not establish that all reasonable and practicable precautions were taken to guard against such an event. The award of interest to the second respondent was appropriate and within the jurisdiction of the appellate court to ensure complete justice.
- Citation
- [2013] UKPC 30
- Parties
- Appellant: General Construction Limited; Respondent: Chue Wing & Co Ltd; Respondent: Ibrahim Cassam & Co Ltd
- Jurisdiction
- United Kingdom
- Judgment Date
- 15 October 2013
- Procedural Posture
- Civil Appeal / Final Appellate Judgment
- Outcome
- appeal dismissed
- Legal Topics
- Force Majeure, Liability for Things Under One's Guard, Interest on Judgment Debts
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
General Construction Limited
Appellant
Chue Wing & Co Ltd
Respondent
Ibrahim Cassam & Co Ltd
Respondent
Procedural Posture
Civil Appeal / Final Appellate Judgment
Legal Issues
- 1 Whether the appellant established that the crane collapse was caused by force majeure under article 1384 of the Civil Code
- 2 Whether the Court of Civil Appeal erred in awarding interest to the second respondent after judgment
Ratio Decidendi
The appellant failed to prove that the collapse of the crane was caused by an event of force majeure, as cyclones of the relevant intensity were foreseeable in Mauritius and the appellant did not establish that all reasonable and practicable precautions were taken to guard against such an event. The award of interest to the second respondent was appropriate and within the jurisdiction of the appellate court to ensure complete justice.
Court Disposition
appeal dismissed
Orders
- Appeal dismissed on both the main issue of force majeure and the award of interest.
- Interest to be paid to the second respondent at the legal rate from the date of the original statement of claim until satisfaction of judgment.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment