Deloitte and Touche v Cable Network Solutions Limited (HPC 599 of 2012) [2014] ZMHC 176 (17 December 2014)

Deloitte and Touche v Cable Network Solutions Limited (HPC 599 of 2012) [2014] ZMHC 176 (17 December 2014)

The Defendant did not complete the contracted works, specifically the fire suppression system, but delays were not solely attributable to the Defendant. The Plaintiff is entitled to a refund for incomplete works less the value of temporary switches supplied by the Defendant. The Defendant is not liable for...

Source-derived case information.

Citation
[2014] ZMHC 176
Parties
Plaintiff: Deloitte and Touche (Suing as a Firm); Defendant: Cable Network Solutions Limited
Court
High Court of Zambia
Jurisdiction
Zambia
Case Number
HPC 599 of 2012
Procedural Posture
Civil / Judgment
Outcome
Judgment for Plaintiff and Defendant in part
Legal Topics
Breach of Contract, Liquidated Damages, Set Off, Variation of Contract, Construction Contracts, Counter Claim
Source Language
en
Contract Law Construction Law Commercial Law Breach of Contract Liquidated Damages Set Off Variation of Contract Construction Contracts +1 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 7 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Deloitte and Touche (Suing as a Firm)

Plaintiff

Cable Network Solutions Limited

Defendant

Procedural Posture

Civil / Judgment

  1. 1 Whether the Defendant failed to perform its contractual obligations under the contract for supply, delivery, installation and commissioning of a Local Area Network.
  2. 2 Whether the Plaintiff is entitled to a refund for incomplete works and liquidated damages.
  3. 3 Whether the Defendant is entitled to its counter-claims for additional works and temporary installations.

Ratio Decidendi

The Defendant did not complete the contracted works, specifically the fire suppression system, but delays were not solely attributable to the Defendant. The Plaintiff is entitled to a refund for incomplete works less the value of temporary switches supplied by the Defendant. The Defendant is not liable for liquidated damages as delays were also caused by the Plaintiff and third parties. The Defendant's counter-claims for additional patch panels and technical works are dismissed for lack of evidence and failure to comply with contractual requirements for written variations.

Court Disposition

Judgment for Plaintiff and Defendant in part

Orders

  • Plaintiff awarded ZMW 141,261,218 less ZMW 35,410 for value of temporary switches supplied by Defendant.
  • Interest awarded from date of Writ of Summons to date of judgment at current Banking Lending Rate, thereafter at Bank of Zambia Bank Lending Rate.