Nehanda Housing Co-operative Society Limited v Harare City Council (748 of 2022) [2022] ZWHHC 748 (19 October 2022)

Nehanda Housing Co-operative Society Limited v Harare City Council (748 of 2022) [2022] ZWHHC 748 (19 October 2022)

Section 282(2)(b) of the Urban Councils Act requires only the payment of all outstanding rates and charges for the issuance of a Rates Clearance Certificate; a certificate of compliance is not a statutory prerequisite. The defendant's refusal to issue the certificate was unlawful.

Source-derived case information.

Citation
[2022] ZWHHC 748
Parties
Plaintiff: Nehanda Housing Co-operative Society Limited; Defendant: Harare City Council
Court
Harare High Court
Jurisdiction
Zimbabwe
Case Number
748 of 2022
Procedural Posture
Civil / Trial Stated Case
Outcome
judgment for the plaintiff
Legal Topics
Rates Clearance Certificate, Statutory Interpretation, Land Development Compliance
Source Language
en
Local Government Law Property Law Rates Clearance Certificate Statutory Interpretation Land Development Compliance

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 9 Party arguments 2
Sign in to unlock

Parties

Nehanda Housing Co-operative Society Limited

Plaintiff

Harare City Council

Defendant

Procedural Posture

Civil / Trial Stated Case

  1. 1 Whether the plaintiff complied with s 282(2)(b) of the Urban Councils Act [Chapter 29:15]
  2. 2 Whether the defendant's refusal to issue a Rates Clearance Certificate was lawful
  3. 3 Whether the defendant should be compelled to issue the Rates Clearance Certificate

Ratio Decidendi

Section 282(2)(b) of the Urban Councils Act requires only the payment of all outstanding rates and charges for the issuance of a Rates Clearance Certificate; a certificate of compliance is not a statutory prerequisite. The defendant's refusal to issue the certificate was unlawful.

Court Disposition

judgment for the plaintiff

Orders

  • The defendant is ordered to issue the plaintiff with a rate clearance certificate in respect to the properties with Deed of Transfer Numbers 2092/09, 2148/09 and 2021/19 within 21 days of this order.
  • Costs will follow the suit.