Placer Mining Act (Extraction de l’or)
This part sets up Yukon placer-mining administration, including mining districts, officials, recording rules, access to claims, and limits on claim size.
- Jurisdiction
- Canada — Yukon
- Instrument
- Act or statute
- Version
- Undated source snapshot
- Language
- en
- Official source
- View official record ↗
Statute overview
About this statute
This part sets up Yukon placer-mining administration, including mining districts, officials, recording rules, access to claims, and limits on claim size. This part sets claim size, staking, marking, filing, renewal, survey, abandonment, and relocation rules for placer claims. This part sets rules for water use, drainage, claim grouping, and related powers, rights, fees, deadlines, and appeals. This part sets rules for placer claims, prospecting leases, royalties on exported gold, enforcement, and entry restrictions on land. This Part sets rules for placer mining classes, notifications, operating plans, inspections, security, and enforcement.
Search within this statute
Search all stored provisions in this version.
Legal text
Provisions of Placer Mining Act (Extraction de l’or)
Showing 6 of 6
Part document.segment-1
Placer Mining Act (Extraction de l’or) — segment 1
- document.segment-1 Verify source ↗
Placer Mining Act (Extraction de l’or) — segment 1
This part sets up Yukon placer-mining administration, including mining districts, officials, recording rules, access to claims, and limits on claim size.
PLACER MINING ACT LOI SUR L’EXTRACTION DE L’OR SY 2003, c. 13 SY 2003, ch. 13 UNOFFICIAL CONSOLIDATION OF THE CODIFICATION NON OFFICIELLE DES STATUTES OF YUKON LOIS DU YUKON Placer Mining Act Loi sur l’extraction de l’or INFORMATION INFORMATION PLACER MINING ACT LOI SUR L’EXTRACTION DE L’OR SY 2003, c. 13; amended by SY 2013, c.18; LY 2003, ch. 13; modifiée par LY 2013, ch. 18; LY 2016, SY 2016, c.5; SY 2016, c.12; SY 2023, c.7 ch. 5; LY 2016, ch. 12; LY 2023, ch. 7 Please Note: This document, prepared by the Yukon Veuillez noter: ce document préparé par le Bureau Legislative Counsel Office, is an unofficial consolidation des conseillers législatifs du Yukon est une codification of this Act and includes any amendments to the Act administrative de la présente loi, laquelle comporte les that are in force and is current to: currency date. modifications à celle-ci qui sont en vigueur au : date en vigueur. For information concerning the date of assent or Pour l’information concernant la date de sanction ou la coming into force of the Act or any amendments, date d’entrée en vigueur de la loi, ou de ses please see the Table of Public Statutes and the Annual modifications, veuillez consulter le tableau des lois Acts on the laws.yukon.ca web site. Links to amending d’intérêt public et des lois annuelles sur le site web legislation, where appropriate, are provided at the end laws.yukon.ca. Des liens vers les lois modificatives, le of each section in this document. cas échéant, sont fournis à la fin de chaque article du présent document. If you find any errors or omissions in this Si vous trouvez des erreurs ou des oublis dans cette consolidation, please contact: codification, veuillez communiquer avec: Legislative Counsel Office le Bureau des conseillers législatifs Tel: (867) 667-8405 Tél: (867) 667-8405 Email: lco@gov.yk.ca courriel: lco@gov.yk.ca UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON c Placer Mining Act Loi sur l’extraction de l’or TABLE OF CONTENTS TABLE DES MATIÈRES TABLE OF CONTENTS (TABLE DES MATIÈRES) PLACER MINING ACT LOI SUR L’EXTRACTION DE L’OR TABLE OF CONTENTS TABLE DES MATIÈRES Section Page Article Page 1 Definitions ............................................................... 1 1 Définitions ............................................................... 1 PART 1 PARTIE 1 DISPOSITION OF GOVERNMENT PLACER MINING CESSION DES DROITS DU GOUVERNEMENT SUR RIGHTS L’EXPLOITATION DES PLACERS 2 Definitions ............................................................... 1 2 Définitions ............................................................... 1 3 Mining officials ........................................................ 3 3 Fonctionnaires des exploitations minières ................ 3 4 Mining districts ....................................................... 3 4 Districts miniers ...................................................... 3 5 Jurisdiction of Minister ............................................ 3 5 Compétence du ministre .......................................... 3 6 Mining recorder ...................................................... 4 6 Registraire minier .................................................... 4 7 Books kept by mining recorder ................................ 4 7 Livres tenus par le registraire minier ....................... 4 8 Date of entry ........................................................... 4 8 Date de chaque inscription ....................................... 4 9 Books open to public ............................................... 5 9 Livres ouverts au public ........................................... 5 10 Certified copies as evidence .................................... 5 10 Copies conformes font foi ........................................ 5 11 Fees ........................................................................ 5 11 Droits ...................................................................... 5 12 Money deposits ....................................................... 5 12 Dépôts de deniers .................................................... 5 13 Monthly statement .................................................. 5 13 Relevé mensuel ........................................................ 5 14 Jurisdiction of mining inspector .............................. 5 14 Juridiction de l’inspecteur ........................................ 5 15 Summary powers of inspector ................................. 6 15 Pouvoirs que l’inspecteur peut exercer 16 Examination of claims and mines ............................ 6 sommairement ........................................................ 6 17 Right to acquire claims ........................................... 6 16 Examen des claims et des mines .............................. 6 18 Security for damages .............................................. 7 17 Droit d’acquérir des claims ...................................... 6 19 Compensation ......................................................... 7 18 Caution pour dommages .......................................... 7 20 Nature and size of claims ........................................ 8 19 Indemnisation ......................................................... 7 21 Claims elsewhere than on a creek ........................... 8 20 Nature et dimensions des claims .............................. 8 22 Claims fronting on a creek ...................................... 8 21 Claims ailleurs que sur un ruisseau .......................... 8 23 How measured ........................................................ 8 22 Claims qui font face à un ruisseau ........................... 8 24 Form of claims ........................................................ 9 23 Mesurage horizontal ................................................ 8 25 Size of discovery claims ........................................ 10 24 Forme des claims ..................................................... 9 26 Extension of boundaries of claim ........................... 10 25 Dimension des claims découverts........................... 10 27 Forms ................................................................... 10 26 Extension des limites des claims ............................ 10 28 Time allowed ......................................................... 10 27 Formulaires ........................................................... 10 29 Part of claim already recorded .............................. 11 28 Temps accordé ...................................................... 10 29 Partie d’un claim déjà inscrit ................................. 11 c UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON Page i Placer Mining Act Loi sur l’extraction de l’or TABLE OF CONTENTS TABLE DES MATIÈRES 30 Location on Sunday ............................................... 11 30 Établissement de claim le dimanche ...................... 11 31 When claims one hundred miles from mining 31 Registraire d’urgence ............................................ 11 recorder‘s office .................................................... 11 32 Notification des demandes .................................... 11 32 Notification of applications .................................... 11 33 Permis aux prospecteurs ....................................... 12 33 Permits to prospectors .......................................... 12 34 Le requérant doit avoir personnellement 34 Claim to be staked by applicant in person .............. 12 délimité un claim .................................................. 12 35 Abandonment and surrender of claim .................... 12 35 Abandon et remise de claims ................................ 12 36 Limitation .............................................................. 13 36 Limites .................................................................. 13 37 Substitute of mining recorder ................................ 13 37 Remplaçant du registraire minier .......................... 13 38 Tagging of claims .................................................. 13 38 Apposition d’étiquettes .......................................... 13 39 Survey of claims .................................................... 13 39 Arpentage de claims .............................................. 13 40 Surveys ................................................................. 15 40 Arpentages ............................................................ 15 41 Title ....................................................................... 15 41 Titre ...................................................................... 15 42 Forfeiture of claim ................................................. 16 42 Déchéance du claim .............................................. 16 43 When owner does not renew.................................. 17 43 Quand le propriétaire ne renouvelle pas ................ 17 44 Contesting title ...................................................... 18 44 Contestation de titre .............................................. 18 45 Proportionate contribution ..................................... 18 45 Contribution proportionnelle .................................. 18 46 When claim disposed of ......................................... 18 46 Quand un claim est cédé ....................................... 18 47 Agreements affecting title ...................................... 19 47 Conventions qui touchent au titre .......................... 19 48 Right of grantee .................................................... 19 48 Droit du cessionnaire ............................................ 19 49 Rights of owner ..................................................... 20 49 Droits du propriétaire ........................................... 20 50 When evidence of location lost ............................... 20 50 Lorsque les marques de l’établissement 51 Claims of service personnel ................................... 21 disparaissent ......................................................... 20 52 Owners of adjoining claims.................................... 21 51 Claims du personnel militaire ................................ 21 53 Renewing of grouped claims on the same day ....... 22 52 Propriétaires de claims adjacents .......................... 21 54 Rights of claim owner to water .............................. 22 53 Concessions rendues renouvelables le même 55 Grant of right to divert or use water ...................... 23 jour ....................................................................... 22 56 Notice of intention to apply for water grants.......... 23 54 Le propriétaire d’un claim a droit à l’eau ............... 22 57 Application for water grant .................................... 24 55 Quand le droit de détourner ou d’utiliser de 58 Adjudication of mining recorder ............................ 25 l’eau peut être concédé ......................................... 23 59 Powers of mining recorder .................................... 25 56 Préavis de demande de concessions 60 Waste or excess ..................................................... 25 hydrauliques ......................................................... 23 61 Rights saved .......................................................... 26 57 Demande de concession hydraulique ..................... 24 62 Water rights of owners of claims ........................... 26 58 Décision du registraire minier ............................... 25 63 Distribution of water ............................................. 27 59 Pouvoirs du registraire minier ............................... 25 64 Rules for measurement of water............................ 27 60 Gaspillage ou excès ............................................... 25 65 Construction of culverts ......................................... 27 61 Droits sauvegardés................................................ 26 66 Duty of owner ........................................................ 28 62 Quantité d’eau à laquelle a droit l’exploitant d’un claim ............................................................. 26 67 Liability of owners ................................................. 28 63 Distribution de l’eau .............................................. 27 68 Transfer includes water privileges ......................... 28 64 Règles à observer pour le mesurage de l’eau ......... 27 69 Ground for reservoirs ............................................ 29 65 Construction de ponceaux ..................................... 27 70 Application of sections 54 to 69 ............................. 29 66 Devoirs du propriétaire ......................................... 28 71 Grant of right to run drains ................................... 29 67 Propriétaires responsables des dégâts ................... 28 72 Compensation ........................................................ 29 68 Transfert d’un claim et privilèges hydrauliques ..... 28 73 Property of constructor .......................................... 30 69 Terrain pour réservoir ........................................... 29 74 Application ............................................................ 30 70 Application des articles 54 à 69 ............................. 29 75 Form of grant ........................................................ 30 71 Droit d’établir des canaux d’écoulement ................ 29 76 Title ....................................................................... 31 72 Dédommagement .................................................. 29 77 Board of arbitrators ............................................... 31 73 Propriété de celui qui les construit ........................ 30 78 Damages by dumping, etc. .................................... 32 74 Demande .............................................................. 30 79 Judgement of the board ........................................ 33 75 Forme de la concession ......................................... 30 80 Costs of inquiry ..................................................... 33 76 Titres .................................................................... 31 Page ii UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON c Placer Mining Act Loi sur l’extraction de l’or TABLE OF CONTENTS TABLE DES MATIÈRES 81 Death or insanity of owner .................................... 34 77 Conseil d’arbitrage ................................................. 31 82 Powers of Minister over property .......................... 34 78 Dommages à d’autres claims, etc. ......................... 32 83 Charges and expenses ........................................... 35 79 Décision du conseil ................................................ 33 84 Assignee to apply for grant within two months ..... 35 80 Frais de l’enquête .................................................. 33 85 Royalty .................................................................. 36 81 Décès ou aliénation mentale du propriétaire .......... 34 86 Offence ................................................................. 36 82 Pouvoirs du ministre au sujet des biens ................. 34 87 Fees ...................................................................... 37 83 Frais et dépens ...................................................... 35 88 Moneys collected ................................................... 37 84 Le cessionnaire doit demander concession dans 89 Misrepresentation, removal of legal posts, etc. ...... 37 un délai de deux mois ............................................ 35 90 Punishment ........................................................... 38 85 Redevance ............................................................. 36 91 Application of Act .................................................. 38 86 Infraction............................................................... 36 92 Lease to prospect .................................................. 39 87 Droits .................................................................... 37 93 Application for lease of abandoned ground ............ 40 88 Deniers perçus ....................................................... 37 94 Evidence of expenditure ........................................ 41 89 Faux exposé, enlèvement de bornes légales, 95 Lessee may stake out claims ................................. 41 etc. ........................................................................ 37 96 Lease on creek or river not already prospected ..... 41 90 Peines .................................................................... 38 97 Fees ...................................................................... 42 91 Application de la loi................................................ 38 98 Order prohibiting entry ......................................... 42 92 Bail pour la recherche ............................................ 39 93 Demande de bail d’un terrain abandonné............... 40 PART 2 94 Preuve de la dépense ............................................. 41 LAND USE AND RECLAMATION 95 Le locataire peut marquer les claims ...................... 41 96 Bail sur ruisseau ou rivière non déjà exploré .......... 41 99 Interpretation ....................................................... 43 97 Droits .................................................................... 42 100 Purpose of Part 2 .................................................. 45 98 Décret interdisant l’entrée ..................................... 42 101 Classes of placer land use ...................................... 45 101.01 Special operating areas ......................................... 46 PARTIE 2 102 Classes 1 to 4 ........................................................ 46 UTILISATION ET REMISE EN ÉTAT DES TERRES 103 Designated Class 1 operations ............................... 48 104 Certificate of Completion ....................................... 49 99 Définitions ............................................................. 