Anthony Glazebrook and Anor v Bellingtone Taylor Kamona (2021/HKC/017) [2022] ZMHC 21 (4 August 2022)

Anthony Glazebrook and Anor v Bellingtone Taylor Kamona (2021/HKC/017) [2022] ZMHC 21 (4 August 2022)

The Settlement Agreement dated 11 December 2020 was voluntarily entered into by the parties, with no evidence of duress. The Defendant, as Managing Director and beneficial owner of the company, was personally involved and liable. The Plaintiff is entitled to the balance of ZMW 528,070.00 under the Settlement...

Source-derived case information.

Citation
[2022] ZMHC 21
Parties
1st Plaintiff: Anthony Glazebrook; 2nd Plaintiff: Angela Chanda Nkoma Glazebrook; Defendant: Bellingtone Taylor Kamona
Court
High Court of Zambia
Jurisdiction
Zambia
Case Number
2021/HKC/017
Procedural Posture
Civil / Judgment
Outcome
Judgment for the Plaintiffs in the sum of ZMW 528,070.00 with interest; Defendant's counterclaim dismissed; no award of costs.
Legal Topics
Privity of Contract, Settlement Agreement, Breach of Contract, Duress, Burden of Proof, Damages, Interest, Costs
Source Language
en
Contract Law Civil Procedure Privity of Contract Settlement Agreement Breach of Contract Duress Burden of Proof Damages +2 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 6 Authorities cited 20 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Anthony Glazebrook

1st Plaintiff

Angela Chanda Nkoma Glazebrook

2nd Plaintiff

Bellingtone Taylor Kamona

Defendant

Procedural Posture

Civil / Judgment

  1. 1 Whether the Plaintiff is entitled to payment of ZMW 528,070.00 as reimbursement under the Settlement Agreement dated 11 December 2020.
  2. 2 Whether the Plaintiff is entitled to damages, additional building costs, interest, and legal costs.
  3. 3 Whether there was duress in the execution of the Settlement Agreement as pleaded by the Defendant.

Ratio Decidendi

The Settlement Agreement dated 11 December 2020 was voluntarily entered into by the parties, with no evidence of duress. The Defendant, as Managing Director and beneficial owner of the company, was personally involved and liable. The Plaintiff is entitled to the balance of ZMW 528,070.00 under the Settlement Agreement, with interest. Claims for additional damages and costs to complete the house were not proved. The Defendant's counterclaim and duress defence are dismissed.

Court Disposition

Judgment for the Plaintiffs in the sum of ZMW 528,070.00 with interest; Defendant's counterclaim dismissed; no award of costs.

Orders

  • Payment of ZMW 528,070.00 to the Plaintiffs as balance under the Settlement Agreement.
  • Interest at bank lending rates from date of action to date of judgment, and thereafter as per the Judgment Act until payment.