XARA (Pvt) Limited v LYNCHGATE Investments (Pvt) Ltd and 2 Others (414 of 2023) [2023] ZWHHC 353 (12 July 2023)

XARA (Pvt) Limited v LYNCHGATE Investments (Pvt) Ltd and 2 Others (414 of 2023) [2023] ZWHHC 353 (12 July 2023)

The 1st defendant breached the lease by failing to secure the correct commercial permit as required, entitling the plaintiff to damages. However, the plaintiff failed to mitigate its loss by not vacating after it became clear the correct permit would not be obtained, and is only entitled to damages up to the point...

Source-derived case information.

Citation
[2023] ZWHHC 353
Parties
Plaintiff: XARA (PVT) LIMITED; 1st Defendant: LYNCHGATE INVESTMENT (PVT) LTD; 2nd Defendant: MARJORIE NYANHEMWA; 3rd Defendant: MICHAEL GONDWE
Court
Harare High Court
Jurisdiction
Zimbabwe
Case Number
414 of 2023
Procedural Posture
Civil Lease Dispute / Judgment After Trial
Outcome
Partial judgment for both parties; set-off of monetary awards; eviction of plaintiff ordered.
Legal Topics
Lease Agreements, Breach of Contract, Damages, Eviction, Holding Over Damages, Arrear Rentals, Tacit Relocation
Source Language
en
Contract Law Landlord and Tenant Law Lease Agreements Breach of Contract Damages Eviction Holding Over Damages Arrear Rentals +1 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 17 Party arguments 2 Amounts and remedies 4
Sign in to unlock

Parties

XARA (PVT) LIMITED

Plaintiff

LYNCHGATE INVESTMENT (PVT) LTD

1st Defendant

MARJORIE NYANHEMWA

2nd Defendant

MICHAEL GONDWE

3rd Defendant

Procedural Posture

Civil Lease Dispute / Judgment After Trial

  1. 1 Whether the defendants breached the lease agreement by failing to secure the agreed permit and if so, whether the plaintiff suffered damages
  2. 2 Whether the plaintiff was entitled to exceed the agreed sum on renovations and if such was consented to
  3. 3 Whether the plaintiff is liable to pay arrear rentals and holding over damages

Ratio Decidendi

The 1st defendant breached the lease by failing to secure the correct commercial permit as required, entitling the plaintiff to damages. However, the plaintiff failed to mitigate its loss by not vacating after it became clear the correct permit would not be obtained, and is only entitled to damages up to the point it should have vacated. Renovation costs are limited to the agreed US$16,800. The plaintiff is liable for arrear rentals and holding over damages after lease expiry, and has no right to remain in occupation. Set-off applies between the parties' monetary claims.

Court Disposition

Partial judgment for both parties; set-off of monetary awards; eviction of plaintiff ordered.

Orders

  • Defendants to pay plaintiff US$79,800 as damages for breach of lease agreement.
  • Plaintiff to pay defendants US$194,400 as arrear rentals and holding over damages.