43 105 Form and Content of applications .......................... 50 100 Objet de la partie 2 ................................................ 45 106 Security may be required ...................................... 50 101 Types d’activités .................................................... 45 107 Minor amendments ............................................... 51 101.01 Zones spéciales d’exploitation ................................ 46 108 Operating plans ..................................................... 51 102 Types 1 à 4 ............................................................ 46 109 Minor amendments - Class 3 or 4 .......................... 52 103 Activités minières désignées de type 1 ................... 48 110 Assigning an approved operating plan ................... 52 104 Attestation d’achèvement des activités ................... 49 111 Inspectors and Chief ............................................. 52 105 Forme et teneur des demandes .............................. 50 112 Powers of inspectors ............................................. 53 106 Demande de garantie ............................................ 50 113 Directions by inspectors ........................................ 53 107 Modifications mineures .......................................... 51 114 Termination or abandonment ................................ 55 108 Renouvellement ..................................................... 51 115 Obstruction ........................................................... 56 109 Modification mineure ⎯ type 3 ou 4 ...................... 52 116 Regulations ........................................................... 56 110 Plan d’exploitation approuvé : cession.................... 52 117 Contraventions ...................................................... 59 111 Inspecteurs et directeur ......................................... 52 118 Limitation period ................................................... 60 112 Pouvoir .................................................................. 53 119 Action to enjoin not prejudiced .............................. 60 113 Instructions données par un inspecteur ................. 53 120 Language .............................................................. 60 114 Fermeture ou abandon .......................................... 55 115 Entrave .................................................................. 56 PART 3 116 Règlements ............................................................ 56 TRANSITIONAL PROVISIONS 117 Infractions ............................................................. 59 118 Prescription ........................................................... 60 121 Existing rights and duties continued ...................... 61 119 Injonction .............................................................. 60 122 Miners Lien Act amended ...................................... 61 120 Langues ................................................................. 60 123 Securities Act amended ......................................... 61 124 Workers’ Compensation Act amended .................... 62 PARTIE 3 c UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON Page iii Placer Mining Act Loi sur l’extraction de l’or TABLE OF CONTENTS TABLE DES MATIÈRES 125 Coming into force .................................................. 62 DISPOSITIONS TRANSITOIRES SCHEDULE 1 121 Droits existants ..................................................... 61 122 Modification à la Loi sur les privilèges miniers ....... 61 FORM 1 123 Modification à la Loi sur les valeurs mobilières ...... 61 APPLICATION FOR GRANT FOR PLACER MINING AND 124 Modification à la Loi sur les accidents du travail .... 62 AFFIDAVIT OF APPLICANT 125 Entrée en vigueur .................................................. 62 FORM 2 APPLICATION FOR RENEWAL OF GRANT FOR PLACER ANNEXE 1 MINING AND AFFIDAVIT OF APPLICANT FORMULAIRE 1 FORM 3 DEMANDE D’UNE CONCESSION D’UN CLAIM GRANT FOR PLACER MINING D’EXPLOITATION DE PLACER ET AFFIDAVIT DU FORM 4 REQUÉRANT GRANT OF RIGHT TO DIVERT WATER AND CONSTRUCT FORMULAIRE 2 DITCHES DEMANDE DE RENOUVELLEMENT DE LA CONCESSION FORM 5 D’UN CLAIM D’EXPLOITATION DE PLACER ET AFFIDAVIT TUNNEL OR DRAIN LICENCE DU REQUÉRANT FORM 6 FORMULAIRE 3 APPLICATION FOR A LEASE TO PROSPECT AND ACTE DE CONCESSION D’UN CLAIM D’EXPLOITATION DE AFFIDAVIT OF THE APPLICANT PLACER FORM 7 FORMULAIRE 4 GROUPING CERTIFICATE CONCESSION DU DROIT DE DÉTOURNER L’EAU ET DE SCHEDULE 2 CONSTRUIRE DES FOSSÉS FORMULAIRE 5 FEES PERMIS POUR CANAL SOUTERRAIN OU CONDUITE FORMULAIRE 6 DEMANDE D’UN BAIL DE PROSPECTION ET AFFIDAVIT DU REQUÉRANT FORMULAIRE 7 CERTIFICAT DE GROUPEMENT ANNEXE 2 DROITS Page iv UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON c Placer Mining Act Loi sur l’extraction de l’or PART 1 PARTIE 1 Section 1 Article 1 PLACER MINING ACT LOI SUR L’EXTRACTION DE L’OR The Commissioner of the Yukon, by and with the advice Le Commissaire du Yukon, sur l'avis et avec le and consent of the Legislative Assembly, enacts as consentement de l'Assemblée législative, édicte : follows 1 Definitions (Définitions) 1 Definitions 1 Définitions In this Act, La définition qui suit s’applique à la présente loi. “lands” means lands in respect of which the rights to « terres » Terres à l’égard desquelles les droits reliés à the gold or other precious minerals or stones are under l’or ou aux autres minéraux précieux ou pierres the administration and control of the Commissioner; précieuses sont sous la maîtrise et la gestion du « terres » Commissaire. “lands” [S.Y. 2003, c. 13, s. 1] [L.Y. 2003, ch. 13, art. 1] PART 1 (PARTIE 1) PART 1 PARTIE 1 DISPOSITION OF GOVERNMENT PLACER MINING RIGHTS (CESSION DES DROITS DU GOUVERNEMENT SUR L’EXPLOITATION DES PLACERS) DISPOSITION OF GOVERNMENT PLACER MINING CESSION DES DROITS DU GOUVERNEMENT SUR RIGHTS L’EXPLOITATION DES PLACERS 2 Definitions (Définitions) 2 Definitions 2 Définitions (1) In this Part, (1) Les définitions qui suivent s’appliquent à la présente partie. “base line” of a creek or river means a traverse line « borne légale » Pieu ayant d’un bout à l’autre un following the general direction of the centre bottom diamètre minimal de cinq pouces, une hauteur lands of the valley of the creek or river, surveyed and minimale de quatre pieds au-dessus du sol et deux established under the direction and with the approval faces planes sur au moins un pied à partir du sommet. of the Minister; « ligne de base » Ces deux faces planes doivent mesurer au moins quatre pouces de large. Sont inclus dans la présente définition “claim” means any parcel of land located or granted toute souche ou tout arbre coupé et aplati ou taillé à for placer mining, and “mining property” includes, faces selon la hauteur et les dimensions susdites. besides claims, any ditches or water rights used for “legal post” mining on the claim, and all other things belonging or used in the working of the claim for mining purposes; « claim » S’entend de tout lopin de terre localisé ou « claim » concédé pour l’exploitation d’un placer, et « propriété minière » ou « terrain minier » s’entend, outre des “creek” means all natural watercourses, whether claims, de tous les fossés ou les droits de prise d’eau usually containing water or not, and that portion of any c UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON Page 1 Placer Mining Act Loi sur l’extraction de l’or PART 1 PARTIE 1 Section 2 Article 2 stream below the point where it enters the valley of the qui servent à l’exploitation des claims, et de toutes parent stream, but does not include streams that have autres choses qui en relèvent ou sont employées dans an average width of one hundred and fifty feet; leur exploitation pour des fins minières. “claim” « ruisseau » « exploitation » ou « exploitation d’un placer » Tout “ditch” includes a flume, pipe, race, or other artificial mode et toute méthode d’exploitation par lesquels de la means for conducting water by its own weight, to be terre, du sol, du gravier ou du ciment peuvent être used for mining purposes; « fossé » enlevés, lavés, déplacés ou affinés ou autrement traités pour l’extraction de l’or ou d’autres minéraux précieux “legal post” means a stake having a diameter ou pierres précieuses. La présente définition exclut throughout of not less than five inches, standing not l’exploitation de la roche en place. “mining” ou “placer less than four feet above the ground and flattened on mining” two sides for at least one foot from the top, each of the sides so flattened measuring at least four inches across « fossé » Sont assimilés à un fossé toute conduite the face, and includes any stump or tree cut off and d’amenée d’eau, tout tuyau, coursier ou autre moyen flattened or faced to that height and size; « borne artificiel par lequel de l’eau destinée à servir à des fins légale » d’exploitation est amenée par sa propre gravité. “ditch” “mine” means any natural stratum or bed of earth, « inspecteur des exploitations minières » Inspecteur soil, gravel, or cement that is mined for gold or other des exploitations minières nommé aux termes de la precious minerals or stones; « mine » présente partie. “mining inspector” “mining” or “placer mining” includes every mode and « ligne de base » À l’égard d’un ruisseau ou d’une method of working whatever whereby earth, soil, rivière, ligne d’exploration arpentée et établie sous la gravel, or cement may be removed, washed, shifted, or direction et avec l’approbation du ministre qui suit la refined or otherwise dealt with, for the purpose of direction générale des basses terres centrales de la obtaining gold or other precious minerals or stones, vallée du ruisseau ou de la rivière. “base line” but does not include the working of rock on the site; « mine » Toute couche ou tout lit naturel de terre, de « exploitation » or « exploitation d’un placer » gravier ou de ciment creusé pour l’extraction de l’or ou “mining inspector” means a mining inspector d’autres minéraux précieux ou pierres précieuses. appointed under this Part; « inspecteur des “mine” exploitations minières » « registraire minier » Registraire minier nommé aux “mining recorder” means a mining recorder appointed termes de la présente partie. “mining recorder” under this Part. « registraire minier » « ruisseau » Tous cours d’eau naturels, qu’ils contiennent ordinairement de l’eau ou non, et la partie de tout cours d’eau en aval de l’endroit où ce cours d’eau pénètre dans la vallée du cours d’eau principal, à l’exclusion des cours d’eau d’une largeur moyenne de 150 pieds. “creek” (2) Nothing contained in this Part shall be construed as (2) La présente partie n’a pas pour effet de restreindre limiting the right of the Commissioner, from time to le droit du Commissaire d’établir, au besoin et sans time, to lay out public roads across, through, along or indemnité, des voies publiques en travers, le long ou under any claim, ditch, or water privilege, without au-dessous de claims, de fossés ou de concessions compensation. hydrauliques. Page 2 UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON c Placer Mining Act Loi sur l’extraction de l’or PART 1 PARTIE 1 Section 3 Article 3 (3) Despite anything in this Part, this Part does not (3) Malgré les autres dispositions de la présente partie, apply to any lands demised or leased for hydraulic ses dispositions ne s’appliquent pas aux terres aliénées mining purposes by any lease granted before August 1, ou louées pour exploitation minière par l’hydraulique 1906 that has been cancelled before that day or that is en vertu d’un bail consenti avant le ler août 1906, qui a thereafter cancelled under the Yukon Placer Mining Act été annulé avant cette date ou qui l’est en vertu de la (Canada), until those lands have been brought under Loi sur l’extraction de l’or dans le Yukon (Canada), tant this Part by order of the Commissioner in Executive que ces terres n’ont pas été assujetties à ces Council or unless those lands were brought under Part I dispositions par décret du commissaire en conseil of the Yukon Placer Mining Act (Canada). exécutif, à moins qu’elles leur aient été assujetties en vertu de la partie I de la Loi sur l’extraction de l’or dans le Yukon (Canada). (4) Nothing in this Part prevents the Commissioner in (4) La présente partie n’a pas pour effet d’empêcher le Executive Council making regulations under which commissaire en conseil exécutif de prendre des dredging leases may be issued for the whole bed of any règlements permettant que soient délivrés des baux de river in the Yukon. dragage relatifs au lit tout entier de toute rivière du Yukon. (5) This Part shall be construed as being subject to (5) La présente partie est assujettie à la partie 2 et à Part 2 and the regulations made under it, to the extent ses règlements dans la mesure où cette partie et ses that the provisions of Part 2 and of the regulations règlements s'appliquent aux terres en question. made thereunder apply in respect of the lands in question. [S.Y. 2003, c. 13, s. 2] [L.Y. 2003, ch. 13, art. 2] 3 Mining officials (Fonctionnaires des exploitations minières) 3 Mining officials 3 Fonctionnaires des exploitations minières Mining recorders, mining inspectors, deputy mining Des registraires miniers, inspecteurs des exploitations recorders, and deputy mining inspectors shall be minières, registraires miniers adjoints et inspecteurs appointed under the Public Service Act for the purpose adjoints des exploitations minières sont nommés en of carrying out this Part. vertu de la Loi sur la fonction publique pour l’application de la présente partie. [S.Y. 2003, c. 13, s. 3] [L.Y. 2003, ch. 13, art. 3] 4 Mining districts (Districts miniers) 4 Mining districts 4 Districts miniers The Commissioner in Executive Council may, by Le commissaire en conseil exécutif peut, par regulation, divide the Yukon into districts to be known règlement, diviser le Yukon en districts qui seront as mining districts, and may, as occasion requires, connus sous le nom de districts miniers et il peut en change the boundaries of those districts. changer les limites. [S.Y. 2003, c. 13, s. 4] [L.Y. 2003, ch. 13, art. 4] 5 Jurisdiction of Minister (Compétence du ministre) 5 Jurisdiction of Minister 5 Compétence du ministre The Minister possesses all the powers and authority of Le ministre possède tous les pouvoirs et la pleine a mining recorder and mining inspector. autorité d’un registraire minier et d’un inspecteur des exploitations minières. [S.Y. 2003, c. 13, s. 5] [L.Y. 2003, ch. 13, art. 5] c UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON Page 3 Placer Mining Act Loi sur l’extraction de l’or PART 1 PARTIE 1 Section 6 Article 6 6 Mining recorder (Registraire minier) 6 Mining recorder 6 Registraire minier A mining recorder shall be appointed for each mining Un registraire minier est nommé dans chaque district district, and within that district the mining recorder minier et, dans les limites de ce district, il est investi possesses all the powers and authority of a mining de tous les pouvoirs et de la pleine autorité d’un inspector. inspecteur des exploitations minières. [S.Y. 2003, c. 13, s. 6] [L.Y. 2003, ch. 13, art. 6] 7 Books kept by mining recorder (Livres tenus par le registraire minier) 7 Books kept by mining recorder 7 Livres tenus par le registraire minier (1) Every mining recorder shall keep the following (1) Tout registraire minier tient les livres suivants, books to be used for placer mining entries pour servir aux inscriptions d’exploitations de placers : (a) record of applications, a) un registre des demandes; (b) record of refused applications, b) un registre des demandes rejetées; (c) record book, c) un livre d’archives; (d) record of abandonments, and d) un registre des abandons; (e) record of documents received, e) un registre des documents reçus. and the mining recorder shall record all documents Il inscrit les documents, relatifs aux propriétés relating to mining property that are brought to him or minières, qui lui sont présentés pour être inscrits, et her for record and file all documents relating to claims classe tous les documents, relatifs à ces claims, qui lui that are brought to him or her to be filed. sont apportés en dépôt. (2) Where a caveat is filed against any claim, the (2) Lorsqu’une mise en garde est déposée à l’encontre caveat lapses unless, before the expiration of one d’un claim, elle devient nulle à moins que, avant month from the receipt of it by a mining recorder, l’expiration d’un mois à compter de sa réception par le proceedings in a court of competent jurisdiction have registraire minier, des procédures n’aient été prises been taken to establish the caveator’s title to the devant un tribunal compétent pour établir le titre de interests specified in the caveat. l’auteur de cette mise en garde à l’intérêt qui y est mentionné. (3) A caveat is any instrument claiming any interest (3) Une mise en garde est une pièce contenant la whatever in the claim with reference to which it is réclamation d’un intérêt quelconque dans le claim au filed, but does not include any instrument creating any sujet duquel elle est produite; mais elle ne comprend sale, mortgage, or other disposition of the property. pas un acte créant vente, hypothèque ou autre aliénation de la propriété. [S.Y. 2003, c. 13, s. 7] [L.Y. 2003, ch. 13, art. 7] 8 Date of entry (Date de chaque inscription) 8 Date of entry 8 Date de chaque inscription Every entry made in any of the books of a mining Toute inscription faite dans les livres du registraire recorder shall show the date on which the entry minier révèle la date à laquelle elle est faite. is made. [S.Y. 2003, c. 13, s. 8] [L.Y. 2003, ch. 13, art. 8] Page 4 UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON c Placer Mining Act Loi sur l’extraction de l’or PART 1 PARTIE 1 Section 9 Article 9 9 Books open to public (Livres ouverts au public) 9 Books open to public 9 Livres ouverts au public All books of record and documents filed in the office of Durant les heures de bureau, le public a gratuitement a mining recorder shall, during office hours, be open to accès à tous les registres et documents déposés au public inspection free of charge. bureau du registraire minier. [S.Y. 2003, c. 13, s. 9] [L.Y. 2003, ch. 13, art. 9] 10 Certified copies as evidence (Copies conformes font foi) 10 Certified copies as evidence 10 Copies conformes font foi Every copy of, or extract from, any entry in any of the Toutes copies ou tous extraits d’une inscription faite books of record, or of any document, filed in the office dans les registres, ou d’un document déposé au bureau of a mining recorder, certified by the mining recorder du registraire minier, doivent être acceptés par tout to be a true copy or extract, shall be admitted in any tribunal comme preuve des matières qu’ils contiennent, court as evidence of the matters contained in it. pourvu que le registraire minier ait certifié que ces copies ou extraits sont conformes. [S.Y. 2003, c. 13, s. 10] [L.Y. 2003, ch. 13, art. 10] 11 Fees (Droits) 11 Fees 11 Droits Before issuing any grant, making any entry in any book Avant de délivrer un acte de concession, de faire une of record, or filing any document, or making any copy inscription sur un registre ou de recevoir en dépôt un or extract, a mining recorder shall