The Applicant persistently delayed in paying rent and failed to meet other obligations under the lease agreements. The Respondent established valid grounds under section 11 of the Act, including intention to reconstruct the premises. The law mandates that where such grounds are established, the court cannot grant a...

Source-derived case information.

Citation
[2024] ZMHC 147
Parties
Applicant: First Capital Bank House; Respondent: Total Energies Marketing Zambia Limited
Court
High Court of Zambia
Jurisdiction
Zambia
Case Number
2022/HP /1704
Procedural Posture
Originating Notice of Motion (application for New Tenancy) / Judgment
Outcome
Application dismissed
Legal Topics
Business Premises Tenancy, Renewal of Lease, Security of Tenure, Breach of Lease, Termination of Tenancy
Source Language
en
Landlord and Tenant Law Commercial Law Business Premises Tenancy Renewal of Lease Security of Tenure Breach of Lease Termination of Tenancy

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 6 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

First Capital Bank House

Applicant

Total Energies Marketing Zambia Limited

Respondent

Procedural Posture

Originating Notice of Motion (application for New Tenancy) / Judgment

  1. 1 Whether the Applicant is entitled to a renewal of the two lease agreements under the Landlord and Tenant (Business Premises) Act
  2. 2 Whether the Respondent's objections to renewal based on persistent delay in rent payment, substantial breaches, and intention to reconstruct are justified

Ratio Decidendi

The Applicant persistently delayed in paying rent and failed to meet other obligations under the lease agreements. The Respondent established valid grounds under section 11 of the Act, including intention to reconstruct the premises. The law mandates that where such grounds are established, the court cannot grant a new tenancy. Therefore, the application for renewal fails.

Court Disposition

Application dismissed

Orders

  • Applicant to hand over possession of the properties within 30 days from the date of judgment