Hwange Colliery Co. (Pvt) Ltd. v Barzem Enterprises (Pvt) Ltd. & Ors (HC 5262 of 2016; HC 931 of 2015; HH 335 of 2016; Ref HC 6985 of 2015) [2016] ZWHHC 335 (6 September 2016)

Hwange Colliery Co. (Pvt) Ltd. v Barzem Enterprises (Pvt) Ltd. & Ors (HC 5262 of 2016; HC 931 of 2015; HH 335 of 2016; Ref HC 6985 of 2015) [2016] ZWHHC 335 (6 September 2016)

The matter was urgent as irreparable prejudice would result if execution proceeded before the scheme of arrangement application was heard. The applicant provided a rational explanation for delay and no adequate alternative remedy existed. The requirements for an interim interdict were met on a prima facie basis.

Source-derived case information.

Citation
[2016] ZWHHC 335
Parties
Applicant: Hwange Colliery Company Limited; 1st Respondent: Barzem Enterprises Private Limited; 2nd Respondent: Hethimex South Africa; 3rd Respondent: Petrotrade Private Limited; 4th Respondent: Alfred Moyo; 5th Respondent: Sakunda Petroleum Private Limited; 6th Respondent: Peter Mationi; 7th Respondent: Shamiso Ncube; 8th Respondent: Shepherd Mpande; 9th Respondent: Elton Mpofu; 10th Respondent: Nyemani Ncube; 11th Respondent: Bradford Investments Private Limited t/a Bradford Lubricants; 12th Respondent: Liteng Sibanda & 15 Ors; 13th Respondent: Jacob Bethel Corporation Private Limited; 14th Respondent: Deputy Sheriff Hwange District; 15th Respondent: The Sheriff N.O.
Court
Harare High Court
Jurisdiction
Zimbabwe
Case Number
HC 5262 of 2016 ; HC 931 of 2015 ; HH 335 of 2016 ; Ref HC 6985 of 2015
Procedural Posture
Urgent Chamber Application / Interim Application for Stay of Execution Pending Determination of Scheme of Arrangement
Outcome
Application for interim interdict granted
Legal Topics
Urgency in Applications, Stay of Execution, Scheme of Arrangement, Interim Interdicts
Source Language
en
Insolvency Civil Procedure Company Law Urgency in Applications Stay of Execution Scheme of Arrangement Interim Interdicts

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 13 Party arguments 2 Amounts and remedies 4
Sign in to unlock

Parties

Hwange Colliery Company Limited

Applicant

Barzem Enterprises Private Limited

1st Respondent

Hethimex South Africa

2nd Respondent

Petrotrade Private Limited

3rd Respondent

Alfred Moyo

4th Respondent

Sakunda Petroleum Private Limited

5th Respondent

Peter Mationi

6th Respondent

Shamiso Ncube

7th Respondent

Shepherd Mpande

8th Respondent

Elton Mpofu

9th Respondent

Nyemani Ncube

10th Respondent

Bradford Investments Private Limited t/a Bradford Lubricants

11th Respondent

Liteng Sibanda & 15 Ors

12th Respondent

Jacob Bethel Corporation Private Limited

13th Respondent

Deputy Sheriff Hwange District

14th Respondent

The Sheriff N.O.

15th Respondent

Procedural Posture

Urgent Chamber Application / Interim Application for Stay of Execution Pending Determination of Scheme of Arrangement

  1. 1 Whether the application met the requirements of urgency
  2. 2 Whether an interim interdict to stay execution should be granted pending determination of scheme of arrangement

Ratio Decidendi

The matter was urgent as irreparable prejudice would result if execution proceeded before the scheme of arrangement application was heard. The applicant provided a rational explanation for delay and no adequate alternative remedy existed. The requirements for an interim interdict were met on a prima facie basis.

Court Disposition

Application for interim interdict granted

Orders

  • Sale in execution of applicant's property stayed pending determination of application for scheme of arrangement
  • Costs to be in the cause