collect the fees document, ou d’en faire une copie ou un extrait, le payable according to Schedule 2. registraire minier doit percevoir les droits exigibles pour ces services, énoncés à l’annexe 2. [S.Y. 2003, c. 13, s. 11] [L.Y. 2003, ch. 13, art. 11] 12 Money deposits (Dépôts de deniers) 12 Money deposits 12 Dépôts de deniers A mining recorder shall receive all deposits of money Le registraire minier reçoit tous les dépôts de deniers directed by this Part to be made with him or her. que la présente partie enjoint de lui faire. [S.Y. 2003, c. 13, s. 12] [L.Y. 2003, ch. 13, art. 12] 13 Monthly statement (Relevé mensuel) 13 Monthly statement 13 Relevé mensuel A statement of the grants issued and fees collected by Tous les mois, au moins, le registraire minier fait a mining recorder shall be rendered to the Minister by rapport au ministre des actes de concession délivrés et the mining recorder at least once every month, and the des droits perçus, et ce rapport est accompagné des statement shall be accompanied by the amount deniers perçus, ou des certificats de dépôt si ces collected or, if the money has been deposited to the deniers ont été déposés au crédit du Commissaire. credit of the Commissioner, by the deposit receipts. [S.Y. 2003, c. 13, s. 13] [L.Y. 2003, ch. 13, art. 13] 14 Jurisdiction of mining inspector (Juridiction de l’inspecteur) 14 Jurisdiction of mining inspector 14 Juridiction de l’inspecteur A mining inspector has jurisdiction within such mining L’inspecteur des exploitations minières possède, dans districts as the Minister orders. les limites des districts miniers, la juridiction que le ministre détermine. [S.Y. 2003, c. 13, s. 14] [L.Y. 2003, ch. 13, art. 14] c UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON Page 5 Placer Mining Act Loi sur l’extraction de l’or PART 1 PARTIE 1 Section 15 Article 15 15 Summary powers of inspector (Pouvoirs que l’inspecteur peut exercer sommairement) 15 Summary powers of inspector 15 Pouvoirs que l’inspecteur peut exercer sommairement (1) A mining inspector may summarily order any (1) L’inspecteur des exploitations minières peut mining works to be so carried on as not to interfere ordonner sommairement que tous les travaux with, or endanger the safety of, the public, any d’exploitation soient exécutés de manière à ne pas employees of the mining works, any public work or gêner ou exposer la sécurité du public ou des ouvriers highway, or any mining property, mineral claim, bed- employés à ces travaux d’exploitation, ou d’un ouvrage rock drain or bed-rock flume. ou chemin public, ou d’une propriété minière, d’un claim minéral, d’un drain de roche de fond ou d’une conduite d’amenée de roche de fond. (2) A mining inspector may order that abandoned (2) Tous travaux abandonnés peuvent être, par ordre works be either filled up or guarded to the inspector’s de l’inspecteur des exploitations minières, comblés ou satisfaction. gardés à sa satisfaction. (3) Any person affected by an order of a mining (3) Toute personne visée par un ordre de l’inspecteur inspector under this section may, within ten days, des exploitations minières en exécution du présent appeal from it to the Minister. article peut, dans les dix jours, interjeter appel de cet ordre devant le ministre. [S.Y. 2003, c. 13, s. 15] [L.Y. 2003, ch. 13, art. 15] 16 Examination of claims and mines (Examen des claims et des mines) 16 Examination of claims and mines 16 Examen des claims et des mines The Minister, mining recorder, or mining inspector, or Le ministre, le registraire minier, l’inspecteur des a person authorised by any of them, may enter into or exploitations minières, ou toute personne désignée par on and examine any claim or mine. l’un d’eux, peut pénétrer dans ou aller sur tout claim ou toute mine et l’examiner. [S.Y. 2003, c. 13, s. 16] [L.Y. 2003, ch. 13, art. 16] 17 Right to acquire claims (Droit d’acquérir des claims) 17 Right to acquire claims 17 Droit d’acquérir des claims (1) Subject to this Act, any individual eighteen years of (1) Sous réserve des autres dispositions de la présente age or over, on their own behalf, on behalf of any loi, toute personne âgée d’au moins 18 ans peut, pour corporation authorized to carry on business in the son propre compte, pour le compte de toute personne Yukon, or on behalf of any other individual eighteen morale autorisée à faire des affaires au Yukon, ou pour years of age or over, may enter for mining purposes, le compte de toute autre personne âgée de 18 ans ou locate, prospect, and mine for gold and other precious plus, aller sur toutes les terres au Yukon, y localiser un minerals or stones on any lands in the Yukon. claim, y prospecter et creuser pour en extraire de l’or et d’autres minéraux précieux ou pierres précieuses. (2) Subsection (1) does not apply to lands (2) Le paragraphe (1) ne s’applique pas : (a) entry on which for the purpose of locating a a) aux terrains sur lesquels il est interdit d’aller claim or prospecting for gold or other precious aux fins de localiser un claim et de prospecter minerals or stones is prohibited by an order pour découvrir de l’or ou d’autres minéraux under section 98, except on the terms and précieux ou des pierres précieuses, par décret conditions, if any, set out in the order; pris en vertu de l’article 98, sauf conformément aux conditions éventuellement fixées dans le décret; (b) used as a cemetery or burial ground; b) aux terrains utilisés comme cimetière ou champ de sépulture; Page 6 UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON c Placer Mining Act Loi sur l’extraction de l’or PART 1 PARTIE 1 Section 18 Article 18 (c) lawfully occupied for placer mining purposes; c) aux terrains légalement occupés pour des fins d’exploitation de placers; (d) set apart and appropriated by the d) aux terrains réservés ou attribués au Commissioner in Executive Council to enable gouvernement du Yukon par le commissaire en the Government of the Yukon to fulfil its conseil exécutif afin que le gouvernement obligations under land claims settlements; s’acquitte de ses obligations en vertu des règlements sur les revendications territoriales; (e) within the boundaries of a city, town, or village, e) aux terrains compris dans les limites d’une ville as defined in the Municipal Act, unless under ou d’un village, tel que défini dans la Loi sur les regulations approved by the Commissioner in municipalités, sauf s’ils tombent sous le régime Executive Council; or de règlements approuvés par le commissaire en conseil exécutif; (f) occupied by a building or within the curtilage of f) aux terrains occupés par un bâtiment ou a dwelling-house. compris dans les limites de la dépendance d’une maison d’habitation. [S.Y. 2003, c. 13, s. 17] [L.Y. 2003, ch. 13, art. 17] 18 Security for damages (Caution pour dommages) 18 Security for damages 18 Caution pour dommages No person shall enter on for mining purposes or shall Nul ne peut, aux fins d’exploitation minière, pénétrer mine on lands owned or lawfully occupied by another dans des terrains possédés ou légalement occupés par person until adequate security is given, to the une autre personne, ni y creuser, sans avoir fourni une satisfaction of a mining recorder, for any loss or garantie jugée suffisante par le registraire minier pour damage that may be thereby caused. couvrir toute perte ou tout dommage pouvant résulter de ce fait. (2) Any dispute respecting a decision of the mining (2) À la demande soit de la personne tenue de fournir recorder under subsection (1) as to the security to be la garantie, soit du propriétaire ou de l’occupant given shall be heard and determined by the Yukon légitime du terrain, l’Office des droits de surface du Surface Rights Board in accordance with the Yukon Yukon tranche, en conformité avec la Loi sur l’Office Surface Rights Board Act (Canada) on application by des droits de surface du Yukon (Canada), tout différend the person who is to give the security or the owner or découlant de la décision rendue par le registraire lawful occupant of the lands. minier au sujet de la garantie à fournir. [S.Y. 2003, c. 13, s. 18] [L.Y. 2003, ch. 13, art. 18] 19 Compensation (Indemnisation) 19 Compensation 19 Indemnisation Persons locating, prospecting, entering on for mining Quiconque, aux fins d’exploitation minière, localise des purposes, or mining on lands owned or lawfully terrains possédés ou légalement occupés par une autre occupied by another person shall make full personne, qui y prospecte, qui y pénètre ou qui y compensation to the owner or occupant of the lands for creuse est tenu d’indemniser entièrement le any loss or damage so caused, which compensation, in propriétaire ou l’occupant de ces terrains de toute case of dispute, shall be determined by the Yukon perte ou de tout dommage ainsi causé. L’Office des Surface Rights Board in accordance with the Yukon droits de surface du Yukon tranche, en conformité avec Surface Rights Board Act (Canada). la Loi sur l’Office des droits de surface du Yukon (Canada), tout différend relatif à l’indemnité. [S.Y. 2003, c. 13, s. 19] [L.Y. 2003, ch. 13, art. 19] c UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON Page 7 Placer Mining Act Loi sur l’extraction de l’or PART 1 PARTIE 1 Section 20 Article 20 20 Nature and size of claims (Nature et dimensions des claims) 20 Nature and size of claims 20 Nature et dimensions des claims (1) A claim on a creek shall not exceed five hundred (1) Un claim situé sur un ruisseau ne peut feet in length, measured along the base line of the dépasser 500 pieds de long, mesurés le long de la ligne creek, established or to be established by a de base du ruisseau, établie ou à établir par un Government survey, as provided in this Part. arpentage officiel, tel qu’il est prescrit à la présente partie. (2) The side boundaries of a claim shall be lines on (2) Les limites latérales d’un claim sont des limites either side of the base line, parallel to it and one tirées de l’un ou de l’autre côté de la ligne de base. thousand feet distant from it. Elles lui sont parallèles et en sont éloignées de mille pieds.
Part document.segment-2
Placer Mining Act (Extraction de l’or) — segment 2
- document.segment-2 Verify source ↗
Placer Mining Act (Extraction de l’or) — segment 2
This part sets claim size, staking, marking, filing, renewal, survey, abandonment, and relocation rules for placer claims.
(3) The end boundaries of a claim shall be lines drawn (3) Les limites terminales du claim sont des lignes at each end of the claim, at right angles to the base tirées à chaque extrémité du claim, à angles droits line, and extending not more than one thousand feet on avec la ligne de base, et ne s’étendant pas à plus de either side of it. mille pieds de l’un ou de l’autre côté. (4) In the event that the base line of a claim is not (4) Si la ligne de base n’est pas établie, le claim peut established, the claim may be staked along the general être marqué suivant la direction générale de la vallée direction of the valley of the creek but, in that case, du ruisseau mais doit, dans ce cas, se conformer aux shall conform to the boundaries that the base line, limites que détermine la ligne de base quand celle-ci when established, defines. est établie. [S.Y. 2003, c. 13, s. 20] [L.Y. 2003, ch. 13, art. 20] 21 Claims elsewhere than on a creek (Claims ailleurs que sur un ruisseau) 21 Claims elsewhere than on a creek 21 Claims ailleurs que sur un ruisseau A claim situated elsewhere than on a creek shall not Un claim situé ailleurs que sur un ruisseau ne peut exceed five hundred feet in length, parallel to the base dépasser 500 pieds de long parallèlement à la ligne de line of the creek toward which it fronts, by one base du ruisseau vers lequel il fait face, sur mille pieds thousand feet. de large. [S.Y. 2003, c. 13, s. 21] [L.Y. 2003, ch. 13, art. 21] 22 Claims fronting on a creek (Claims qui font face à un ruisseau) 22 Claims fronting on a creek 22 Claims qui font face à un ruisseau A claim fronting on a creek or river shall be staked as Un claim qui fait face à un ruisseau ou à une rivière nearly as possible parallel to the general direction of doit être marqué, autant que possible, parallèlement à the valley of the creek or river and shall conform to the la direction générale de la vallée de ce ruisseau ou de boundaries that the base line, when established, cette rivière, et se conformer aux limites que defines. détermine la ligne de base quand celle-ci est établie. [S.Y. 2003, c. 13, s. 22] [L.Y. 2003, ch. 13, art. 22] 23 How measured (Mesurage horizontal) 23 How measured 23 Mesurage horizontal Claims shall be measured horizontally, irrespective of Les claims sont mesurés horizontalement, sans égard inequalities on the surface of the ground. aux inégalités de la surface du sol. [S.Y. 2003, c. 13, s. 23] [L.Y. 2003, ch. 13, art. 23] Page 8 UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON c Placer Mining Act Loi sur l’extraction de l’or PART 1 PARTIE 1 Section 24 Article 24 24 Form of claims (Forme des claims) 24 Form of claims 24 Forme des claims (1) Every claim on a creek shall be as nearly as (1) Tout claim situé sur un ruisseau doit être, autant possible rectangular in form and shall be marked by que possible, de forme rectangulaire et marqué de two legal posts firmly fixed in the ground on the base deux bornes légales solidement fixées au sol, sur la line at each end of the claim. ligne de base, à chaque extrémité du claim. (2) A claim situated elsewhere than on a creek shall be (2) Les claims situés ailleurs que sur un ruisseau as nearly as possible rectangular in form and shall be doivent être, autant que possible, de forme marked by two legal posts firmly fixed in the ground in rectangulaire et marqués de deux bornes solidement a line parallel to the base line and on the side nearest fixées au sol en une ligne parallèle à la ligne de base et the creek or river toward which it fronts. du côté le plus voisin du ruisseau auquel, ou de la rivière à laquelle, il fait face. (3) The line between the two legal posts shall be well (3) La ligne qui relie les deux bornes légales doit être cut out so that one post may, if the nature of the bien marquée, de sorte qu’une borne puisse être vue à surface permits, be seen from the other. partir de l’autre, si la nature de la surface du sol le permet. (4) One of the flattened sides of each legal post shall (4) Un des côtés aplatis de chaque borne légale doit face the claim, and on each post shall be written on the faire face au claim, et sur chaque borne doit être side facing the claim a legible notice stating the name lisiblement écrit, du côté qui fait face au claim, un avis or number of the claim, or both if possible, its length in énonçant le nom ou le numéro du claim, ou les deux si feet, the date when staked and the name of the locator possible, sa longueur en pieds, la date de sa of the claim. démarcation et le nom de la personne qui l’a localisé. (5) The legal posts shall be numbered 1 and 2 (5) Les bornes légales doivent être respectivement respectively, and it is not lawful to move them except numérotées 1 et 2, et il n’est pas permis de les that post No. 2 may be moved by a Canada Lands déplacer; la borne no 2 peut toutefois être déplacée par Surveyor if the distance between the posts exceeds the un arpenteur fédéral si la distance entre les deux length prescribed by this Part, but not otherwise. bornes excède la longueur prescrite par la présente partie, mais non autrement. (6) Despite anything contained in this Part, failure on (6) Malgré les autres dispositions de la présente partie, the part of a locator of a claim to comply with any of la négligence de la part du localisateur d’un claim de se the provisions of this section shall not be deemed to conformer à l’une des dispositions du présent article invalidate the location, if, on the facts, it appears to the n’est pas censée invalider sa localisation, si, selon les satisfaction of a mining recorder that there has been faits, il paraît, à la satisfaction du registraire minier, on the part of the locator an honest attempt to comply que le localisateur a, de bonne foi, essayé de se with this Part, and that the non-observance of the conformer à la présente partie, et que l’inobservation formalities referred to in this section is not of a des formalités mentionnées au présent article n’est pas character calculated to mislead other persons who de nature à induire en erreur d’autres personnes desire to locate claims in the vicinity. désireuses de localiser des claims dans le voisinage. [S.Y. 2003, c. 13, s. 24] [L.Y. 2003, ch. 13, art. 24] c UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON Page 9 Placer Mining Act Loi sur l’extraction de l’or PART 1 PARTIE 1 Section 25 Article 25 25 Size of discovery claims (Dimension des claims découverts) 25 Size of discovery claims 25 Dimension des claims découverts Any person or party of persons who locate the first Toute personne ou tout groupe de personnes qui claim on any creek, hill, bench, bar or plain, or who localise le premier claim dans un ruisseau, sur un locate a claim on any creek, hill, bench, bar or plain on coteau, une terrasse, dans une crevasse ou une plaine, which there is no recorded claim, is entitled to a claim ou qui localise un claim dans un ruisseau, sur un or claims respectively of the following size: coteau, une terrasse, dans une crevasse ou une plaine sur lesquels il n’y a pas de claims inscrits, a droit à un ou à plusieurs claims aux dimensions suivantes, respectivement : (a) one locator, one claim, fifteen hundred feet in a) un localisateur : un claim de 1 500 pieds length; and de long; b) a party of two or more locators, two claims, b) un groupe de deux localisateurs ou plus : deux each one thousand two hundred and fifty feet claims de 1 250 pieds de long chacun; et in length, and, for each member of the party chaque membre du groupe, en sus de deux : beyond two, a claim of the ordinary size only. un claim seulement aux dimensions ordinaires. [S.Y. 2003, c. 13, s. 25] [L.Y. 2003, ch. 13, art. 25] 26 Extension of boundaries of claim (Extension des limites des claims) 26 Extension of boundaries of claim 26 Extension des limites des claims The boundaries of any claim may, by order of the Les limites d’un claim peuvent, par ordre du ministre Minister or a mining recorder, on application by the ou du registraire minier, être, à la demande du owner of the claim, be enlarged to the size of a claim propriétaire de ce claim, étendues jusqu’aux allowed by this Part, if the enlargement will not dimensions d’un claim reconnues par la présente interfere with any mining property that is owned by partie, pourvu que cette extension n’empiète pas sur any other person or that is subject to the terms of an une propriété minière appartenant à une autre agreement with the Commissioner. personne ou assujettie aux termes d’une convention avec le Commissaire. [S.Y. 2003, c. 13, s. 26] [L.Y. 2003, ch. 13, art. 26] 27 Forms (Formulaires) 27 Forms 27 Formulaires The forms of application for grant, of application for Les formulaires de demande de concession, de renewal of grant, and of grant of a claim are those demande de renouvellement de concession et d’actes contained respectively in Forms 1, 2, and 3 of de concession d’un claim sont ceux qui