Once a company is no longer in receivership, it is the proper party to sue or be sued for obligations arising from contracts entered into during receivership; section 114 of the Companies Act applies only while the company is in receivership.

Source-derived case information.

Citation
[2012] ZMHC 39
Parties
Plaintiff: Danait Transport Limited; Defendant: Zambezi Portland Cement Limited
Court
High Court of Zambia
Jurisdiction
Zambia
Case Number
HPC 629 of 2010
Procedural Posture
Civil / Ruling on Application for Misjoinder and Joinder
Outcome
Application dismissed with costs
Legal Topics
Receivership, Agency, Joinder and Misjoinder of Parties
Source Language
en
Company Law Commercial Law Receivership Agency Joinder and Misjoinder of Parties

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 4 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Danait Transport Limited

Plaintiff

Zambezi Portland Cement Limited

Defendant

Procedural Posture

Civil / Ruling on Application for Misjoinder and Joinder

  1. 1 Whether the receiver or the company is the proper party to be sued for contracts entered into during receivership after the company ceases to be in receivership
  2. 2 Interpretation of section 114 of the Companies Act regarding liability of receivers

Ratio Decidendi

Once a company is no longer in receivership, it is the proper party to sue or be sued for obligations arising from contracts entered into during receivership; section 114 of the Companies Act applies only while the company is in receivership.

Court Disposition

Application dismissed with costs

Orders

  • Application for misjoinder and joinder dismissed
  • Matter to come up for status conference on 28th August 2012 at 9:20 hours