Manela Development Limited v MKP Builders (Z) Limited (2012/HP/0529) [2020] ZMHC 395 (30 April 2020)

Manela Development Limited v MKP Builders (Z) Limited (2012/HP/0529) [2020] ZMHC 395 (30 April 2020)

The Plaintiff breached a fundamental condition of the contract by failing to deliver any completed slabs within the agreed three-month period despite receiving mobilization funds and materials. The Defendant was entitled to terminate the contract. The Plaintiff is not entitled to damages for wrongful termination or...

Source-derived case information.

Citation
[2020] ZMHC 395
Parties
Plaintiff: Manela Developments Limited; Defendant: MKP Builders (Z) Limited
Court
High Court of Zambia
Jurisdiction
Zambia
Case Number
2012/HP/0529
Procedural Posture
Civil / Judgment
Outcome
Plaintiff's claim for wrongful termination and loss of profit dismissed; judgment for Plaintiff for work done to be assessed; Defendant's counterclaim dismissed for want of prosecution; costs to Plaintiff.
Legal Topics
Wrongful Termination, Breach of Contract, Damages, Loss of Profit, Notice of Termination
Source Language
en
Contract Law Construction Law Wrongful Termination Breach of Contract Damages Loss of Profit Notice of Termination

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 6 Party arguments 2 Amounts and remedies 5
Sign in to unlock

Parties

Manela Developments Limited

Plaintiff

MKP Builders (Z) Limited

Defendant

Procedural Posture

Civil / Judgment

  1. 1 Whether the Plaintiff failed to perform the contract
  2. 2 Whether the Defendant wrongfully terminated the contract
  3. 3 Whether the Defendant could terminate the contract without notice

Ratio Decidendi

The Plaintiff breached a fundamental condition of the contract by failing to deliver any completed slabs within the agreed three-month period despite receiving mobilization funds and materials. The Defendant was entitled to terminate the contract. The Plaintiff is not entitled to damages for wrongful termination or loss of profit but is entitled to payment for work actually done, to be assessed.

Court Disposition

Plaintiff's claim for wrongful termination and loss of profit dismissed; judgment for Plaintiff for work done to be assessed; Defendant's counterclaim dismissed for want of prosecution; costs to Plaintiff.

Orders

  • Judgment for Plaintiff for work done to be assessed by Deputy Registrar
  • Plaintiff's claims for wrongful termination and loss of profit dismissed