sont Schedule 1. respectivement énoncés aux formulaires 1, 2 et 3 de l’annexe 1. [S.Y. 2003, c. 13, s. 27] [L.Y. 2003, ch. 13, art. 27] 28 Time allowed (Temps accordé) 28 Time allowed 28 Temps accordé An application in duplicate for a grant of a claim shall Une demande de concession d’un claim, faite en double be filed with the mining recorder for the district in exemplaire, doit être déposée entre les mains du which the claim is situated within ten days after the registraire minier du district dans lequel ce claim est location of it if it is located within ten miles of the situé dans les dix jours qui suivent la localisation du office of the mining recorder. claim, s’il est localisé dans un rayon de dix milles du bureau du registraire minier. Page 10 UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON c Placer Mining Act Loi sur l’extraction de l’or PART 1 PARTIE 1 Section 29 Article 29 (2) One additional day shall be allowed for every (2) Il est accordé un jour supplémentaire pour chaque additional ten miles or fraction for filing an application rayon de dix milles ou fraction de dix milles under subsection (1). additionnels. [S.Y. 2003, c. 13, s. 28] [L.Y. 2003, ch. 13, art. 28] 29 Part of claim already recorded (Partie d’un claim déjà inscrit) 29 Part of claim already recorded 29 Partie d’un claim déjà inscrit No grant shall be issued by a mining recorder for a Le registraire minier ne peut émettre de concession part of a claim that is already recorded. pour une partie d’un claim qui est déjà inscrit. [S.Y. 2003, c. 13, s. 29] [L.Y. 2003, ch. 13, art. 29] 30 Location on Sunday (Établissement de claim le dimanche) 30 Location on Sunday 30 Établissement de claim le dimanche The location of a claim on Sunday or any public holiday La localisation d’un claim le dimanche ou un jour de is not for that reason invalid. fête public n’est pas pour cela invalide. [S.Y. 2003, c. 13, s. 30] [L.Y. 2003, ch. 13, art. 30] 31 When claims one hundred miles from mining recorder‘s office (Registraire d’urgence) 31 When claims one hundred miles from 31 Registraire d’urgence mining recorder‘s office (1) Where a claim is more than one hundred miles (1) Si un claim est à plus de cent milles d’un bureau de from the office of a mining recorder and situated registraire minier et situé à un endroit où d’autres where other claims are being located, the locators of claims sont localisés, les localisateurs, au nombre d’au them, not less than five in number, are authorized to moins cinq, sont autorisés à se réunir et à nommer meet and appoint one of their number an emergency registraire d’urgence l’un d’entre eux. Celui-ci peut recorder, who may receive applications for grants of recevoir les demandes de concession de claims localisés claims located in accordance with this Part. conformément à la présente partie. (2) The emergency recorder appointed under (2) Le registraire d’urgence inscrit sur chaque subsection (1) shall note on each application the day on demande la date à laquelle il l’a reçue et le montant which each application was received and the amount of des droits versés à cet égard. fees paid in respect of the application. [S.Y. 2003, c. 13, s. 31] [L.Y. 2003, ch. 13, art. 31] 32 Notification of applications (Notification des demandes) 32 Notification of applications 32 Notification des demandes (1) The emergency recorder shall, as soon as possible (1) Le plus tôt possible après sa nomination, le after their appointment, notify the mining recorder for registraire d’urgence notifie sa nomination au the district in which the claims are situated of their registraire minier du district où sont situés les claims appointment, and shall deliver personally or otherwise et il lui remet, personnellement ou autrement, les to that mining recorder the applications and fees demandes et les droits qu’il a reçus à l’égard de ces received by them in respect of those claims. claims. (2) Where the emergency recorder has accepted from (2) Lorsque le registraire d’urgence a accepté d’une any person an application made in accordance with this personne une demande faite en conformité avec la Part and in the form set out in Form 1 of Schedule 1 présente partie et selon le formulaire 1 de l’annexe 1, and the fee therefor, the mining recorder may issue to ainsi que le droit à cet égard, le registraire minier peut that person a grant in Form 3 of Schedule 1. délivrer à cette personne un acte de concession selon le formulaire 3 de l’annexe 1. (3) The grant mentioned in subsection (2) shall date (3) L’acte de concession mentionné au paragraphe (2) from the time the emergency recorder accepted the date du moment où le registraire d’urgence a accepté application and fee. la demande et les droits. c UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON Page 11 Placer Mining Act Loi sur l’extraction de l’or PART 1 PARTIE 1 Section 33 Article 33 (4) Where the emergency recorder fails, within four (4) Lorsque le registraire d’urgence omet, dans les months, to notify the mining recorder of their quatre mois, de notifier sa nomination au registraire appointment and to deliver to the mining recorder the minier et de lui remettre les demandes de claims applications for claims received and the fees collected, reçues et les droits perçus, le registraire minier peut the mining recorder may refuse to issue grants for refuser de délivrer les actes de concession pour ces those claims. claims. [S.Y. 2003, c. 13, s. 32] [L.Y. 2003, ch. 13, art. 32] 33 Permits to prospectors (Permis aux prospecteurs) 33 Permits to prospectors 33 Permis aux prospecteurs Any person, on satisfying a mining recorder that they Lorsqu’une personne convainc un registraire minier are about to undertake a bona fide prospecting trip, qu’elle est sur le point d’entreprendre de bonne foi une may, on payment of a fee of two dollars, receive excursion de recherche, elle peut, sur paiement d’un written permission from the mining recorder allowing droit de deux dollars, recevoir du registraire minier un them to record a claim within the mining recorder’s permis par écrit l’autorisant à faire inscrire un claim mining district at any time within a period not dans les limites du district minier du registraire à tout exceeding six months from the date of the staking the moment situé au cours d’une période n’excédant pas claim. six mois à compter de la date à laquelle elle a jalonné le claim. [S.Y. 2003, c. 13, s. 33] [L.Y. 2003, ch. 13, art. 33] 34 Claim to be staked by applicant in person (Le requérant doit avoir personnellement délimité un claim) 34 Claim to be staked by applicant in person 34 Le requérant doit avoir personnellement délimité un claim No application shall be received for a claim that has not Aucune demande n’est reçue pour un claim qui n’a pas been staked by the applicant in person in the manner été jalonné par le requérant lui-même de la manière specified in this Part, except that if any person files que spécifie la présente partie, mais si une personne with a mining recorder powers of attorney from not dépose entre les mains du registraire minier des more than two persons, that person may stake procurations de deux personnes au plus, elle peut à la subsequent to the filing not more than three claims in suite d’un tel dépôt jalonner au plus trois claims au the name of each of those persons during any year the nom de chacune de ces personnes pendant toute année power of attorney is in force. où la procuration est en vigueur. [S.Y. 2003, c. 13, s. 34] [L.Y. 2003, ch. 13, art. 34] 35 Abandonment and surrender of claim (Abandon et remise de claims) 35 Abandonment and surrender of claim 35 Abandon et remise de claims (1) A person holding a grant of a claim may, at any (1) La personne qui détient la concession d’un claim time, abandon the claim by giving notice in writing of peut abandonner le claim en donnant au registraire their intention to do so to a mining recorder and minier un préavis par écrit et en lui remettant son acte surrendering their grant to the mining recorder. de concession. (2) No claim that has been abandoned under (2) Nul claim ne peut être localisé de nouveau dans subsection (1) shall be relocated within thirty days after les 30 jours de cet abandon sans qu’un avis de cet it is abandoned, or until after notice of the abandon n’ait été affiché pendant au moins une abandonment has been posted up for at least a week in semaine dans un endroit bien en vue sur le claim et a conspicuous place on the claim and in the office of dans le bureau du registraire minier, ni sans qu’une the mining recorder, or until a statutory declaration déclaration solennelle, attestant que l’avis a été ainsi has been filed with the mining recorder that the notices affiché, n’ait été déposée entre les mains du registraire have been so posted. minier. Page 12 UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON c Placer Mining Act Loi sur l’extraction de l’or PART 1 PARTIE 1 Section 36 Article 36 (3) Persons holding an interest in a claim at the time (3) Les personnes qui possèdent un intérêt dans un of its forfeiture or abandonment do not have the right claim, lors de sa confiscation ou de son abandon, n’ont to relocate the claim, or any part of it, within one year pas le droit de localiser de nouveau ce claim, ni aucune after the date of its forfeiture or abandonment. de ses parties, au cours de l’année qui suit la date de cette confiscation ou de cet abandon. [S.Y. 2003, c. 13, s. 35] [L.Y. 2003, ch. 13, art. 35] 36 Limitation (Limites) 36 Limitation 36 Limites Any person who records a claim in their own name or La personne qui inscrit un claim en son nom propre, ou who has a claim recorded in their name by power of qui a un claim inscrit en son nom propre par attorney does not have the right to locate or have procuration, n’a pas le droit de localiser ou de faire located for them another claim within the valley or localiser, pour elle, un autre claim dans les limites de la basin of the same creek or river within sixty days of vallée ou du bassin du même ruisseau ou de la même the date on which the claim was located. rivière pendant les 60 jours qui suivent la date à laquelle le claim a été localisé. [S.Y. 2003, c. 13, s. 36] [L.Y. 2003, ch. 13, art. 36] 37 Substitute of mining recorder (Remplaçant du registraire minier) 37 Substitute of mining recorder 37 Remplaçant du registraire minier During the absence of a mining recorder from their Pendant que le registraire minier est absent de son office, an application for a claim may be received by bureau, toute personne qu’il peut nommer pour any person whom they may appoint to perform their exercer ses fonctions en son absence peut recevoir une duties in their absence. demande de concession de claim. [S.Y. 2003, c. 13, s. 37] [L.Y. 2003, ch. 13, art. 37] 38 Tagging of claims (Apposition d’étiquettes) 38 Tagging of claims 38 Apposition d’étiquettes As soon as reasonably possible after a grant of a claim, Aussitôt qu’il est raisonnablement possible de le faire the holder of the claim shall affix or cause to be affixed après la concession d’un claim, le détenteur du claim securely to each of the legal posts of the claim a metal appose, ou fait apposer solidement, sur chacune des tag plainly marked or impressed with the number and bornes légales du claim, une étiquette métallique letter or letters, if any, of the grant of the claim and, in portant lisiblement la marque ou l’impression du the event of default, the claim may be cancelled by a numéro et de la ou des lettres, s’il y a lieu, de la mining recorder on the application of anyone who, in concession du claim, et, à défaut de ce faire, la the opinion of the mining recorder, has been misled by concession peut être annulée par le registraire minier, the absence of the tags. à la demande de toute personne qui, de l’avis du registraire minier, a été induite en erreur par l’absence de telles étiquettes. (2) A mining recorder on application therefor shall (2) La registraire minier, sur demande, fournit supply the numbered tags mentioned in subsection (1) gratuitement l’étiquette numérotée mentionnée au free of charge. paragraphe (1). [S.Y. 2003, c. 13, s. 38] [L.Y. 2003, ch. 13, art. 38] 39 Survey of claims (Arpentage de claims) 39 Survey of claims 39 Arpentage de claims (1) The survey of claims made under instructions (1) L’arpentage de claims fait en exécution issued by direction of the Minister to a duly qualified d’instructions données par ordre du ministre à un Canada Lands Surveyor shall be accepted as defining arpenteur fédéral dûment qualifié, nommé par lui, est absolutely the boundaries of the claims surveyed, if the accepté comme déterminant absolument les limites des returns of the survey are approved by the Minister or claims arpentés, pourvu que les procès-verbaux de an official appointed by the Minister for that purpose, l’arpentage soient approuvés par le ministre ou par un c UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON Page 13 Placer Mining Act Loi sur l’extraction de l’or PART 1 PARTIE 1 Section 39 Article 39 and notice of the survey has been published in the fonctionnaire nommé par lui à cette fin, pourvu que Yukon Gazette for twelve successive issues and remains l’annonce de cet arpentage ait été publiée dans douze unprotested during that period. numéros successifs de la Gazette du Yukon et pourvu qu’il n’y ait pas eu d’opposition à cette annonce durant cette période. (2) The owner of a claim surveyed pursuant to (2) Le propriétaire d’un claim ainsi arpenté doit, avant subsection (1) shall, prior to the first appearance of the que l’annonce ne paraisse pour la première fois dans la advertisement in the Yukon Gazette, cause to be posted Gazette du Yukon, faire afficher, dans un endroit bien in a conspicuous spot on the claim a notice of their en vue sur le claim, avec un avis de son intention intention to advertise the survey of the claim, and also d’annoncer l’arpentage du claim, un plan de cet a plan of the survey of the claim prepared by the arpentage dressé par l’arpenteur. surveyor. (3) If, within the time during which the notice referred (3) Si, pendant la période de publication de cet avis, to in this section is published, the survey is protested, opposition est faite à l’arpentage, cette opposition est the protest shall be heard and decided on by the entendue et jugée par le ministre, et les frais de Minister, and the costs of the hearing are in the l’instance sont répartis à la discrétion du ministre qui discretion of the Minister, who may direct that the peut ordonner que la totalité ou une partie de ces frais costs or any portion of them shall be paid by any party soit versée par l’une des parties à la contestation. to the proceedings. (4) If a decision is rendered varying the boundaries of (4) S’il est rendu une décision qui fait différer les the claim from those defined by the advertised survey, limites du claim de celles déterminées par l’arpentage the owner of the claim may have the claim re-surveyed annoncé, le propriétaire du claim peut faire réarpenter and new returns prepared embodying the changes le claim et faire préparer un nouveau rapport involved by that decision, and the re-survey on being comprenant les changements qu’entraîne cette approved by the Minister, or the official appointed by décision, et ce réarpentage, une fois approuvé par le the Minister for that purpose, may without ministre ou par le fonctionnaire nommé par lui à cette advertisement be accepted by the Minister in lieu of the fin, peut être accepté, sans annonce, par le ministre à survey that has been protested. la place de l’arpentage qui a été contesté. (5) The expenses in connection with the survey and (5) Les frais qu’entraînent l’arpentage et l’annonce des advertisement of claims shall be defrayed by the claims sont acquittés par les propriétaires des claims, owners of the claims, but no fees will be charged by mais le gouvernement n’exige pas de droits pour la the Government for filing plans or other documents in production des plans ou d’autres documents qui s’y connection therewith. rapportent. (6) An appeal may be taken at any time within twenty (6) Appel de la décision du ministre devant la Cour days from the decision of the Minister under this suprême peut être interjeté dans les vingt jours qui section to the Supreme Court. suivent cette décision. (7) The procedure in all cases under this section, and (7) La procédure dans toutes les contestations, sous le on appeal therefrom, shall be in accordance with rules régime du présent article, et lors d’un appel, doit être prepared by the Commissioner in Executive Council. conforme aux règles préparées par le commissaire en conseil exécutif. [S.Y. 2003, c. 13, s. 39] [L.Y. 2003, ch. 13, art. 39] Page 14 UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON c Placer Mining Act Loi sur l’extraction de l’or PART 1 PARTIE 1 Section 40 Article 40 40 Surveys (Arpentages) 40 Surveys 40 Arpentages The Minister may authorise and direct the survey of the Le ministre peut autoriser et ordonner l’arpentage de la base line of any creek or river to be made in ligne de base de tout ruisseau ou de toute rivière, selon accordance with such general instructions as may be les instructions générales que peut donner l’arpenteur issued by the Surveyor General (Canada), and the général (Canada), et cet arpentage doit, sous réserve survey is, subject to the provisions of this Part with des dispositions de la présente partie relatives à respect to advertisement and protest, a final l’annonce et à l’opposition, être une détermination determination of the location of the base line. finale du tracé de cette ligne de base. [S.Y. 2003, c. 13, s. 40] [L.Y. 2003, ch. 13, art. 40] 41 Title (Titre) 41 Title 41 Titre (1) Any person having duly located a claim may obtain (1) Toute personne qui a dûment localisé un claim peut a grant of it for one or five years by paying to a mining en obtenir la concession pour un an ou pour cinq ans recorder, in advance, the fees prescribed in Schedule 2. en payant d’avance au registraire minier les droits prévus à l’annexe 2. (2) Any person referred to in subsection (1) is, on (2) Dès qu’elle reçoit cet acte de concession, cette receiving a grant of a claim, entitled to hold the claim personne a droit de jouir du claim durant la période for the period mentioned in it, with the absolute right mentionnée dans l’acte, avec le droit absolu de of renewal from year to year thereafter on payment of renouvellement, d’année en année, contre paiement du the renewal fee prescribed in Schedule 2, if that droit de renouvellement prescrit à l’annexe 2, si, à la person, fois : (a) during each year of the period, and during a) pendant chaque année au cours de cette each year for which the renewal is granted, période, et pendant chaque année pour laquelle does, or causes to be done, work on the claim ce renouvellement est accordé, cette personne to the value of two hundred dollars, in effectue ou fait effectuer des travaux d’une accordance with a schedule to be prepared by valeur de 200 $ sur le claim, conformément à the Commissioner in Executive Council; and une échelle que prépare le commissaire en conseil exécutif; (b) files, within fourteen days after the date of the b) dans les quatorze jours suivant la date de expiration