National Housing Authority v Tumelo (Appeal 19 of 2007) [2008] ZMSC 128 (16 May 2008)

National Housing Authority v Tumelo (Appeal 19 of 2007) [2008] ZMSC 128 (16 May 2008)

The appellant breached the contracts by failing to complete and deliver the houses within the stipulated period, and the asserted shortage of cement was not substantiated or communicated. The award of mesne profits was not justified as the claim was unsubstantiated and the respondent was not in possession. The...

Source-derived case information.

Citation
[2008] ZMSC 128
Parties
Appellant: National Housing Authority; Respondent: Chali Tumelo
Court
Supreme Court of Zambia
Jurisdiction
Zambia
Case Number
Appeal 19 of 2007
Procedural Posture
Civil Appeal / Judgment on Appeal
Outcome
appeal partially allowed; cross-appeal dismissed
Legal Topics
Breach of Contract, Damages, Mesne Profits, Liability for Loss of Property, Construction Contracts
Source Language
en
Contract Law Property Law Breach of Contract Damages Mesne Profits Liability for Loss of Property Construction Contracts

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 10 Party arguments 2 Amounts and remedies 4
Sign in to unlock

Parties

National Housing Authority

Appellant

Chali Tumelo

Respondent

Procedural Posture

Civil Appeal / Judgment on Appeal

  1. 1 Whether the appellant breached the contract by failing to complete and deliver two houses within the stipulated period
  2. 2 Whether the award of mesne profits was justified
  3. 3 Whether the appellant was liable for loss of respondent's property (cement and household goods) due to lack of security

Ratio Decidendi

The appellant breached the contracts by failing to complete and deliver the houses within the stipulated period, and the asserted shortage of cement was not substantiated or communicated. The award of mesne profits was not justified as the claim was unsubstantiated and the respondent was not in possession. The appellant was liable for the loss of cement and household goods due to its undertaking to provide security and retain custody of the property.

Court Disposition

appeal partially allowed; cross-appeal dismissed

Orders

  • Awards for mesne profits are set aside
  • All other awards to the respondent are upheld