Hwange Colliery Company Ltd. v Ele Resources (Pvt) Ltd. & Anor (HC 5601 of 2010) [2015] ZWHHC 763 (30 September 2015)

Hwange Colliery Company Ltd. v Ele Resources (Pvt) Ltd. & Anor (HC 5601 of 2010) [2015] ZWHHC 763 (30 September 2015)

The second defendant is liable to pay interest at the prescribed rate on the guaranteed sum from 25 February 2010, as the principal debtor's acceptance of liability is binding on the surety and there is no exemption from interest in the surety agreement.

Source-derived case information.

Citation
[2015] ZWHHC 763
Parties
Plaintiff: Hwange Colliery Company Limited; 1st Defendant: ELE Resources (Private) Limited; 2nd Defendant: Alliance Insurance Company (Private) Limited
Court
Harare High Court
Jurisdiction
Zimbabwe
Case Number
HC 5601 of 2010
Procedural Posture
Civil / Trial Judgment
Outcome
judgment for plaintiff
Legal Topics
Guarantee Liability, Interest on Judgment Debt, Joint and Several Liability
Source Language
en
Contract Suretyship Guarantee Liability Interest on Judgment Debt Joint and Several Liability

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

Hwange Colliery Company Limited

Plaintiff

ELE Resources (Private) Limited

1st Defendant

Alliance Insurance Company (Private) Limited

2nd Defendant

Procedural Posture

Civil / Trial Judgment

  1. 1 Whether the second defendant is liable to pay interest on the guaranteed sum
  2. 2 From what date interest should be calculated on the guaranteed sum

Ratio Decidendi

The second defendant is liable to pay interest at the prescribed rate on the guaranteed sum from 25 February 2010, as the principal debtor's acceptance of liability is binding on the surety and there is no exemption from interest in the surety agreement.

Court Disposition

judgment for plaintiff

Orders

  • 1st and 2nd defendants jointly and severally to pay plaintiff US$588,733.00, with 2nd defendant's liability limited to US$300,000.00 plus interest at 5% per annum from 25 February 2010 to payment in full.
  • 1st defendant to pay interest on US$288,733.00 at 5% per annum from 25 February 2010 to payment in full.