of the period or the renewal of it, l’expiration de cette période ou de ce with the mining recorder or his or her agent renouvellement, cette personne dépose, entre their affidavit, stating that the work has been les mains du registraire minier ou de son done and setting out a detailed statement of agent, un affidavit fait par elle ou par son the work done. agent, établissant que ces travaux ont été effectués et en donnant un état détaillé. (3) Any work done outside of a claim with intent to (3) Pour l’application du présent article, tous les work the claim shall be deemed, if it has direct relation travaux exécutés en dehors d’un claim pour to the claim and is done to the satisfaction of the l’exploitation de ce claim sont réputés être des travaux mining recorder, be deemed to be work done on the exécutés sur le claim s’ils se rapportent directement au claim for the purposes of this section. claim et s’ils sont exécutés à la satisfaction du registraire minier. (4) Where more work is performed by or on behalf of (4) Lorsqu’il est exécuté, par le propriétaire enregistré the recorded owner of a claim than is required by this d’un claim ou pour son compte, plus de travaux que Part to be performed during any year, the excess work n’en exige la présente partie pendant une année up to a value of eight hundred dollars, on proof that it quelconque, l’excédent des travaux jusqu’à concurrence has been performed in accordance with this Part, or d’une valeur de 800 $, sur preuve qu’ils ont été the Yukon Placer Mining Act (Canada), shall be applied exécutés conformément à la présente partie ou à la Loi c UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON Page 15 Placer Mining Act Loi sur l’extraction de l’or PART 1 PARTIE 1 Section 42 Article 42 by the mining recorder on work required to be done sur l’extraction de l’or dans le Yukon (Canada), est during the subsequent year or years, and excess work appliqué par le registraire minier aux travaux dont may only be recorded during the year in which it was l’exécution est requise pendant l’année subséquente ou performed or within fourteen days of the expiration of les années subséquentes; l’excédent des travaux ne that year. peut être inscrit que pendant l’année où ils ont été accomplis ou dans les quatorze jours de l’expiration de l’année concernée. (5) A schedule prepared by the Commissioner in (5) Une échelle que prépare le commissaire en conseil Executive Council under subsection (2) exécutif en vertu du paragraphe (2) à la fois : (a) may establish categories of claims on the basis a) peut établir des catégories de claims en of any attribute or combination of attributes fonction d’un attribut ou d’une combinaison (which attributes may for greater certainty d’attributs, étant entendu que ces derniers include the agreement, as to the categorization peuvent comprendre l’accord des personnes of particular claims, of persons specified in the visées par l’échelle à l’égard de la schedule); catégorisation de claims particuliers; (b) may require that work on a claim be valued b) peut exiger que les travaux effectués sur le differently according to when the work is done claim soient évalués différemment, selon le or according to the category of the claim; and moment où sont effectués les travaux ou selon la catégorie du claim; (c) may waive, or may empower the Minister to c) peut renoncer, ou habiliter le ministre à le waive, all or any portion of the renewal fee in faire, à tout ou partie des droits de respect of a claim or category of claims. renouvellement à l’égard d’un claim ou d’une catégorie de claims. [S.Y. 2016, c. 12, s. 1] [S.Y. 2003, c. 13, s. 41] [L.Y. 2016, ch. 12, art. 1] [L.Y. 2003, ch. 13, art. 41] 42 Forfeiture of claim (Déchéance du claim) 42 Forfeiture of claim 42 Déchéance du claim (1) In the event that the work referred to in section 41 (1) Si les travaux mentionnés à l’article 41 ne sont pas is not done as provided in that section, the title of the effectués de la façon qui y est prescrite, le titre du owner to the claim thereupon becomes absolutely propriétaire du claim tombe dès lors absolument en forfeited, the claim is forthwith open for relocation déchéance, le claim peut immédiatement faire l’objet without any declaration of cancellation or forfeiture on d’une nouvelle localisation, sans déclaration the part of the Commissioner and the claim shall not be d’annulation ou de déchéance de la part du reserved from entry and relocation during the fourteen Commissaire, et le claim peut être inscrit et localisé de days of grace mentioned in that section. nouveau pendant les quatorze jours de délai mentionnés dans cet article. (2) This section does not affect any rights granted by (2) Le présent article ne modifie pas les droits the terms of any existing agreement with the accordés en vertu des modalités contenues dans une Commissioner. entente en vigueur avec le Commissaire. (3) If the mining recorder is satisfied, on written (3) S'il estime que le propriétaire d'un claim minier ne application filed with the mining recorder by an owner pourra pas ou n'a pas pu effectuer les travaux visés à of a claim, that the owner will be or has been unable to l'article 41 selon les modalités qui y sont prévues en do the work referred to in section 41 as provided in raison des restrictions ou des obligations prévues à la that section, owing to a restriction or requirement partie 2 ou à toute autre loi fédérale ou territoriale, le imposed by Part 2 or by any other Act of Parliament or registraire minier doit, sur demande écrite du of the Legislature, the mining recorder shall grant such propriétaire du claim et sous réserve du relief with respect to that work as may be necessary paragraphe (5), accorder à l'égard de ces travaux l'aide under the circumstances, subject to subsection (5). qui peut être nécessaire dans les circonstances. Page 16 UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON c Placer Mining Act Loi sur l’extraction de l’or PART 1 PARTIE 1 Section 43 Article 43 (4) If the Minister is satisfied, on written application (4) S'il estime que le propriétaire d'un claim minier ne filed with the mining recorder by an owner of a claim, pourra pas ou n'a pas pu effectuer les travaux visés à that the owner will be or has been unable to do the l'article 41 selon les modalités qui y sont prévues, et ce work referred to in section 41 as provided in that pour des raisons indépendantes de sa volonté, à section, owing to any circumstance beyond the owner's l'exception des restrictions ou des obligations visées au control, other than a restriction or requirement paragraphe (3), le ministre peut, sur demande écrite referred to in subsection (3), the Minister may grant du propriétaire du claim au registraire minier et sous such relief with respect to that work as may be réserve du paragraphe (5), accorder à l'égard de ces necessary under the circumstances, subject to travaux l'aide qui peut être nécessaire dans les subsection (5). circonstances. (5) Relief granted under subsection (3) or (4) is subject (5) L'octroi de l'aide prévue aux paragraphes (3) et (4) to any conflicting right acquired by another person est assujetti à tout droit incompatible acquis par un under this Part before the application for relief was tiers sous le régime de la présente partie avant la filed with the mining recorder. présentation de la demande d'aide au registraire minier. [S.Y. 2003, c. 13, s. 42] [L.Y. 2003, ch. 13, art. 42] 43 When owner does not renew (Quand le propriétaire ne renouvelle pas) 43 When owner does not renew 43 Quand le propriétaire ne renouvelle pas (1) Where the owner of a claim has done the required (1) Lorsque le propriétaire d’un claim y a effectué les work thereon but has failed to renew the grant of the travaux exigés, mais a négligé d’en renouveler la claim, a mining recorder may issue a grant to any concession, le registraire minier peut délivrer un acte person relocating the claim. de concession à toute personne qui localise de nouveau ce claim. (2) The owner of a claim may, within six months after (2) Le propriétaire du claim peut, dans les six mois qui the date on which their grant became due for renewal, suivent la date à laquelle le claim devait être renouvelé, apply for a renewal grant and for the cancellation of demander un renouvellement de sa concession, et la any grant so issued, and the latter grant shall be révocation de toute concession ainsi accordée, et cette cancelled or, in the event that a grant has not been dernière concession doit être révoquée, ou, lorsqu’il n’a issued for the claim, any pending application for the pas été accordé de concession du claim, toute demande claim shall be refused, if it is proved to the satisfaction pendante de concession de ce claim doit être refusée, of a mining recorder that the required work was done s’il est prouvé, à la satisfaction du registraire minier, by the owner, and on the owner paying the expenses to que le travail exigé a été exécuté par le propriétaire, et which the relocator may have been put in locating and pourvu que le propriétaire acquitte les dépenses que le applying for the claim and, in the event that a grant nouveau localisateur peut avoir faites pour localiser et has been issued for it, paying also all the expenses to demander le claim, et lorsqu’il a été accordé une which the relocator may have been put in obtaining the concession à cet effet, pourvu qu’il solde toutes les grant, and also compensation for any work that the dépenses que le nouveau localisateur a pu faire pour relocator has performed in good faith on the claim. obtenir cette concession, ainsi qu’une indemnité pour les travaux qu’il y a exécutés de bonne foi. (3) Where the owner of a claim fails to renew his or (3) À défaut par le propriétaire d’un claim de her grant within the time provided by this Part, the renouveler sa concession dans le délai prescrit par la renewal fee, if paid within three months after the date présente partie, le droit de renouvellement, s’il est of expiration, is thirty dollars, and after three months acquitté dans les trois mois qui suivent la date de and within six months from the date of expiration is l’expiration, est de 30 $, et, après les trois mois et dans forty-five dollars. les six mois de cette date d’expiration, de 45 $. [S.Y. 2003, c. 13, s. 43] [L.Y. 2003, ch. 13, art. 43] c UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON Page 17 Placer Mining Act Loi sur l’extraction de l’or PART 1 PARTIE 1 Section 44 Article 44 44 Contesting title (Contestation de titre) 44 Contesting title 44 Contestation de titre (1) No title shall be contested by any person who does (1) Sauf permission du ministre, nul titre ne peut être not claim an adverse right except by leave of the contesté par une personne qui ne revendique pas de Minister, and on that leave being given it is not droit adverse. Suite à une permission du ministre, necessary to have any other authority on behalf of the aucune autre autorisation au nom du Commissaire Commissioner. n’est requise. (2) In the event that a claim reverts to the (2) Si un claim retourne au Commissaire par suite du Commissioner as a consequence of litigation litige qui résulte de cette permission, le demandeur a le undertaken pursuant to the leave given under premier droit de localiser ce claim. subsection (1), the plaintiff has the first right to locate the claim. [S.Y. 2003, c. 13, s. 44] [L.Y. 2003, ch. 13, art. 44] 45 Proportionate contribution (Contribution proportionnelle ) 45 Proportionate contribution 45 Contribution proportionnelle Where two or more persons are co-owners in a claim, Si plusieurs personnes détiennent un claim en each person shall contribute, proportionately to his or commun, chacune contribue, proportionnellement à her interest, to the work required to be done on the son intérêt, aux travaux qui y sont requis ainsi qu’au claim and to the payment of renewal fees, and if it is paiement des droits de renouvellement, et si, après proved to a mining recorder, after notice of hearing signification de l’avis de l’instance à toutes les parties has been served on all parties interested in the manner intéressées, de la manière prescrite par le registraire directed by the mining recorder, that any co-owner has minier, il est prouvé à ce dernier que l’un des not done so, that co-owner’s interest may, by order of copropriétaires ne l’a pas fait, l’intérêt de ce the mining recorder, become vested in the other co- copropriétaire peut, par ordre du registraire minier, owners who have performed the work and paid the passer aux autres copropriétaires qui ont exécuté les fees in proportion to their respective interests. travaux et payé les droits, proportionnellement à leurs intérêts. [S.Y. 2003, c. 13, s. 45] [L.Y. 2003, ch. 13, art. 45] 46 When claim disposed of (Quand un claim est cédé) 46 When claim disposed of 46 Quand un claim est cédé (1) The owner of a claim may sell, mortgage or (1) Le propriétaire d’un claim peut vendre, dispose of it if the instrument showing the disposal is hypothéquer ou aliéner ce claim, pourvu que la pièce deposited in duplicate with a mining recorder. qui fait preuve de cette aliénation soit déposée en double entre les mains du registraire minier. (2) The mining recorder shall, on the deposit of the (2) Le registraire minier, sur ce dépôt, enregistre la instrument referred to in subsection (1), register the pièce et remet au cessionnaire une des expéditions instrument and return to the assignee one of the portant à l’endos un certificat qu’elle a été enregistrée duplicates with a certificate endorsed thereon that the dans son bureau, et garde l’autre. instrument has been recorded in their office, and retain the other. [S.Y. 2003, c. 13, s. 46] [L.Y. 2003, ch. 13, art. 46] Page 18 UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON c Placer Mining Act Loi sur l’extraction de l’or PART 1 PARTIE 1 Section 47 Article 47 47 Agreements affecting title (Conventions qui touchent au titre) 47 Agreements affecting title 47 Conventions qui touchent au titre No agreement affecting the title to any claim, or to any Nulle convention portant atteinte au titre d’un claim ou interest in it, is enforceable against any person without d’un intérêt dans ce claim ne peut être exécutoire notice, unless the agreement or a memorandum of it is contre une personne sans qu’il lui en soit donné avis, à in writing, duly signed, and is recorded in the office of moins que cette convention ou tout sommaire de cette the mining recorder. convention ne soit écrit, dûment signé, et enregistré dans le bureau du registraire minier. [S.Y. 2003, c. 13, s. 47] [L.Y. 2003, ch. 13, art. 47] 48 Right of grantee (Droit du cessionnaire) 48 Right of grantee 48 Droit du cessionnaire Every person who receives a grant of a claim, or the Toute personne qui obtient la concession d’un claim ou permission to record a claim within the period not le permis de s’inscrire pour un claim dans la période exceeding six months authorized by this Part, d’au plus six mois autorisée aux termes de la présente partie : (a) may, during the continuance of their grant or a) peut, tant que dure sa concession ou son permission, fish, and shoot for their own use, permis, pêcher et chasser pour son propre subject to the provisions of any law for the usage, sous réserve des dispositions de toute protection of fish and game, loi pour la protection du poisson et du gibier; (b) may cut timber, not otherwise acquired, for b) peut couper du bois, non autrement acquis, their own use and for any purpose incidental pour son propre usage et pour toute fin relative and necessary to the operation of their claim, et nécessaire à l’exploitation de son claim; (c) has the exclusive right to enter on their claim c) a le droit exclusif d'aller sur son propre claim for the miner-like working of it and the pour l'exploiter en mineur et y construire et construction and maintenance of structures, entretenir des installations — notamment une including a residence, that are required for the maison d'habitation — nécessaires à cette fin; miner-like working of it, and (d) is entitled exclusively to all the proceeds d) a exclusivement le droit à tous les produits qui realised from it, on which, however, the royalty en proviennent, sur lesquels doit cependant prescribed by this Part is payable, être exigible la redevance prescrite par la présente partie. but the mining recorder may grant to the holders of Le registraire minier peut accorder aux détenteurs other claims such rights of entry on the claim as may d’autres claims les droits de passage sur ce claim qui be absolutely necessary for the working of their claims, peuvent être absolument nécessaires pour l’exploitation on such terms as to him or her seem reasonable, and de leurs propres claims, et ce, aux conditions qu’il juge may also grant permits to other claim owners to cut raisonnables, et il peut aussi accorder à d’autres timber thereon for their own use. propriétaires de claims la permission d’y couper du bois pour leur propre usage. (2) The Minister may, on application, grant any person (2) Le ministre peut, sur demande, accorder à toute operating a dredge permission to take the dredge personne qui se sert d’une drague l’autorisation de through a mining claim owned by any other person to faire passer cette drague sur un claim minier adjoining property that he or she may desire to work appartenant à une autre personne pour l’installer sur with the same dredge, and for that purpose may grant un claim contigu qu’elle désire exploiter avec cette the right to thaw, disturb, or remove such portion of drague, et, pour les fins mentionnées, il peut accorder the claim as in the opinion of the Minister is necessary le droit de dégeler, de remuer ou d’enlever telle partie for such operation. de ce claim qui, de l’avis du ministre, est nécessaire à cette exploitation. c UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON Page 19 Placer Mining Act Loi sur l’extraction de l’or PART 1 PARTIE 1 Section 49 Article 49 (3) Before a permission is granted under (3) Avant que cette autorisation soit accordée, le subsection (2), the applicant shall deposit with the requérant doit déposer entre les mains du ministre une Minister a sufficient sum of money to secure payment somme d’argent suffisante pour assurer le paiement au to the owner of the claim for all damage that may be propriétaire du claim de tout dommage occasionné par caused by the passage of the dredge through the claim, le passage de la drague sur ce claim, et tout dommage and all damage caused by the passage through the causé par ce passage sur le claim doit être évalué par claim shall be assessed by the Minister and, from the le ministre, et, sur le montant déposé entre ses mains moneys deposited with the Minister by the applicant, par le requérant, le dommage ainsi évalué doit être the damage as assessed shall be paid and the balance, payé, et le reste du montant, s’il y en a, doit être if any, refunded. remboursé.
Part document.segment-3
Placer Mining Act (Extraction de l’or) — segment 3
- document.segment-3 Verify source ↗
Placer Mining Act (Extraction de l’or) — segment 3
This part sets rules for water use, drainage, claim grouping, and related powers, rights, fees, deadlines, and appeals.
