Speedpay Limited v Puma Energy Plc (2024/HPC/0027) [2025] ZMHC 7 (7 February 2025)

Speedpay Limited v Puma Energy Plc (2024/HPC/0027) [2025] ZMHC 7 (7 February 2025)

There was no valid and enforceable agreement between the parties following the expiry of the EUSLA, as negotiations for the purchase of the license did not result in a concluded contract. Therefore, the Plaintiff is not entitled to specific performance, an independent valuation, payment for the license, or damages...

Source-derived case information.

Citation
[2025] ZMHC 7
Parties
Plaintiff: Speedpay Limited; Defendant: Puma Energy PLC
Court
High Court of Zambia
Jurisdiction
Zambia
Case Number
2024/HPC/0027
Procedural Posture
Civil / Judgment
Outcome
Plaintiff's claims dismissed; costs awarded to Defendant.
Legal Topics
Specific Performance, Breach of Contract, Software Licensing, Damages, Valuation of Intangible Assets
Source Language
en
Contract Law Commercial Law Specific Performance Breach of Contract Software Licensing Damages Valuation of Intangible Assets

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 7 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Speedpay Limited

Plaintiff

Puma Energy PLC

Defendant

Procedural Posture

Civil / Judgment

  1. 1 Whether there was a valid enforceable agreement between the Plaintiff and Defendant following termination of the EUSLA
  2. 2 Whether the Plaintiff is entitled to specific performance of the EUSLA
  3. 3 Whether the Defendant is in breach of the EUSLA

Ratio Decidendi

There was no valid and enforceable agreement between the parties following the expiry of the EUSLA, as negotiations for the purchase of the license did not result in a concluded contract. Therefore, the Plaintiff is not entitled to specific performance, an independent valuation, payment for the license, or damages for breach of contract.

Court Disposition

Plaintiff's claims dismissed; costs awarded to Defendant.

Orders

  • Order for specific performance of clause 3.6 of the EUSLA refused.
  • Order for independent valuation refused.