International (Pvt) Ltd v Kembo & Anor (HH 199 of 2003) [2003] ZWHHC 199 (25 November 2003)

International (Pvt) Ltd v Kembo & Anor (HH 199 of 2003) [2003] ZWHHC 199 (25 November 2003)

The court found the first defendant's evidence untruthful and accepted the plaintiff's version that the first defendant negligently attempted to overtake when there was insufficient room, causing the collision. The damages claimed were supported by credible evidence and found to be fair and reasonable.

Source-derived case information.

Citation
[2003] ZWHHC 199
Parties
Plaintiff: International (Private) Limited; First Defendant: Grant Kembo; Second Defendant: Post and Telecommunications Corporation
Court
Harare High Court
Jurisdiction
Zimbabwe
Case Number
HH 199 of 2003
Procedural Posture
Civil / Judgment
Outcome
judgment for plaintiff
Legal Topics
Negligence, Motor Vehicle Accident, Damages
Source Language
en
Tort Civil Liability Negligence Motor Vehicle Accident Damages

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

International (Private) Limited

Plaintiff

Grant Kembo

First Defendant

Post and Telecommunications Corporation

Second Defendant

Procedural Posture

Civil / Judgment

  1. 1 Whether the first defendant was negligent in causing the collision
  2. 2 Whether the damages claimed by the plaintiff were fair and reasonable

Ratio Decidendi

The court found the first defendant's evidence untruthful and accepted the plaintiff's version that the first defendant negligently attempted to overtake when there was insufficient room, causing the collision. The damages claimed were supported by credible evidence and found to be fair and reasonable.

Court Disposition

judgment for plaintiff

Orders

  • Defendants to pay the plaintiff jointly and severally the sum of $204,384.59, one paying the other to be absolved.
  • Interest at the prescribed rate from 7 March 2002 to the date of final payment.