The applicant demonstrated on a balance of probabilities that, due to the respondent being based outside the jurisdiction and the urgency of the matter, an interim attachment order was necessary to prevent the proceedings from being rendered nugatory and to preserve the subject matter pending arbitration.

Source-derived case information.

Citation
[2018] ZMHC 559
Parties
Applicant: Zambia Logistics Limited; Respondent: ARS Freight Company Limited
Court
High Court of Zambia
Jurisdiction
Zambia
Case Number
HPC/ARB 7 of 2018
Procedural Posture
Arbitration Related Civil Application / Ruling on Application for Interim Attachment of Property Before Commencement of Arbitration
Outcome
Application for interim attachment of property confirmed
Legal Topics
Interim Measures, Attachment of Property, Enforcement of Arbitral Awards
Source Language
en
Arbitration Civil Procedure Interim Measures Attachment of Property Enforcement of Arbitral Awards

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 1 Authorities cited 1 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

Zambia Logistics Limited

Applicant

ARS Freight Company Limited

Respondent

Procedural Posture

Arbitration Related Civil Application / Ruling on Application for Interim Attachment of Property Before Commencement of Arbitration

  1. 1 Whether the applicant is entitled to an interim order of attachment of property before the commencement of arbitration proceedings under section 11 of the Arbitration Act No. 19 of 2000

Ratio Decidendi

The applicant demonstrated on a balance of probabilities that, due to the respondent being based outside the jurisdiction and the urgency of the matter, an interim attachment order was necessary to prevent the proceedings from being rendered nugatory and to preserve the subject matter pending arbitration.

Court Disposition

Application for interim attachment of property confirmed

Orders

  • Order of interim attachment of the respondent's truck, trailer, and container confirmed
  • No order as to costs