Dexprint Investments v Ace Property & Investments (Pvt) Ltd & Ors (HH 48 of 2004) [2004] ZWHHC 48 (27 January 2004)

Dexprint Investments v Ace Property & Investments (Pvt) Ltd & Ors (HH 48 of 2004) [2004] ZWHHC 48 (27 January 2004)

The purported cancellation of the agreement by the first respondent was premature as the required notice period had not expired; therefore, the first respondent was in breach of contract. The issue of damages for breach is referred to trial.

Source-derived case information.

Citation
[2004] ZWHHC 48
Parties
Applicant: Dexprint Investments; 1st Respondent: Ace Property & Investments (Private) Limited; 2nd Respondent: Pauline Dorothy Hardy; 3rd Respondent: Valuequest Investments Holding (Private) Limited; 4th Respondent: Registrar of Deeds
Court
Harare High Court
Jurisdiction
Zimbabwe
Case Number
HH 48 of 2004
Procedural Posture
Opposed Application / Judgment
Outcome
Issue of damages for breach of contract referred to trial.
Legal Topics
Breach of Contract, Specific Performance, Damages, Lis Alibi Pendens, Notice Requirements
Source Language
en
Contract Law Civil Procedure Breach of Contract Specific Performance Damages Lis Alibi Pendens Notice Requirements

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 2 Party arguments 2 Amounts and remedies 5
Sign in to unlock

Parties

Dexprint Investments

Applicant

Ace Property & Investments (Private) Limited

1st Respondent

Pauline Dorothy Hardy

2nd Respondent

Valuequest Investments Holding (Private) Limited

3rd Respondent

Registrar of Deeds

4th Respondent

Procedural Posture

Opposed Application / Judgment

  1. 1 Whether the contract between applicant and first respondent was validly cancelled
  2. 2 Whether proper notice of breach was given in terms of the agreement
  3. 3 Whether the plea of lis alibi pendens applies

Ratio Decidendi

The purported cancellation of the agreement by the first respondent was premature as the required notice period had not expired; therefore, the first respondent was in breach of contract. The issue of damages for breach is referred to trial.

Court Disposition

Issue of damages for breach of contract referred to trial.

Orders

  • The issue of damages for breach of contract is referred to trial.