Manela Developments Limited v MKP Builders (Z) Limited (HP 529 of 2012) [2020] ZMHC 52 (30 April 2020)

Manela Developments Limited v MKP Builders (Z) Limited (HP 529 of 2012) [2020] ZMHC 52 (30 April 2020)

The Plaintiff failed to deliver any completed slabs within the agreed three-month period despite receiving K350,000 and 300 bags of cement. The breach of a fundamental condition entitled the Defendant to terminate the contract. The Plaintiff was not entitled to damages for wrongful termination or loss of profit but...

Source-derived case information.

Citation
[2020] ZMHC 52
Parties
Plaintiff: Manela Developments Limited; Defendant: MKP Builders (Z) Limited
Court
High Court of Zambia
Jurisdiction
Zambia
Case Number
HP 529 of 2012
Procedural Posture
Civil / Judgment
Outcome
Plaintiff's claim for damages for wrongful termination and loss of profit dismissed; judgment for Plaintiff for payment for work done to be assessed; Defendant's counterclaim dismissed for want of prosecution; costs to Plaintiff.
Legal Topics
Breach of Contract, Wrongful Termination, Damages, Loss of Profit, Notice of Termination, Construction Contracts
Source Language
en
Contract Law Construction Law Breach of Contract Wrongful Termination Damages Loss of Profit Notice of Termination Construction Contracts

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 7 Authorities cited 6 Party arguments 2 Amounts and remedies 5
Sign in to unlock

Parties

Manela Developments Limited

Plaintiff

MKP Builders (Z) Limited

Defendant

Procedural Posture

Civil / Judgment

  1. 1 Whether the Plaintiff failed to perform the contract
  2. 2 Whether the Defendant wrongfully terminated the contract
  3. 3 Whether the Defendant could terminate the contract without notice

Ratio Decidendi

The Plaintiff failed to deliver any completed slabs within the agreed three-month period despite receiving K350,000 and 300 bags of cement. The breach of a fundamental condition entitled the Defendant to terminate the contract. The Plaintiff was not entitled to damages for wrongful termination or loss of profit but was entitled to payment for work done, to be assessed.

Court Disposition

Plaintiff's claim for damages for wrongful termination and loss of profit dismissed; judgment for Plaintiff for payment for work done to be assessed; Defendant's counterclaim dismissed for want of prosecution; costs to Plaintiff.

Orders

  • Judgment for Plaintiff for work done to be assessed by Deputy Registrar
  • Plaintiff's claims for damages for wrongful termination and loss of profit dismissed