Sundew Green (Private) Limited v Kagona and Another (643 of 2021) [2021] ZWHHC 643 (17 November 2021)

Sundew Green (Private) Limited v Kagona and Another (643 of 2021) [2021] ZWHHC 643 (17 November 2021)

The applicant, as owner of the property with permanent structures in existence prior to the respondent's mining activities, is entitled to protection under s 31 of the Act. The respondent did not obtain consent to mine within prohibited distances. The applicant has a clear right, reasonable apprehension of injury,...

Source-derived case information.

Citation
[2021] ZWHHC 643
Parties
Applicant: Sundew Green (Private) Limited; 1st Respondent: Goliath Kagona; 2nd Respondent: Provincial Mining Director
Court
Harare High Court
Jurisdiction
Zimbabwe
Case Number
643 of 2021
Procedural Posture
Opposed Application / Confirmation of Provisional Interdict
Outcome
Provisional order confirmed; final interdict granted against first respondent; costs awarded to applicant on ordinary scale.
Legal Topics
Interdicts, Proximity of Mining to Permanent Structures, Consent for Mining Activities
Source Language
en
Property Law Mining Law Interdicts Proximity of Mining to Permanent Structures Consent for Mining Activities

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 4 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Sundew Green (Private) Limited

Applicant

Goliath Kagona

1st Respondent

Provincial Mining Director

2nd Respondent

Procedural Posture

Opposed Application / Confirmation of Provisional Interdict

  1. 1 Whether the first respondent conducted mining activities within prohibited distances of applicant's permanent structures without consent
  2. 2 Whether the applicant is entitled to a final interdict under s 31 of the Mines and Minerals Act

Ratio Decidendi

The applicant, as owner of the property with permanent structures in existence prior to the respondent's mining activities, is entitled to protection under s 31 of the Act. The respondent did not obtain consent to mine within prohibited distances. The applicant has a clear right, reasonable apprehension of injury, and no alternative remedy. The provisional interdict is confirmed.

Court Disposition

Provisional order confirmed; final interdict granted against first respondent; costs awarded to applicant on ordinary scale.

Orders

  • The provisional order dated 9 January 2017 is confirmed.
  • The respondent and any persons acting on his behalf are interdicted from mining within 450 metres of the applicant’s homestead and 90 metres of the applicant’s cattle dip, spray race, shades, employees’ houses, and fowl runs.