Attorney General and Anor v Mumba (Appeal 50 of 2002) [2004] ZMSC 120 (19 April 2004)

Attorney General and Anor v Mumba (Appeal 50 of 2002) [2004] ZMSC 120 (19 April 2004)

The omission to award interest was an accidental slip correctable under the slip rule, and interest should run from the date of the notice of complaint as pleaded, not from the date of correction.

Source-derived case information.

Citation
[2004] ZMSC 120
Parties
1st Appellant: The Attorney-General; 2nd Appellant: Development Bank of Zambia; Respondent: Gershom Moses Burton Mumba
Court
Supreme Court of Zambia
Jurisdiction
Zambia
Case Number
Appeal 50 of 2002
Procedural Posture
Civil Appeal / Post Judgment Notice of Motion Under Slip Rule
Outcome
Notice of Motion allowed; judgment corrected to include interest.
Legal Topics
Slip Rule, Interest on Judgment, Damages
Source Language
en
Civil Procedure Employment Law Slip Rule Interest on Judgment Damages

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 2 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

The Attorney-General

1st Appellant

Development Bank of Zambia

2nd Appellant

Gershom Moses Burton Mumba

Respondent

Procedural Posture

Civil Appeal / Post Judgment Notice of Motion Under Slip Rule

  1. 1 Whether the omission to award interest on compensation was inadvertent and correctable under the slip rule
  2. 2 From what date interest should run on the awarded damages

Ratio Decidendi

The omission to award interest was an accidental slip correctable under the slip rule, and interest should run from the date of the notice of complaint as pleaded, not from the date of correction.

Court Disposition

Notice of Motion allowed; judgment corrected to include interest.

Orders

  • Damages in Kwacha to carry interest at short-term deposit rate from date of Notice of Complaint to date of judgment, and thereafter at 10% until final payment.
  • Damages in US dollars to carry interest at 3% from date of Notice of Complaint until final payment.