The court found that a verbal contract existed for the provision of a telelogger at Erin estate and that the plaintiff was entitled to $39,000 for six months' service. The court also found the written contract was prematurely terminated by the defendant without proper notice, entitling the plaintiff to $13,982 for...

Source-derived case information.

Citation
[2017] ZWHHC 42
Parties
Plaintiff: Lamp Distributors [Private] Limited; Defendant: Allied Timbers Zimbabwe [Private] Limited
Court
Harare High Court
Jurisdiction
Zimbabwe
Case Number
HC 5342 of 2015 ; HH 42 of 2017
Procedural Posture
Civil Trial / Judgment
Outcome
judgment for the plaintiff in part
Legal Topics
Breach of Contract, Damages, Verbal Contract, Written Contract, Quantum of Damages
Source Language
en
Contract Law Breach of Contract Damages Verbal Contract Written Contract Quantum of Damages

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Party arguments 2 Amounts and remedies 4
Sign in to unlock

Parties

Lamp Distributors [Private] Limited

Plaintiff

Allied Timbers Zimbabwe [Private] Limited

Defendant

Procedural Posture

Civil Trial / Judgment

  1. 1 Whether there was a verbal contract for provision of telelogger at Erin estate from August 2012 to January 2013 and if so, whether payment is due.
  2. 2 Whether the written contract for provision of teleloggers at Erin and Stappleford estates was breached and if so, what sums are due.
  3. 3 Whether the plaintiff is entitled to damages for unlawful termination of contract.

Ratio Decidendi

The court found that a verbal contract existed for the provision of a telelogger at Erin estate and that the plaintiff was entitled to $39,000 for six months' service. The court also found the written contract was prematurely terminated by the defendant without proper notice, entitling the plaintiff to $13,982 for services rendered under the written contract. The plaintiff failed to prove damages for breach, so no award was made under that head. The plaintiff was awarded a total of $52,982 plus interest and one third of its costs.

Court Disposition

judgment for the plaintiff in part

Orders

  • Defendant to pay plaintiff $52,982 with interest at 5% per annum from date of judgment to date of payment.
  • Defendant to pay one third of plaintiff's costs of suit.