Suban Petroleum Zambia Limited v Dockland Construction Limited (APPEAL NO. 29/2009; SCZ/8/10/2009) [2013] ZMSC 82 (22 October 2013)

Suban Petroleum Zambia Limited v Dockland Construction Limited (APPEAL NO. 29/2009; SCZ/8/10/2009) [2013] ZMSC 82 (22 October 2013)

The Supreme Court held that the Tank Farm and electrical works were not part of the original contract and constituted additional works for which the Respondent was entitled to payment. Some sums claimed by the Respondent were proved by evidence and admitted by the Appellant, but other figures, particularly those...

Source-derived case information.

Citation
[2013] ZMSC 82
Parties
Appellant: Susan Petroleum Zambia Limited; Respondent: Dockland Construction Limited
Court
Supreme Court of Zambia
Jurisdiction
Zambia
Case Number
APPEAL NO. 29/2009 ; SCZ/8/10/2009
Procedural Posture
Civil Appeal / Supreme Court Judgment on Appeal From High Court
Outcome
Appeal partly allowed and partly dismissed
Legal Topics
Breach of Contract, Special Damages, Assessment of Damages, Construction Contracts, Counterclaims, Delay in Performance
Source Language
en
Contract Law Civil Procedure Breach of Contract Special Damages Assessment of Damages Construction Contracts Counterclaims Delay in Performance

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 7 Party arguments 2 Amounts and remedies 7
Sign in to unlock

Parties

Susan Petroleum Zambia Limited

Appellant

Dockland Construction Limited

Respondent

Procedural Posture

Civil Appeal / Supreme Court Judgment on Appeal From High Court

  1. 1 Whether the Tank Farm and electrical works were part of the original contract or constituted additional works
  2. 2 Whether the sums claimed as special damages and other amounts were proved by evidence
  3. 3 Whether the Appellant was entitled to its counterclaim for loss due to delay in completion

Ratio Decidendi

The Supreme Court held that the Tank Farm and electrical works were not part of the original contract and constituted additional works for which the Respondent was entitled to payment. Some sums claimed by the Respondent were proved by evidence and admitted by the Appellant, but other figures, particularly those pleaded as special damages, were not proved. The Appellant's counterclaim for loss due to delay was dismissed as the delay was justified by additional works, heavy rains, and delays by other subcontractors. The trial judge erred by not ordering assessment of damages for unproven sums; the matter was referred to the Deputy Registrar for assessment.

Court Disposition

Appeal partly allowed and partly dismissed

Orders

  • Deputy Registrar to assess general damages and figures not proved
  • Each party to bear own costs of the appeal