Hellicy Chakosamoto Ng'ambi v Oliver Musonda (Trading as Pladoc Enterprises) (2015/HPC/0364) [2020] ZMHC 397 (16 December 2020)

Hellicy Chakosamoto Ng'ambi v Oliver Musonda (Trading as Pladoc Enterprises) (2015/HPC/0364) [2020] ZMHC 397 (16 December 2020)

The defendant breached the building contract by failing to complete the house within the agreed timeframe and was negligent in commencing construction without statutory approvals and a building permit. The defendant also breached the oral contracts for drilling a borehole and supplying house fittings. The plaintiff...

Source-derived case information.

Citation
[2020] ZMHC 397
Parties
Plaintiff: Hellicy Chakosamoto Ng'ambi; Defendant: Oliver Musonda (trading as Pladoc Enterprises)
Court
High Court of Zambia
Jurisdiction
Zambia
Case Number
2015/HPC/0364
Procedural Posture
Civil Commercial (building Contract) / Judgment
Outcome
Judgment for the plaintiff; defendant's counterclaim dismissed in totality.
Legal Topics
Building Contracts, Breach of Contract, Negligence, Statutory Approvals, Damages, Oral Contracts, Defamation
Source Language
en
Contract Law Tort Law (negligence) Property Law Building Contracts Breach of Contract Negligence Statutory Approvals Damages +2 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 7 Authorities cited 24 Party arguments 2 Amounts and remedies 7
Sign in to unlock

Parties

Hellicy Chakosamoto Ng'ambi

Plaintiff

Oliver Musonda (trading as Pladoc Enterprises)

Defendant

Procedural Posture

Civil Commercial (building Contract) / Judgment

  1. 1 Whether the building contract was breached and by whom
  2. 2 Whether there was negligence in commencing construction without statutory approvals
  3. 3 Whether the oral contracts for borehole drilling and house fittings were breached

Ratio Decidendi

The defendant breached the building contract by failing to complete the house within the agreed timeframe and was negligent in commencing construction without statutory approvals and a building permit. The defendant also breached the oral contracts for drilling a borehole and supplying house fittings. The plaintiff is entitled to damages and refunds for these breaches. The defendant's counterclaims for labour, borehole charges, freight, defamation, and other damages fail for lack of contractual or evidentiary basis.

Court Disposition

Judgment for the plaintiff; defendant's counterclaim dismissed in totality.

Orders

  • Damages for breach of the building contract for failing to construct the house within the agreed timeframe.
  • Damages for negligence for commencing construction without statutory approvals and a building permit.