Mr S Lansom v Sterling Constructions and Renewables Ltd (England and Wales : Breach of Contract) [2024] UKET 6004348/2024 (19 November 2024)

Mr S Lansom v Sterling Constructions and Renewables Ltd (England and Wales : Breach of Contract) [2024] UKET 6004348/2024 (19 November 2024)

The tribunal found that the respondent failed to pay the claimant's contractual entitlements upon termination, amounting to a breach of contract and entitling the claimant to damages.

Citation
[2024] UKET 6004348/2024
Parties
Claimant: Mr S Lansom; Respondent: Sterling Constructions and Renewables Ltd
Jurisdiction
United Kingdom
Judgment Date
19 November 2024
Procedural Posture
Employment Tribunal Breach of Contract / Judgment
Outcome
Claim upheld
Legal Topics
Breach of Contract, Employment Termination

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 1 Authorities cited 1 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Mr S Lansom

Claimant

Sterling Constructions and Renewables Ltd

Respondent

Procedural Posture

Employment Tribunal Breach of Contract / Judgment

  1. 1 Whether the respondent breached the employment contract with the claimant
  2. 2 Whether the claimant is entitled to damages for breach of contract

Ratio Decidendi

The tribunal found that the respondent failed to pay the claimant's contractual entitlements upon termination, amounting to a breach of contract and entitling the claimant to damages.

Court Disposition

Claim upheld

Orders

  • Respondent to pay damages to the claimant for breach of contract