Midlands State University v Galaxy Engineering Design Consultants (Private) Limited (127 of 2021) [2021] ZWSC 127 (1 November 2021)

Midlands State University v Galaxy Engineering Design Consultants (Private) Limited (127 of 2021) [2021] ZWSC 127 (1 November 2021)

The High Court erred in granting judgment denominated in United States dollars contrary to Statutory Instrument 33/19; the respondent had completed its contractual obligations prior to cessation of work and was entitled to payment in local currency with interest; the doctrine of fictional fulfilment applied as the...

Source-derived case information.

Citation
[2021] ZWSC 127
Parties
Appellant: Midlands State University; Respondent: Galaxy Engineering Design Consultants (Private) Limited
Court
Supreme Court of Zimbabwe
Jurisdiction
Zimbabwe
Case Number
127 of 2021
Procedural Posture
Civil Appeal / Supreme Court Judgment on Appeal From High Court
Outcome
Appeal partially succeeds; judgment of High Court amended; each party to bear its own costs.
Legal Topics
Suspensive Conditions, Interest on Judgment Debts, Currency Conversion, Factual Findings on Completion of Contractual Obligations
Source Language
en
Contract Law Civil Procedure Suspensive Conditions Interest on Judgment Debts Currency Conversion Factual Findings on Completion of Contractual Obligations

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 6 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

Midlands State University

Appellant

Galaxy Engineering Design Consultants (Private) Limited

Respondent

Procedural Posture

Civil Appeal / Supreme Court Judgment on Appeal From High Court

  1. 1 Whether the High Court erred in granting judgment denominated in United States dollars contrary to Statutory Instrument 33/19
  2. 2 Whether the High Court erred in awarding interest on the sum of US$84,827.17
  3. 3 Whether the High Court erred in finding that the respondent had completed all contractual obligations as at the date of cessation of work

Ratio Decidendi

The High Court erred in granting judgment denominated in United States dollars contrary to Statutory Instrument 33/19; the respondent had completed its contractual obligations prior to cessation of work and was entitled to payment in local currency with interest; the doctrine of fictional fulfilment applied as the appellant frustrated the suspensive condition; interest on the sum of $84,827.17 was properly awarded as it was an agreed issue.

Court Disposition

Appeal partially succeeds; judgment of High Court amended; each party to bear its own costs.

Orders

  • The appeal partially succeeds with each party to bear its own costs.
  • The judgment of the court a quo is amended by the deletion of paragraphs 1 and 2 and their substitution with: 1. Interest on the sum of RTGS$84,827.17 at the rate of 19.5% per annum from 1 November 2010 to the date that sum was paid. 2. RTGS$3,207,450.68 together with interest thereon at the rate of 19.5% per annum...