(4) Where, in the operation necessary for the passage (4) Lorsque, dans l’opération nécessaire au passage de of the dredge referred to in subsection (2), any pay la drague, des graviers aurifères sont enlevés, l’or qui gravels are removed, the gold that may be contained in peut être contenu dans ces graviers doit être recouvré it shall be recovered by the operator of the dredge, and par la personne qui fait cette opération, et tout cet or all such gold is the property of the owner of the claim. est la propriété du propriétaire du claim. (5) An appeal from an assessment of damage under (5) Dans les dix jours qui suivent la décision du this section may be taken at any time within ten days ministre relativement au montant de l’évaluation, appel from the decision of the Minister to the Supreme Court de cette décision peut être interjeté devant la Cour with respect to the amount of the assessment. suprême. [S.Y. 2003, c. 13, s. 48] [L.Y. 2003, ch. 13, art. 48] 49 Rights of owner (Droits du propriétaire) 49 Rights of owner 49 Droits du propriétaire No rights of any person owning or applying for a claim Les actes d’omission ou de commission ou les retards shall suffer from any acts of omission or commission, d’un fonctionnaire nommé en exécution de la présente or delays, on the part of any official appointed under partie ne sauraient porter atteinte aux droits d’une this Part. personne qui détient ou sollicite un claim. [S.Y. 2003, c. 13, s. 49] [L.Y. 2003, ch. 13, art. 49] 50 When evidence of location lost (Lorsque les marques de l’établissement disparaissent) 50 When evidence of location lost 50 Lorsque les marques de l’établissement disparaissent Whenever, through the acts or defaults of any person Lorsque, par les actes ou fautes d’une autre personne other than the recorded owner of a claim or the que le propriétaire enregistré d’un claim ou de son owner’s duly authorized agent, the evidence of the agent par lui dûment autorisé, la preuve de la location or record on the ground or the situation of the localisation ou de l’inscription sur le terrain ou de claim has been destroyed, lost, or effaced, or is difficult l’emplacement du claim a été détruite, perdue ou to ascertain, effect shall be given to the location as far effacée, ou qu’il est difficile de la reconnaître, la as possible, and the Minister may make all necessary localisation doit être, autant que possible, rétablie, et le inquiries, directions, and references for the purpose of ministre peut faire toutes les enquêtes, donner tous les carrying out the object of verifying the claim and ordres et prendre tous les renseignements nécessaires vesting title in that owner. en pareil cas dans le but de satisfaire à l’objet de vérifier le claim et d’attribuer le titre à ce propriétaire. [S.Y. 2003, c. 13, s. 50] [L.Y. 2003, ch. 13, art. 50] Page 20 UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON c Placer Mining Act Loi sur l’extraction de l’or PART 1 PARTIE 1 Section 51 Article 51 51 Claims of service personnel (Claims du personnel militaire) 51 Claims of service personnel 51 Claims du personnel militaire The Commissioner in Executive Council may make Le commissaire en conseil exécutif peut prendre des regulations exempting members of the armed forces of règlements exemptant les membres des forces armées His Majesty or any of His Majesty’s allies, during the de Sa Majesté ou de l’un de ses alliés, durant la période period of their service and one year after it, from the de leur service à ce titre et durant l’année subséquente provisions of this Part respecting forfeiture of mineral à ce service, des dispositions de la présente partie claims held by them at the time of their enlistment, for touchant la confiscation de claims miniers par eux non-performance of work or non-payment of détenus lors de leur enrôlement, pour défaut d’exécuter assessments or rentals. les travaux ou de payer des cotisations ou loyers. [S.Y.2023, c.7, s.20] [S.Y. 2003, c. 13, s. 51 ] [L.Y. 2003, ch. 13, art. 51] 52 Owners of adjoining claims (Propriétaires de claims adjacents) 52 Owners of adjoining claims 52 Propriétaires de claims adjacents (1) Adjoining claims, not exceeding ten in number, (1) Des claims adjacents, au nombre d’au plus dix, may be grouped together for the performance of work peuvent être groupés pour l’exécution des travaux par by their owner or owners on filing with a mining leur ou leurs propriétaires en déposant entre les mains recorder a notice of intention to group the claims and du registraire minier un avis de son ou de leur obtaining a grouping certificate in Form 7 of intention de grouper ainsi ces claims et en obtenant un Schedule 1. certificat de groupement selon le formulaire 7 de l’annexe 1. (2) Adjoining claims exceeding ten in number and any (2) Des claims adjacents, dont le nombre excède dix, number of claims some of which do not adjoin may et des claims, quel qu’en soit le nombre, dont certains with the approval of the Minister be grouped together ne sont pas adjacents peuvent, avec l’approbation du for the performance of work by the owner or owners if ministre, être groupés pour l’exécution des travaux par the owner or owners show to the satisfaction of the leur ou leurs propriétaires si ce ou ces derniers Minister that the claims are to be operated by a system démontrent, à la satisfaction du ministre, que les of mining that has a direct bearing on all other claims claims doivent être exploités au moyen d’un système affected and renders a considerable area necessary to d’exploitation minière qui a un rapport direct avec tous successful operation by the system proposed, and the les autres claims visés et nécessite une vaste région Minister may, in those cases, issue a grouping pour que l’exploitation au moyen du système proposé certificate in Form 7 of Schedule 1. réussisse, et le ministre peut, en pareils cas, émettre un certificat de groupement selon le formulaire 7 de l’annexe 1. (3) The holder or holders of a grouping certificate in (3) Le ou les détenteurs d’un certificat de groupement, Form 7 of Schedule 1 may perform on any one or more selon le formulaire 7 de l’annexe 1, peuvent exécuter, of the claims, in respect of which the grouping dans un ou plusieurs des claims à l’égard desquels le certificate was issued, all or any part of the work certificat de groupement a été émis, la totalité ou une required to entitle them to a certificate of work for partie des travaux requis pour admettre ce ou ces each claim so held by them, but if the work is not done détenteurs à un certificat de travaux pour chaque claim the claims shall be deemed to be vacant and qu’ils détiennent ainsi, mais, si ces travaux ne sont pas abandoned without any declaration of cancellation or exécutés, les claims sont censés être vacants et forfeiture on the part of the Commissioner. abandonnés, sans aucune déclaration d’annulation ou de confiscation de la part du Commissaire. c UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON Page 21 Placer Mining Act Loi sur l’extraction de l’or PART 1 PARTIE 1 Section 53 Article 53 (4) Any grouping certificate issued by the Minister may (4) Tout certificat de groupement émis par le ministre be cancelled by the Minister on the expiration of sixty peut être annulé par ce dernier à l’expiration de 60 days from the mailing of a notice by registered mail to jours à compter de l’envoi, par lettre recommandée, the owners of the claims in the group, if it appears d’un avis aux propriétaires de claims dans le groupe, from the report of a mining inspector or otherwise that lorsqu’il ressort du rapport d’un inspecteur des the system of mining contemplated when the grouping exploitations minières ou d’une autre façon que le certificate was issued is not being installed or operated système d’exploitation minière, envisagé lors de la with reasonable diligence. délivrance de ce certificat de groupement, n’est pas installé ou mis en fonctionnement avec une diligence raisonnable. [S.Y. 2003, c. 13, s. 52] [L.Y. 2003, ch. 13, art. 52] 53 Renewing of grouped claims on the same day (Concessions rendues renouvelables le même jour) 53 Renewing of grouped claims on the 53 Concessions rendues renouvelables le same day même jour (1) Grants of claims in respect of which a grouping (1) Le registraire minier peut, sur demande du certificate has been issued, and grants of any claims propriétaire, rendre renouvelables le même jour les within a mining district, owned by one person, may, on concessions à l’égard desquelles un certificat de application by the owners, be made renewable by a groupement a été délivré et les concessions de tous les mining recorder on the same date. claims que détient une même personne dans les limites d’un district minier. (2) In granting the privilege allowed under this (2) En accordant le privilège qu’autorise le présent section, the mining recorder shall charge the applicant article, le registraire minier exige du requérant, pour two dollars and fifty cents for every period of three chaque claim, la somme de 2,50 $ par trimestre ou months or less for each claim during that portion of the fraction de trimestre nécessaire pour que le year it is necessary to renew it to make all the claims renouvellement de la concession, s’il y a lieu, coïncide renewable on the same day, and the representation avec celui des autres claims; et, pour la fraction work required for the fractional portion of the year for d’année pour laquelle chaque concession est which each claim is renewed shall be allowed at the renouvelée, le requérant est tenu de faire des travaux rate of fifty dollars for each three months or fraction obligatoires pour une valeur de 50 $ par trimestre ou thereof, and the representation work shall be fraction de trimestre, et ces travaux obligatoires sont performed and recorded on or before the date from effectués et inscrits à ou avant la date du premier which all the claims are first made renewable. renouvellement commun des concessions. [S.Y. 2003, c. 13, s. 53] [L.Y. 2003, ch. 13, art. 53] 54 Rights of claim owner to water (Le propriétaire d’un claim a droit à l’eau) 54 Rights of claim owner to water 54 Le propriétaire d’un claim a droit à l’eau Every person who owns a claim is entitled to the Toute personne qui détient un claim a droit à l’eau de seepage water on their claim and to the use of so much filtration sur son claim et à l’usage de la quantité d’eau of the water naturally flowing through or past their qui coule naturellement au travers ou au-delà de son claim, and not already lawfully appropriated, as, in the claim, qui n’est pas déjà légalement attribuée et qui opinion of a mining inspector, is necessary for the due est, de l’avis de l’inspecteur des exploitations minières, working of the claim, and they are entitled to drain nécessaire pour exploiter convenablement le claim; et their own claim free of charge. elle a le droit d’assécher gratuitement son propre claim. [S.Y. 2003, c. 13, s. 54] [L.Y. 2003, ch. 13, art. 54] Page 22 UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON c Placer Mining Act Loi sur l’extraction de l’or PART 1 PARTIE 1 Section 55 Article 55 55 Grant of right to divert or use water (Quand le droit de détourner ou d’utiliser de l’eau peut être concédé) 55 Grant of right to divert or use water 55 Quand le droit de détourner ou d’utiliser de l’eau peut être concédé (1) A mining recorder may, with the approval of the (1) Avec l’approbation du ministre et sur demande Minister, on application being made as mentioned in faite aux conditions mentionnées à la présente partie, this Part, grant to any person or persons for any un registraire minier peut concéder à une ou à mining purpose or any purpose incidental to mining, plusieurs personnes, à toute fin d’exploitation minière for any term not exceeding five years, or in special ou à toute fin s’y rattachant, pour une période cases for such longer term as may be determined, the maximale de cinq ans ou, dans des cas particuliers, right to divert or take, and use or sell, the water from pour le laps de temps qui peut être fixé, le droit de any stream or lake, at any particular part thereof, and détourner ou de prendre, d’utiliser ou de vendre l’eau the right-of-way through and entry on any mining de tout cours d’eau ou lac, à un endroit particulier de property for the purpose of constructing and repairing ce cours d’eau ou lac, ainsi que le droit de passer sur ditches and flumes to convey that water. toute propriété minière dans le but de construire et de réparer des fossés et des conduites pour amener cette eau. (2) Before entering on or constructing or repairing (2) Avant d’aller sur la propriété minière d’une autre works on the mining property of any other person, the personne, ou d’y construire ou réparer des ouvrages, le applicant shall give adequate security, by bond or requérant doit donner, par voie de cautionnement ou otherwise, to the satisfaction of the mining recorder to autrement, à la satisfaction du registraire minier, une secure payment to the owner of the mining property of garantie suffisante d’indemnité au propriétaire de cette all damage caused by the entry, construction or repair. propriété minière pour tout préjudice causé de ce fait ou par la construction ou les réparations. [S.Y. 2003, c. 13, s. 55] [L.Y. 2003, ch. 13, art. 55] 56 Notice of intention to apply for water grants (Préavis de demande de concessions hydrauliques) 56 Notice of intention to apply for water 56 Préavis de demande de concessions grants hydrauliques (1) Every applicant for a water grant shall post for (1) Pendant les vingt jours qui précèdent sa demande twenty days prior to the making of the application a de concession hydraulique, le requérant tient affiché un notice in writing of their intention to apply to a mining avis qu’il a l’intention de demander cette concession au recorder for that grant registraire minier : (a) at the point of the proposed diversion or taking a) au point de dérivation ou de prise d’eau of the water, projetée; (b) on the claim on which the water is intended to b) sur le claim où cette eau est destinée à servir; be used, (c) on each claim or person’s land to be crossed by c) sur chaque claim ou terrain privé que l’eau doit the water in the course of transit to the place of traverser pour se rendre chez le destinataire; the user, and (d) in the office of the mining recorder, d) au bureau du registraire minier. and shall forward a copy of the notice to the Minister. Il expédie une copie de cet avis au ministre. (2) The notice referred to in subsection (1) shall state (2) Cet avis doit énoncer les détails suivants : (a) the name of the applicant; a) le nom du requérant; c UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON Page 23 Placer Mining Act Loi sur l’extraction de l’or PART 1 PARTIE 1 Section 57 Article 57 (b) the name or, if unnamed, a sufficient b) le nom, ou s’il ne porte pas de nom, une description, of the stream, lake, or other source description suffisante du cours d’eau, du lac ou from which water is intended to be diverted or autre source d’où cette eau doit être détournée taken; ou prise; (c) the point of diversion or taking of the water or c) le point de dérivation ou de prise d’eau, ou la intended ditch-head, and the point where the tête de fossé projetée, ainsi que le point où water is to be returned to the source; l’eau doit retourner à la source; (d) the means by which it is intended to divert, d) le moyen projeté pour détourner, ou prendre, take or store the water; ou emmagasiner l’eau; (e) the number of inches of water to be e) le nombre de pouces d’eau demandés; applied for; (f) the purposes for which the water is required, f) un exposé raisonnablement circonstancié des stated with reasonable particularity; fins pour lesquelles cette eau est requise; (g) the claim on which the water is to be used or, g) le claim sur lequel l’eau doit être employée, ou if the right to sell water is asked, the locality si le droit de vendre de l’eau est sollicité, dans within which the right is to be exercised; and quelle localité ce droit doit être exercé; (h) the date of the posting of the notice and the h) la date de l’affichage de l’avis et la date à date on which application will be made to the laquelle demande de l’acte de concession mining recorder for the granting of the record. hydraulique sera faite au registraire minier. [S.Y. 2003, c. 13, s. 56] [L.Y. 2003, ch. 13, art. 56] 57 Application for water grant (Demande de concession hydraulique) 57 Application for water grant 57 Demande de concession hydraulique On the day mentioned in the notice of application Le jour mentionné dans l’avis de la demande, ou un referred to in section 56 or on a subsequent day and at jour et à une heure postérieurs que fixe le registraire a time to be fixed by the mining recorder, as the case minier, selon le cas, sollicitation d’une concession, en may be, application shall be made by or on behalf of accord avec les termes de l’avis, est faite par le the applicant, either by attendance in person or by requérant personnellement présent, ou en son nom par agent, or in writing, for a grant in accordance with the un agent, ou par écrit. terms of the notice. [S.Y. 2003, c. 13, s. 57] [L.Y. 2003, ch. 13, art. 57] Page 24 UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON c Placer Mining Act Loi sur l’extraction de l’or PART 1 PARTIE 1 Section 58 Article 58 58 Adjudication of mining recorder (Décision du registraire minier) 58 Adjudication of mining recorder 58 Décision du registraire minier The mining recorder shall, on the day and at the time Ce jour-là et à cette même heure, le registraire doit referred to in section 57, proceed to adjudicate on the rendre sa décision sur la demande. Contre preuve application, and may, with the approval of the Minister, satisfaisante que l’avis a été publié de la manière on proof to the Minister’s satisfaction of the posting of prévue à l’article 56, que le requérant est capable de the notice in the manner described in section 56, of the construire les ouvrages nécessaires, qu’en vertu des ability of the applicant to construct the necessary dispositions précédentes de la présente partie ou de works, of the right of the applicant to apply for a l’une d’elles il a le droit de solliciter une concession record under the provisions of this Part and of the hydraulique et que le volume d’eau non verbalisé peut volume of unrecorded water available for diversion être détourné, eu égard aux droits et actes de having regard to existing rights and records, whether concession existants dont jouissent les propriétaires de held by land owners or mine owners, and to pending terrains ou les propriétaires de mines ainsi qu’aux applications, which facts shall be reported on by the demandes pendantes, faits qui doivent être rapportés mining recorder, issue to the applicant a grant, in par le registraire minier, celui-ci peut, avec Form 4 of Schedule 1, of such amount of water and for l’approbation du ministre, accorder au requérant un such purposes as, in the discretion of the mining acte de concession, rédigé conformément à le recorder, are reasonably required by the applicant for formulaire 4 de l’annexe 1, pour la quantité d’eau et the purposes specified in his or her notice of pour telles autres fins qu’au jugement du registraire application. minier le requérant peut raisonnablement exiger pour l’exécution des objets mentionnés dans son avis de demande. [S.Y. 2003, c. 13, s. 58] [L.Y. 2003, ch. 13, art. 58] 59 Powers of mining recorder (Pouvoirs du registraire minier) 59 Powers of mining recorder 59 Pouvoirs du registraire minier A mining recorder may adjourn the adjudication of an Le registraire minier peut différer cette décision selon application for a water grant from time to time as que les circonstances rendent la chose opportune, et circumstances render expedient, and may take peut recevoir des dépositions par déclaration evidence by statutory declaration, summon and solennelle, assigner et interroger des témoins sous la examine witnesses on oath and hear all parties whose foi du serment, et entendre toutes les parties sur les rights are or may be affected by the application. droits desquels la demande a ou peut avoir un effet. [S.Y. 2003, c. 13, s. 59] [L.Y. 2003, ch. 13, art. 59] 60 Waste or excess (Gaspillage ou excès) 60 Waste or excess 60 Gaspillage ou excès (1) Every holder of a water grant shall take all (1) Toute personne qui détient une concession reasonable means for utilising the water granted to hydraulique doit prendre tous les moyens raisonnables them, and if they wilfully waste any water or take a d’utiliser l’eau à elle concédée, et si, de propos quantity of water in excess of their actual délibéré, elle gaspille de l’eau ou en prend plus que requirements, or have worked out or abandoned the pour ses besoins réels, ou a épuisé et abandonné le ou claim or claims with respect to which the water grant les claims à l’égard desquels la concession hydraulique was issued, a mining inspector may, on notice, cancel a été accordée, l’inspecteur des exploitations minières or reduce the grant or impose such conditions as the peut, après avis, révoquer ou réduire la concession, ou inspector thinks proper. imposer les conditions qu’il juge utiles. (2) An appeal may be taken, at any time within ten (2) Dans les dix jours qui suivent l’acte de l’inspecteur days from any action of the mining inspector under des exploitations minières, il peut être interjeté appel subsection (1), to the Minister. de cet acte devant le ministre. [S.Y. 2003, c. 13, s. 60] [L.Y. 2003, ch. 13, art. 60] c UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON Page 25 Placer Mining Act Loi sur l’extraction de l’or PART 1 PARTIE 1 Section 61 Article 61 61 Rights saved (Droits sauvegardés) 61 Rights saved 61 Droits sauvegardés Every grant of water on an occupied creek is subject to Toute concession hydraulique sur un ruisseau occupé the rights of such owners of claims as shall, at the time doit être assujettie aux droits des propriétaires de of the grant, be working on the stream above or below claims qui, à la date de cette concession, travaillent sur the ditch-head, and of any other persons lawfully using le cours d’eau en amont ou en aval de la tête du fossé, the water for any purpose whatever. et de toutes les autres personnes qui se servent légalement de cette eau pour quelque objet que ce soit. [S.Y. 2003, c. 13, s. 61] [L.Y. 2003, ch. 13, art. 61] 62 Water rights of owners of claims (Quantité d’eau à laquelle a droit l’exploitant d’un claim) 62 Water rights of owners of claims 62 Quantité d’eau à laquelle a droit l’exploitant d’un claim (1) If, after a water grant has been made, any person (1) Si, après avoir fait la concession, une ou plusieurs or persons locate and work in good faith any claim or personnes localisent et exploitent de bonne foi un ou claims below the ditch-head on any stream that has plusieurs claims en aval de la tête du fossé, sur un been diverted, they are collectively entitled to the cours d’eau ainsi détourné, elles ont collectivement continuous flow in the stream of the water passing the droit à l’écoulement continu de l’eau qui passe à claim or claims to the following extent travers le ou les claims dans ce cours d’eau, et ce, dans la mesure qui suit : (a) if three hundred inches