Trustees of the ARDA Transau Relocation Development Trust v ZETDC (HC 22 of 2020; HMT 29 of 2020) [2020] ZWMTHC 29 (4 April 2020)

Trustees of the ARDA Transau Relocation Development Trust v ZETDC (HC 22 of 2020; HMT 29 of 2020) [2020] ZWMTHC 29 (4 April 2020)

Given the declaration of COVID-19 as a national disaster and the classification of water and electricity as essential services, the applicants' lack of water due to electricity disconnection posed a serious threat to public health and hygiene. The urgency was not self-created, and interim relief was necessary to...

Source-derived case information.

Citation
[2020] ZWMTHC 29
Parties
Applicant: The Trustees of the Arda-Transau Relocation Development Trust; Respondent: Zimbabwe Electricity Transmission and Distribution Company (ZETDC) (Pvt) Ltd
Court
Mutare High Court
Jurisdiction
Zimbabwe
Case Number
HC 22 of 2020 ; HMT 29 of 2020
Procedural Posture
Urgent Chamber Application / Interim Relief Application
Outcome
Interim relief granted
Legal Topics
Urgency in Applications, Essential Services During Disaster, COVID 19 Emergency Measures, Electricity and Water Supply
Source Language
en
Administrative Law Public Health Law Urgency in Applications Essential Services During Disaster COVID 19 Emergency Measures Electricity and Water Supply

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 5 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

The Trustees of the Arda-Transau Relocation Development Trust

Applicant

Zimbabwe Electricity Transmission and Distribution Company (ZETDC) (Pvt) Ltd

Respondent

Procedural Posture

Urgent Chamber Application / Interim Relief Application

  1. 1 Whether the disconnection of electricity to water pumps during a declared state of disaster justifies urgent interim relief
  2. 2 Whether the applicants are entitled to restoration of electricity supply to access water during COVID-19 lockdown

Ratio Decidendi

Given the declaration of COVID-19 as a national disaster and the classification of water and electricity as essential services, the applicants' lack of water due to electricity disconnection posed a serious threat to public health and hygiene. The urgency was not self-created, and interim relief was necessary to prevent irreparable harm and support national efforts to contain the pandemic.

Court Disposition

Interim relief granted

Orders

  • The respondent is ordered to immediately restore electricity supply services to the Zimbabwe National Water Authority water pumps within Arda–Transau community for the duration of the state of disaster, subject to the load shedding schedule.
  • No order as to costs.