Bank of Zambia v Votex Refrigration Company & Another (Appeal 4 of 2013) [2016] ZMSC 237 (22 December 2016)

Bank of Zambia v Votex Refrigration Company & Another (Appeal 4 of 2013) [2016] ZMSC 237 (22 December 2016)

The Supreme Court held that the appellant was liable to pay the 1st respondent for the additional works as the final account did not include the cost of the variation, which was necessitated by defects in the appellant's own design and delayed approval by its consulting engineers. The delay in completion was not...

Source-derived case information.

Citation
[2016] ZMSC 237
Parties
Appellant: Bank of Zambia; 1st Respondent: Votex Refrigeration Company; 2nd Respondent: Dockland Construction Company Limited
Court
Supreme Court of Zambia
Jurisdiction
Zambia
Case Number
Appeal 4 of 2013
Procedural Posture
Civil Appeal / Supreme Court Judgment
Outcome
Appeal dismissed except as to refund of liquidated damages withheld by the 2nd respondent.
Legal Topics
Breach of Contract, Liquidated Damages, Variation of Contract, Subcontracting, Final Account, Unjust Enrichment
Source Language
en
Contract Law Construction Law Breach of Contract Liquidated Damages Variation of Contract Subcontracting Final Account Unjust Enrichment

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 4 Party arguments 2 Amounts and remedies 7
Sign in to unlock

Parties

Bank of Zambia

Appellant

Votex Refrigeration Company

1st Respondent

Dockland Construction Company Limited

2nd Respondent

Procedural Posture

Civil Appeal / Supreme Court Judgment

  1. 1 Whether the appellant was liable to pay the 1st respondent for additional works not included in the original contract sum
  2. 2 Whether the appellant was entitled to levy liquidated damages for delay in completion
  3. 3 Whether the final account discharged the appellant's obligations to the 1st respondent

Ratio Decidendi

The Supreme Court held that the appellant was liable to pay the 1st respondent for the additional works as the final account did not include the cost of the variation, which was necessitated by defects in the appellant's own design and delayed approval by its consulting engineers. The delay in completion was not attributable to the 1st respondent, so the appellant was not entitled to levy liquidated damages. The 2nd respondent was ordered to refund the sum it withheld as liquidated damages, as its counterclaim failed and retention of the sum would amount to unjust enrichment.

Court Disposition

Appeal dismissed except as to refund of liquidated damages withheld by the 2nd respondent.

Orders

  • Appellant to pay the 1st respondent the full contract price plus the cost of additional works.
  • 2nd respondent to refund K92,641,714.74 to the appellant with interest as specified.