Siwawa v Cooper Construction (Pvt) Ltd. (HC 2069 of 2015) [2015] ZWHHC 790 (14 October 2015)

Siwawa v Cooper Construction (Pvt) Ltd. (HC 2069 of 2015) [2015] ZWHHC 790 (14 October 2015)

The applicant lacked privity of contract and therefore could not seek cancellation. The respondent proved, on a balance of probabilities, that it supplied machinery and is entitled to the outstanding hire fee.

Citation
[2015] ZWHHC 790
Parties
Applicant: Symptoms Siwawa; Respondent: Cooper Construction (Pvt) Ltd
Court
Harare High Court
Jurisdiction
Zimbabwe
Judgment Date
14 October 2015
Case Number
HC 2069 of 2015
Procedural Posture
Opposed Application / Judgment
Outcome
Applicant's application dismissed; respondent's counter application allowed.
Legal Topics
Privity of Contract, Contract Cancellation, Hire of Machinery, Counterclaim
Source Language
English

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 2 Authorities cited 3 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

Symptoms Siwawa

Applicant

Cooper Construction (Pvt) Ltd

Respondent

Procedural Posture

Opposed Application / Judgment

  1. 1 Whether the applicant had locus standi to seek cancellation of the agreement
  2. 2 Whether the respondent is entitled to payment of outstanding hire fees

Ratio Decidendi

The applicant lacked privity of contract and therefore could not seek cancellation. The respondent proved, on a balance of probabilities, that it supplied machinery and is entitled to the outstanding hire fee.

Court Disposition

Applicant's application dismissed; respondent's counter application allowed.

Orders

  • Applicant's application dismissed with costs.
  • Applicant to pay respondent $39,374.50 with interest at the prescribed rate from 25 February 2015 to payment in full.