or less are diverted, a) s’il en est détourné 300 pouces ou moins, elles they are entitled to not more than forty ont droit à 40 pouces, au maximum; inches, and (b) if over three hundred inches are diverted, they b) s’il en est détourné plus de 300 pouces, elles are entitled to not more than sixty inches, ont droit à 60 pouces, au maximum. except, in either case, on paying to the owner of the Toutefois, dans l’un et l’autre cas, elles ont droit à ditch and all other persons interested in it davantage si elles payent, au propriétaire du fossé et à compensation equal to the amount of damage toutes les autres personnes qui y détiennent un intérêt, sustained by the continuous flow of such extra quantity une indemnité égale au préjudice éprouvé par of water as is desired, and in computing that damage l’écoulement continu de la quantité d’eau qu’elles the loss sustained by the owners of those claims using veulent en supplément. Dans l’estimation de ce water from the ditch, and all other reasonable losses, préjudice, il est tenu compte de la perte subie par les shall be considered. propriétaires de ces claims qui utilisent l’eau du fossé, ainsi que de toutes les autres pertes raisonnables. (2) The right to the continuous flow and to the extra (2) Le droit à ce débit continu et à cette quantité d’eau quantity of water referred to in subsection (1) is supplémentaire est, dans tous les cas, subordonné à subject in all cases to the approval in writing of the l’approbation écrite du registraire minier, sous réserve mining recorder, subject to appeal to the Minister d’un appel devant le ministre dans les vingt jours à within twenty days from the date of the decision compter de la décision rendue. rendered. [S.Y. 2003, c. 13, s. 62] [L.Y. 2003, ch. 13, art. 62] Page 26 UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON c Placer Mining Act Loi sur l’extraction de l’or PART 1 PARTIE 1 Section 63 Article 63 63 Distribution of water (Distribution de l’eau) 63 Distribution of water 63 Distribution de l’eau The holder of a water grant with the privilege of selling Le détenteur d’une concession hydraulique qui jouit du water may distribute the water to such persons and on privilège de vendre de l’eau peut distribuer cette eau such terms as they deem advisable, within the limits aux personnes et aux conditions qu’il juge favorables, mentioned in their grant, but the price charged for the dans les limites mentionnées dans l’acte de concession; water is subject to the control of the Minister, and the mais le prix exigé pour cette eau est contrôlé par le water shall be supplied to all owners of claims who ministre, et l’eau doit être fournie à tous les make application therefor in a fair proportion and propriétaires de claims qui en font la demande, dans according to priority of application. une juste proportion et selon l’ordre des demandes. [S.Y. 2003, c. 13, s. 63] [L.Y. 2003, ch. 13, art. 63] 64 Rules for measurement of water (Règles à observer pour le mesurage de l’eau) 64 Rules for measurement of water 64 Règles à observer pour le mesurage de l’eau In measuring water in any ditch or sluice, the following En mesurant l’eau dans un fossé ou dans une conduite rules shall be observed d’amenée, il faut observer les règles suivantes : (a) the water taken into a ditch or sluice shall be a) l’eau introduite dans un fossé ou une conduite measured at the ditch or sluice head; d’amenée doit être mesurée à la tête du fossé ou de la conduite d’amenée; (b) no water shall be taken into a ditch or sluice b) il ne doit être introduit d’eau dans un fossé ou except in a trough placed horizontally at the dans une conduite d’amenée que par un godet place at which the water enters it; placé horizontalement à l’endroit où l’eau y pénètre; (c) one inch of water means one-half the quantity c) un pouce d’eau est la moitié de la quantité of water that will pass through an orifice two d’eau pouvant passer par un orifice de deux inches high by one inch wide with a constant pouces de haut sur un pouce de large sous la head of seven inches above the upper side of pression constante de sept pouces en amont du the orifice; and côté supérieur de l’orifice; (d) a sluice head shall consist of fifty inches of d) une tête de conduite d’amenée consiste water. en 50 pouces d’eau. [S.Y. 2003, c. 13, s. 64] [L.Y. 2003, ch. 13, art. 64] 65 Construction of culverts (Construction de ponceaux) 65 Construction of culverts 65 Construction de ponceaux The owner of any ditch, water privilege, or claim shall, Le propriétaire d’un fossé, d’un privilège hydraulique at their own expense, construct, secure, and maintain ou d’un claim doit, à ses propres frais, construire, all culverts necessary for the passage of waste and affermir et entretenir tous les ponceaux nécessaires au superfluous water flowing through or over the ditch, passage de l’eau inutilisée et superflue qui coule par ce water privilege or claim. fossé, ce privilège ou ce claim. [S.Y. 2003, c. 13, s. 65] [L.Y. 2003, ch. 13, art. 65] c UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON Page 27 Placer Mining Act Loi sur l’extraction de l’or PART 1 PARTIE 1 Section 66 Article 66 66 Duty of owner (Devoirs du propriétaire) 66 Duty of owner 66 Devoirs du propriétaire The owner of any ditch or water privilege shall Le propriétaire d’un fossé ou d’un privilège hydraulique construct and secure it in a proper and substantial doit le construire et l’affermir d’une manière manner and maintain it in good repair, to the convenable et solide, et l’entretenir en bon état, à la satisfaction of a mining recorder, and so that no satisfaction du registraire minier, et de telle sorte damage shall occur to any road or work in its vicinity qu’aucun chemin ou aucune installation dans le from any part of the works of the ditch or water voisinage n’ait à souffrir de quelque partie que ce soit privilege. des ouvrages de ce fossé ou de ce privilège hydraulique. [S.Y. 2003, c. 13, s. 66] [L.Y. 2003, ch. 13, art. 66] 67 Liability of owners (Propriétaires responsables des dégâts) 67 Liability of owners 67 Propriétaires responsables des dégâts (1) The owner of any ditch or water privilege is liable (1) Le propriétaire d’un fossé ou d’un privilège for, and shall make good in such manner as a mining hydraulique est responsable de tous les dégâts recorder determines, all damages that may be auxquels peut donner lieu la rupture ou l’imperfection occasioned by or through any part of the works of the d’une partie quelconque des ouvrages de ce fossé ou de ditch or water privilege breaking or being imperfect. ce privilège hydraulique, et il doit réparer ces dommages de la manière que détermine le registraire minier. (2) An appeal from the determination of a mining (2) Dans les dix jours, il peut être interjeté appel recorder under this section may be taken at any time devant le ministre de la décision rendue par le within ten days to the Minister. registraire minier, sous l’autorité du présent article. [S.Y. 2003, c. 13, s. 67] [L.Y. 2003, ch. 13, art. 67] 68 Transfer includes water privileges (Transfert d’un claim et privilèges hydrauliques) 68 Transfer includes water privileges 68 Transfert d’un claim et privilèges hydrauliques Every grant of water obtained by the owner of a claim Toute concession hydraulique obtenue par le shall be deemed appurtenant to the claim in respect of propriétaire d’un claim est réputée appartenir au claim which the grant is obtained, and all assignments, à l’égard duquel cette concession est obtenue, et toutes transfers, or conveyances permitted by law of any cessions, tous transferts ou tous transports d’un claim claim shall be construed to have conveyed and que la loi permet de faire sont réputés avoir transporté transferred, and to convey and transfer, any and all ou transféré, et transportent ou transfèrent, tous les recorded water privileges appurtenant to the claim privilèges hydrauliques enregistrés qui dépendent du assigned, transferred, or conveyed. claim cédé, transféré ou transporté. [S.Y. 2003, c. 13, s. 68] [L.Y. 2003, ch. 13, art. 68] Page 28 UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON c Placer Mining Act Loi sur l’extraction de l’or PART 1 PARTIE 1 Section 69 Article 69 69 Ground for reservoirs (Terrain pour réservoir) 69 Ground for reservoirs 69 Terrain pour réservoir The Minister may, when approving an application for Dès qu’il a approuvé la demande d’autorisation permission to impound the surplus waters of any creek d’endiguer l’excédent des eaux d’un ruisseau ou d’un or gulch, withdraw from mining entry any vacant ravin, le ministre peut soustraire l’inscription minière ground required as a reservoir site or for any other de tout terrain vacant s’avérant nécessaire à purpose in connection with the storage of water, but l’établissement d’un réservoir ou à tout autre objet only ground that has been thoroughly prospected and relatif à l’emmagasinage de l’eau; mais, seuls les found to be worthless for placer mining purposes, or terrains qui, après avoir été prospectés à fond et ground that has been worked out and abandoned, may s’étant avérés sans valeur pour l’exploitation minière, be so withdrawn. ou les terrains qui ont été épuisés et abandonnés, peuvent être ainsi soustraits à l’inscription. [S.Y. 2003, c. 13, s. 69] [L.Y. 2003, ch. 13, art. 69] 70 Application of sections 54 to 69 (Application des articles 54 à 69) 70 Application of sections 54 to 69 70 Application des articles 54 à 69 Sections 54 to 69 cease to have any force or effect Les articles 54 à 69 cessent d'être en vigueur, ou within a water management area on the establishment d'avoir effet, dans une zone de gestion des eaux lors de of such area by the Commissioner in Executive Council l'établissement d'une telle zone par le commissaire en under the Waters Act. conseil exécutif, en conformité avec la Loi sur les eaux. [S.Y. 2003, c. 13, s. 70] [L.Y. 2003, ch. 13, art. 70] 71 Grant of right to run drains (Droit d’établir des canaux d’écoulement) 71 Grant of right to run drains 71 Droit d’établir des canaux d’écoulement A mining recorder may grant permission to run a drain Pour la construction et l’entretien de conduites or tunnel for drainage purposes through any occupied destinées au drainage, le registraire minier peut or unoccupied lands, whether mineral or not, and may accorder la permission de diriger une conduite, ou un give exclusive rights-of-way through and entry on any canal souterrain d’écoulement, à travers tous les mining ground for any term not exceeding five years terrains occupés ou inoccupés, qu’ils soient miniers ou for the purpose of constructing and maintaining drains non, et il peut concéder des droits exclusifs pour passer for the drainage of the mining ground. sur tout terrain minier pendant une période maximale de cinq ans. [S.Y. 2003, c. 13, s. 71] [L.Y. 2003, ch. 13, art. 71] 72 Compensation (Dédommagement) 72 Compensation 72 Dédommagement Every person granted permission to run a drain or Avant le début des travaux de construction, le tunnel shall pay, before construction of the drain or cessionnaire doit indemniser les propriétaires des tunnel commences, monetary compensation to the terrains ou des claims sur lesquels il passe de tout owner of the land or of any claim entered on by that préjudice qu’ils peuvent subir du fait de la construction person for any damage they may sustain by the de la conduite ou du canal souterrain. Le construction of the drain or tunnel, and the dédommagement, s’il n’en est pas convenu, est fixé : compensation, if not agreed on, shall be settled by (a) in the case of a dispute with the owner of the a) en cas de différend avec le propriétaire du land, the Yukon Surface Rights Board in terrain, par l’Office des droits de surface du accordance with the Yukon Surface Rights Yukon, en conformité avec la Loi sur l’Office des Board Act (Canada); and droits de surface du Yukon (Canada); c UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON Page 29 Placer Mining Act Loi sur l’extraction de l’or PART 1 PARTIE 1 Section 73 Article 73 (b) in the case of a dispute with the owner of a b) en cas de différend avec le propriétaire d’un claim, the board of arbitrators referred to in claim, par le conseil d’arbitrage mentionné à section 77. l’article 77. [S.Y. 2003, c. 13, s. 72] [L.Y. 2003, ch. 13, art. 72] 73 Property of constructor (Propriété de celui qui les construit) 73 Property of constructor 73 Propriété de celui qui les construit The drain or tunnel referred to in section 71, when Une fois leur construction terminée, la conduite ou le constructed, shall be deemed to be the property of the canal souterrain mentionné à l’article 71 est réputé être person who constructed it. la propriété de la personne qui l’a construit. [S.Y. 2003, c. 13, s. 73] [L.Y. 2003, ch. 13, art. 73] 74 Application (Demande) 74 Application 74 Demande (1) Every application for a grant of permission to (1) Toute demande de permission de construire une construct a drain or tunnel shall state the names of the conduite ou un canal souterrain doit énoncer le nom applicants, the nature and extent of the proposed drain des requérants, la nature et l’étendue de la conduite ou or tunnel, the amount of toll, if any, to be charged and du canal souterrain projeté, le montant de la taxe à the privileges sought to be acquired, and shall, except exiger, s’il y a lieu, et les privilèges que l’on se propose where the drain or tunnel is intended only for the d’acquérir, et, sauf lorsque la conduite, ou le canal drainage of the claim of the person constructing it, be souterrain, est destinée à assécher uniquement le claim accompanied by a deposit of twenty-five dollars, which de la personne qui l’a construit, la demande doit être shall be refunded if the application is refused, but not accompagnée d’un dépôt de 25 $ qui sera remboursé otherwise. seulement si la demande est rejetée. (2) Ten full days notice shall be given of any (2) Un préavis de dix jours francs est requis pour cette application for a grant under subsection (1) to be made demande si elle est faite en juin, juillet, août, in June, July, August, September or October, and one septembre ou octobre, et un avis d’un mois est requis month’s notice of an application to be made in any si elle est faite au cours d’un autre mois, au moyen other month, by affixing the notice to a post planted in d’un avis fixé à un poteau planté dans une partie bien a conspicuous part of the ground and by affixing a copy en vue du terrain, et d’une copie affichée bien en vue of it conspicuously on the inner walls of the office of sur un mur intérieur du bureau du registraire minier. the mining recorder. (3) Prior to the application for a grant under (3) Antérieurement à cette demande, le terrain subsection (1), the ground included in it shall be concerné doit être marqué à la satisfaction du marked out to the satisfaction of the mining recorder. registraire minier. (4) Any person may, within the times prescribed for (4) Toute personne peut, au cours des périodes the notice of an application for a grant under prescrites pour l’avis de la demande, et non pas après, subsection (1) but not afterwards, protest to the faire opposition à l’octroi de cette demande devant le Minister against the application being granted. ministre. [S.Y. 2003, c. 13, s. 74] [L.Y. 2003, ch. 13, art. 74] 75 Form of grant (Forme de la concession) 75 Form of grant 75 Forme de la concession (1) The grant of the right-of-way to construct drains (1) L’acte de concession du droit de passage pour and tunnels shall be in Form 5 of Schedule 1. construire des conduites et des canaux souterrains doit être rédigé selon le formulaire 5 de l’annexe 1. Page 30 UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON c Placer Mining Act Loi sur l’extraction de l’or PART 1 PARTIE 1 Section 76 Article 76 (2) The grant referred to in subsection (1) shall be (2) Le concessionnaire fait enregistrer son acte au registered by the grantee in the office of the mining bureau du registraire minier, à qui il paie alors un droit recorder, to whom the grantee shall at the time pay a de cinq dollars, ou, si l’acte de concession l’autorise à fee of five dollars, or, if the grant gives power to collect percevoir des taxes, un droit de 40 dollars. tolls, a fee of forty dollars. (3) An annual rent of ten dollars shall be paid, in (3) Le concessionnaire paie, d’avance, pour le droit de advance, by the grantee referred to in this section for passage qu’il possède légalement, une redevance each quarter of a mile of right-of-way they legally hold, annuelle de 10 dollars par quart de mille, sauf si la except where the drain is for the purpose of draining conduite a pour objet de n’assécher que le claim de la only the claim of the person constructing it. personne qui l’a construite. [S.Y. 2003, c. 13, s. 75] [L.Y. 2003, ch. 13, art. 75] 76 Title (Titres) 76 Title 76 Titres In case of any dispute respecting the location of a S’il existe un différend au sujet de la localisation d’un claim, the title to the claim shall depend on priority of claim, le titre de propriété du claim est reconnu selon the location, subject to any question respecting the la priorité de cette localisation, sous réserve de toute validity of the record itself and to the claimant having contestation quant à la validité de l’inscription elle- complied with all the terms and conditions of this Part. même, et à condition que le demandeur se soit conformé à toutes les modalités de la présente partie. [S.Y. 2003, c. 13, s. 76] [L.Y. 2003, ch. 13, art. 76] 77 Board of arbitrators (Conseil d’arbitrage) 77 Board of arbitrators 77 Conseil d’arbitrage (1) In the event of any dispute between the owners of (1) Advenant des différends entre les propriétaires de claims or lessees of locations with respect to the claims ou les locataires de terrains à l’égard de la distribution of water, encroachments, or dumping, or distribution de l’eau, des empiétements, de la décharge to the amount of compensation to be paid for any ou de l’indemnité à verser pour les dommages damage caused by any drain or tunnel constructed for occasionnés par la conduite, ou par le canal souterrain drainage purposes under this Part, or to any other construit pour le drainage, sous l’autorité de la matter referred to in section 78, the dispute may be présente partie, ou de tout autre élément mentionné à heard and determined by a board of arbitrators. l’article 78, ces différends sont entendus et réglés par un conseil d’arbitrage. (2) The Minister, on the request of any owner or lessee (2) Après avoir reçu, de la part de ces propriétaires, ou referred to in subsection (1) for the appointment of a de ces locataires, une demande de nomination d’un board of arbitrators and on being furnished with a conseil d’arbitrage, accompagné d’une déclaration statement of the matter complained of, clearly énonçant clairement par écrit l’objet de la plainte, le expressed in writing, shall ministre : (a) notify each party to the dispute to appoint an a) donne, à chaque partie au différend, avis de arbitrator; and nommer un arbitre; (b) notify all persons holding any interest in the b) signifie, à toutes les personnes qui possèdent claim or property of the proposed arbitration un intérêt dans le claim ou dans la propriété proceedings, minière, un avis des procédures d’arbitrage projetées. c UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON Page 31 Placer Mining Act Loi sur l’extraction de l’or PART 1 PARTIE 1 Section 78 Article 78 and where any person who was notified to appoint Si la personne qui a reçu avis de nommer un arbitre refuses or neglects to appoint an arbitrator within refuse ou néglige de le faire dans les trente jours à thirty days after the date of the notification, the compter de la date de cet avis, le ministre doit nommer Minister, on being requested to do so by the arbitrator cet arbitre ou ces arbitres, sur demande à cet effet par or arbitrators appointed, or by any interested owner or l’arbitre ou les arbitres nommés, ou par tout lessee, shall appoint the arbitrator or arbitrators. propriétaire ou locataire intéressé. (3) In the event that the total number of arbitrators (3) Lorsque le nombre total des arbitres ainsi nommés appointed under subsection (2) is an even number, an forme un nombre pair, ces arbitres doivent nommer un additional arbitrator shall be appointed by those arbitre supplémentaire. arbitrators. (4) In the event that the total number of arbitrators (4) Si les arbitres ainsi choisis forment un nombre pair appointed under subsection (2) is an even number and et s’ils sont incapables de s’accorder sur le choix de the arbitrators are unable to agree on the additional l’arbitre supplémentaire, ou s’ils négligent de le faire arbitrator or fail to do so within five days from the date dans les cinq jours à compter de la nomination du on which the last arbitrator was appointed, the dernier arbitre choisi, le ministre doit nommer l’arbitre Minister, on being requested to do so by the arbitrators supplémentaire, à invitation des arbitres déjà choisis already appointed or by any interested owner or lessee, ou sur invitation d’un des propriétaires ou des shall appoint the additional arbitrator. locataires intéressés. (5) The arbitrators are entitled to be paid a per diem (5) Les arbitres ont le droit de recevoir une allocation allowance of ten dollars, together with necessary travel de 10 dollars par jour, le remboursement des frais de and living expenses, while actually engaged in an déplacement et de séjour nécessaires pendant qu’ils arbitration, and the costs of the arbitration, including s’occupent réellement de l’arbitrage; les frais de cet the cost of any examination of the property that may arbitrage, y compris les frais de tout examen de be found necessary, shall be borne by the owners or propriété jugé nécessaire, sont supportés par les lessees who are parties to the dispute and in the propriétaires ou les locataires qui sont parties au proportion set out in the award of the arbitrators. différend, et ce, dans la proportion établie par la sentence des arbitres. (6) The procedure in all cases before a board of (6) Dans tous les cas, la procédure soumise à un arbitrators under this Part shall be in accordance with conseil d’arbitrage sous le régime de la présente partie rules prepared by the Minister. doit se conformer aux règles élaborées par le ministre. [S.Y. 2003, c. 13, s. 77] [L.Y. 2003, ch. 13, art. 77] 78 Damages by dumping, etc. (Dommages à d’autres claims, etc.) 78 Damages by dumping, etc. 78 Dommages à d’autres claims, etc. Except as provided in this Part, no person mining on Sous réserve des autres dispositions de la présente any claim shall cause damage or injury to the holder of partie, nulle personne qui exploite un claim ne doit any claim other than their own by throwing earth, clay, causer de dommage ou de préjudice au détenteur de stones, or other material on the other claim or by tout autre claim que le sien, en jetant de la terre, de causing or allowing water that may be pumped or l’argile, des pierres ou d’autres matières sur cet autre bailed or that may flow from their own claim to flow claim, ou en faisant couler ou en laissant couler, dans into or on the other claim. ou sur cet autre claim, de l’eau qui peut être pompée ou vidée ou qui peut couler de son propre claim.
