China Jiangxi Construction Corporation (Zambia) Limited v Arthur Kunsanama (Suing as Administrator of the Estate of the Late Baird Maurice Kunsanama) and Anor (CAZ/08/251/2018) [2019] ZMCA 375 (10 July 2019)

China Jiangxi Construction Corporation (Zambia) Limited v Arthur Kunsanama (Suing as Administrator of the Estate of the Late Baird Maurice Kunsanama) and Anor (CAZ/08/251/2018) [2019] ZMCA 375 (10 July 2019)

The stay of execution was confirmed because the grounds of appeal regarding quantum and apportionment of liability had prospects of success, and denying the stay could render the appeal nugatory. The application for payment into court was dismissed as it was a procedural misapprehension; payment into court is not...

Source-derived case information.

Citation
[2019] ZMCA 375
Parties
Appellant: China Jiangxi Construction Corporation (Zambia) Limited; 1st Respondent: Arthur Kunsanama (Suing as an Administrator of the Estate of Late Baird Maurice Kunsaunama); 2nd Respondent: Road Development Agency
Court
Court of Appeal of Zambia
Jurisdiction
Zambia
Case Number
CAZ/08/251/2018
Procedural Posture
Civil Appeal / Ruling on Applications for Stay of Execution Pending Appeal and Payment Into Court
Outcome
Stay of execution confirmed; application for payment into court dismissed
Legal Topics
Stay of Execution, Assessment of Damages, Payment Into Court, Apportionment of Liability
Source Language
en
Civil Procedure Tort Law Stay of Execution Assessment of Damages Payment Into Court Apportionment of Liability

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 10 Party arguments 2 Amounts and remedies 4
Sign in to unlock

Parties

China Jiangxi Construction Corporation (Zambia) Limited

Appellant

Arthur Kunsanama (Suing as an Administrator of the Estate of Late Baird Maurice Kunsaunama)

1st Respondent

Road Development Agency

2nd Respondent

Procedural Posture

Civil Appeal / Ruling on Applications for Stay of Execution Pending Appeal and Payment Into Court

  1. 1 Whether the stay of execution pending appeal should be granted
  2. 2 Whether the application for payment into court is proper and should be allowed
  3. 3 Whether the notice of appeal was fatally defective for not specifying parts of the judgment appealed

Ratio Decidendi

The stay of execution was confirmed because the grounds of appeal regarding quantum and apportionment of liability had prospects of success, and denying the stay could render the appeal nugatory. The application for payment into court was dismissed as it was a procedural misapprehension; payment into court is not intended as security pending appeal but as a pre-judgment settlement mechanism.

Court Disposition

Stay of execution confirmed; application for payment into court dismissed

Orders

  • Ex parte order of stay of execution granted on 27th November, 2018 is confirmed with costs to the appellant
  • Application for payment into court is dismissed with costs to the 1st respondent