Part document.segment-4
Placer Mining Act (Extraction de l’or) — segment 4
- document.segment-4 Verify source ↗
Placer Mining Act (Extraction de l’or) — segment 4
This part sets rules for placer claims, prospecting leases, royalties on exported gold, enforcement, and entry restrictions on land.
(2) If the owner of a claim wishes to deposit the (2) Si le propriétaire d’un claim désire déposer des leavings, deads, waste, or tailings therefrom on any résidus, des matières stériles, des déchets, des adjacent claim or on any other adjacent mining grenailles ou des résidus provenant de son claim sur un property, whether the claim or mining property was claim voisin, ou sur tout autre terrain minier contigu, acquired under this Part or any other Act, order in que ce claim voisin ou ce terrain minier contigu ait été council, or regulation governing mining in the Yukon, acquis sous le régime des dispositions de la présente which claim or mining property is of not less than five partie, ou de toute autre loi, ou d’un décret, ou d’un Page 32 UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON c Placer Mining Act Loi sur l’extraction de l’or PART 1 PARTIE 1 Section 79 Article 79 years standing, or if the owner wishes to cause or règlement régissant l’exploitation minière au Yukon, et allow water that may be pumped or bailed or that may s’ils datent d’au moins cinq ans, ou si ce propriétaire flow from his or her own claim to flow into or on the désire faire couler, ou laisser couler, de l’eau qui peut other claim or mining property, he or she may give one être pompée ou vidée, ou qui peut couler de son claim month‘s notice of that wish in writing to the owner or sur cet autre claim ou terrain minier, ce propriétaire lessee of that adjacent claim or mining property. peut adresser par écrit un préavis d’un mois, à cet effet, au propriétaire ou au locataire du claim ou du terrain minier contigu. (3) If, at the expiration of the month referred to in (3) Si, à l’expiration du mois, le propriétaire qui donne subsection (2), the owner giving the notice and the cet avis et le propriétaire, ou le locataire de ce claim, owner or lessee of the adjacent claim or mining ou de ce terrain minier contigu, ne peuvent s’entendre property has not been able to arrive at an agreement sur le prix à payer pour le terrain de la décharge, le respecting the price to be paid for the dumping ground propriétaire qui donne l’avis peut s’adresser au or for damages caused by the flow of water, the owner ministre pour faire déterminer par le conseil giving notice may apply to the Minister to have the d’arbitrage la valeur et les dimensions du terrain de la value and size of the dumping ground and the amount décharge ainsi que le montant de ces dommages, et le of the damages determined by the board of arbitrators, conseil a le pouvoir de permettre d’utiliser comme and the board has power to permit so much of the terrain de décharge la partie de ce claim ou de ce adjacent claim or mining property to be used for terrain minier contigu qui lui paraît juste, et ce, au prix dumping and at such a price as the board of qu’il juge équitable. arbitrators deems just. [S.Y. 2003, c. 13, s. 78] [L.Y. 2003, ch. 13, art. 78] 79 Judgement of the board (Décision du conseil) 79 Judgement of the board 79 Décision du conseil (1) The judgement of the board of arbitrators shall be (1) La décision du conseil d’arbitrage doit être écrite et in writing and shall be filed in the office of the mining produite au bureau du registraire minier. recorder. (2) Any judgement of the board of arbitrators is final (2) Cette décision est définitive quant aux faits, mais il as to facts, but may be appealed to the Supreme Court peut en être interjeté appel devant la Cour suprême sur on any question of law. toute question de droit. [S.Y. 2003, c. 13, s. 79] [L.Y. 2003, ch. 13, art. 79] 80 Costs of inquiry (Frais de l’enquête) 80 Costs of inquiry 80 Frais de l’enquête The board of arbitrators may award such costs of and Le conseil d’arbitrage peut adjuger les frais incidental to an inquiry as it deems just. occasionnés par l’enquête et les frais annexes, selon ce qu’il juge équitable. [S.Y. 2003, c. 13, s. 80] [L.Y. 2003, ch. 13, art. 80] c UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON Page 33 Placer Mining Act Loi sur l’extraction de l’or PART 1 PARTIE 1 Section 81 Article 81 81 Death or insanity of owner (Décès ou aliénation mentale du propriétaire) 81 Death or insanity of owner 81 Décès ou aliénation mentale du propriétaire Where the owner of a claim or of any interest in a Lorsque le propriétaire d’un claim, ou de tout intérêt claim dies or is adjudged to be insane, the provisions dans un claim, meurt ou s’il est déclaré atteint of this Part respecting forfeiture for non-performance d’aliénation mentale, les dispositions de la présente of work, payment of fees, and renewal do not apply partie relatives à la déchéance pour inexécution des except as provided in this Part, in the first case, either travaux, pour le paiement des droits et pour le during the last illness or after the death of that owner, renouvellement ne s’appliquent pas, sauf dans la and in the second case, either after that owner has mesure prévue à la présente partie, dans le premier been adjudged insane or, if it appears that the neglect cas, soit durant sa dernière maladie, soit après son or omission on account or by reason of which the claim décès, et, dans le deuxième cas, après qu’il ait été ainsi would otherwise have been deemed to be forfeited was déclaré aliéné, ou, s’il est constaté que la négligence ou attributable to their insanity, during such period prior l’omission, à cause ou en raison de laquelle ce claim to them having been adjudged insane as they may be aurait autrement été réputé déchu était attribuable à shown to have been insane. son aliénation mentale, pour la période durant laquelle sa démence a pu être constatée avant qu’il en ait été déclaré atteint. [S.Y. 2003, c. 13, s. 81] [L.Y. 2003, ch. 13, art. 81] 82 Powers of Minister over property (Pouvoirs du ministre au sujet des biens) 82 Powers of Minister over property 82 Pouvoirs du ministre au sujet des biens (1) The Minister may, by order, limit the period during (1) Le ministre peut, par ordonnance, limiter la which all or any interest in any mining claim, the période durant laquelle l’intérêt total ou partiel dans un property of a deceased or insane person, shall be claim minier appartenant à cette personne décédée ou exempt from the provisions of this Part that require the démente est ainsi exempt des dispositions de la annual performance of work and payment of fees and présente partie, laquelle requiert l’exécution annuelle may fix the date on which it shall again become subject de travaux et le paiement de droits; il peut fixer la date to all the provisions of this Part and on which renewal à laquelle le claim minier redevient sujet à toutes les grants for the property shall be issued on payment of dispositions de la présente partie, et à laquelle le the prescribed fee. renouvellement de la concession de cette propriété doit être accordé contre paiement du droit prescrit. (2) On failure to renew the grants referred to in (2) À défaut de ce renouvellement, le titre du subsection (1), the title of the owner of the property propriétaire de cette propriété devient alors shall thereupon become absolutely forfeited and absolument déchu, et : (a) where the estate of the deceased person is the a) dans le cas où la succession de cette personne sole owner of the claim, the claim shall décédée est l’unique propriétaire de ce claim, forthwith be open for relocation without any ce claim est immédiatement sujet à une declaration of cancellation or forfeiture on the location nouvelle, sans aucune déclaration de part of the Commissioner; and révocation ou de déchéance de la part du Commissaire; (b) where the estate is a co-owner in the claim, the b) lorsque cette succession est copropriétaire de interest of the estate thereupon becomes ce claim, l’intérêt de la succession est alors vested in the other co-owners in proportion to dévolu aux autres copropriétaires, en their respective interests. proportion de leurs intérêts. (3) The Minister may, by order, from time to time, (3) Le ministre peut, par ordonnance, proroger la extend the period of the exemption referred to in période de cette exemption, selon que les circonstances subsection (1) as the necessity of the case may in the peuvent, à son avis, l’exiger, mais, dans le cas de Minister’s opinion require but, in the case of deceased personnes décédées, la période durant laquelle cette Page 34 UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON c Placer Mining Act Loi sur l’extraction de l’or PART 1 PARTIE 1 Section 83 Article 83 persons, the period during which the exemption applies exemption s’applique ne peut dépasser trois ans à shall not extend beyond three years from the date of compter de la date du décès de la personne. the death of the deceased. (4) Where there is no legal representative of the estate (4) S’il n’existe pas de représentant légal pour la of any deceased or insane person, the Minister may succession de la personne décédée ou démente, le cause the public administrator to take possession of the ministre peut assigner à l’administrateur public de estate and administer it, subject to the provisions of prendre possession des biens de cette personne any Act respecting the administration of the estates of relativement à un claim, et les administrer, sous deceased or insane persons in the Yukon. réserve de toute loi concernant l’administration des biens de personnes décédées ou démentes au Yukon. (5) No exemption of the interest of a deceased or (5) Nulle exemption de l’intérêt, dans un claim, d’un insane owner in any claim applies to or exempts any propriétaire décédé ou dément ne s’applique à l’intérêt co-owner’s interest from the provisions of this Part d’un copropriétaire ni ne l’exempte des dispositions de with respect to the annual performance of work and la présente partie quant à l’exécution des travaux payment of renewal fees. annuels et au paiement des droits de renouvellement. (6) Where the estate of a deceased or insane person (6) Lorsque la succession d’une personne décédée ou owns an interest in a claim and all the living co-owners démente possède un intérêt dans un claim et que tous have, during the period of the exemption referred to in les copropriétaires vivants ont, durant la période this section, failed to perform the required work or to d’exemption, négligé de faire les travaux requis ou de pay renewal fees, the interests of those co-owners payer les droits de renouvellement, les intérêts de ces may, on that failure being proved to the satisfaction of copropriétaires peuvent, sur preuve de cette the Minister after notice of hearing has been served on négligence, établie à la satisfaction du ministre, après all parties interested in the manner directed by the signification de l’avis de l’audience à toutes les parties Minister, be vested in the estate by order of the intéressées, de la manière par lui prescrite, être Minister. attribués à cette succession, par ordre du ministre. [S.Y. 2003, c. 13, s. 82] [L.Y. 2003, ch. 13, art. 82] 83 Charges and expenses (Frais et dépens) 83 Charges and expenses 83 Frais et dépens All charges and expenses that may be incurred by the Tous les frais et dépens que le ministre ou Minister or the public administrator, or by any person l’administrateur public, ou une personne agissant sous acting under the instructions of either of them, in or les ordres de l’un d’eux, peut encourir en exploitant about the working of a mining property, or in taking or une propriété minière, ou à son sujet, ou en prenant ou keeping possession thereof, are and remain a first en gardant possession de cette propriété, constituent charge against that property until paid to the Minister une première charge sur cette propriété tant qu’ils ne or public administrator, as the case may be. sont pas remboursés au ministre, ou à l’administrateur public, selon le cas. [S.Y. 2003, c. 13, s. 83] [L.Y. 2003, ch. 13, art. 83] 84 Assignee to apply for grant within two months (Le cessionnaire doit demander concession dans un délai de deux mois) 84 Assignee to apply for grant within two 84 Le cessionnaire doit demander concession months dans un délai de deux mois (1) Any person who receives from the public (1) Toute personne qui reçoit, de l’administrateur administrator, or other legal representative of the public ou d’un autre représentant légal de la succession estate of a deceased or insane person, an assignment d’une personne décédée ou démente, une cession ou le or transfer of a claim or interest in a claim that has transport d’un claim, ou d’un intérêt dans un claim been exempted from the provisions of this Part with exempté des dispositions de la présente partie quant à respect to performance of work and payment of l’exécution de travaux et au paiement de droits de renewal fees by reason of the death or insanity of the renouvellement par suite du décès ou de l’aliénation owner of the claim or interest shall apply to a mining mentale du propriétaire de ce claim, ou de cet intérêt, c UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON Page 35 Placer Mining Act Loi sur l’extraction de l’or PART 1 PARTIE 1 Section 85 Article 85 recorder and pay the prescribed fee for a grant of it doit s’adresser au registraire minier et payer le droit within two months from the date of the assignment or prescrit pour une concession de ce claim dans les deux transfer. mois qui suivent la date de cette cession ou de ce transport. (2) Where a grant is not applied for and the recording (2) Si une concession n’est pas demandée, et si le droit fee paid within the two months specified in d’enregistrement n’est pas versé dans les deux mois subsection (1), the provisions exempting the claim or visés au paragraphe (1), les dispositions qui exemptent interest cease to apply and the claim or interest shall le claim, ou l’intérêt, cessent de s’appliquer; à on the expiration of the two months become absolutely l’expiration du délai de deux mois, ce claim, ou cet forfeited and open for location. intérêt, est absolument déchu, et le claim est de nouveau à localiser. [S.Y. 2003, c. 13, s. 84] [L.Y. 2003, ch. 13, art. 84] 85 Royalty (Redevance) 85 Royalty 85 Redevance (1) There shall be levied and collected on all gold (1) Sur tout or exporté du Yukon, il est appliqué et shipped from the Yukon a royalty at the rate of two perçu une redevance d’un taux de deux pour cent et and one-half per cent of its value, or at such less rate demi de sa valeur, ou d’un taux inférieur, à la as may be fixed by the Commissioner in Executive discrétion du commissaire en conseil exécutif. Council. (2) Gold on which royalty is payable is gold dust as (2) L’or sur lequel la redevance est payable est la mined or gold in the form of bars as presented for poussière d’or à son état naturel ou l’or sous forme de export. lingots tels qu’ils sont présentés pour l’exportation. (3) The royalty imposed by this section shall be paid in (3) La redevance doit être payée, en monnaie légale, currency to the Minister, or other officer named by the au ministre ou à toute personne qu’il peut désigner; Minister, and the gold for the purpose of estimating l’or est évalué à 15 dollars l’once pour le calcul de la that royalty shall be valued at fifteen dollars per ounce. redevance. [S.Y. 2003, c. 13, s. 85] [L.Y. 2003, ch. 13, art. 85] 86 Offence (Infraction) 86 Offence 86 Infraction (1) Every person who exports or attempts to export (1) Quiconque exporte ou tente d’exporter du Yukon de from the Yukon any gold with respect to which the l’or dont la redevance imposée par l’article 85 n’a pas royalty imposed by section 85 has not been paid is été payée, commet une infraction et est passible, sur guilty of an offence and liable on summary conviction déclaration de culpabilité par procédure sommaire, to a fine not exceeding one thousand dollars or to d’une amende maximale de 1 000 dollars ou d’un imprisonment for a term not exceeding three years or emprisonnement d’une durée maximale de trois ans, to both. ou ces deux peines. (2) Where a person is convicted under subsection (1), (2) Lorsqu’une personne est déclarée coupable sous le the convicting magistrate or justice may order the gold régime du paragraphe (1), le magistrat ou le juge de in respect of which the conviction is entered to be paix prononçant la condamnation peut ordonner la forfeited and thereupon the gold is forfeited to the confiscation de l’or identifié dans la déclaration de Commissioner. culpabilité; cette confiscation s’effectue immédiatement au profit du Commissaire. (3) Every person about to export gold from the Yukon (3) Quiconque est sur le point d’exporter de l’or du shall on demand produce to any peace officer a Yukon doit présenter à tout agent de la paix, sur certificate from the Minister, or the person authorized demande, un certificat du ministre ou de la personne by the Minister under subsection 85(3) certifying that autorisée par lui en vertu du paragraphe 85(3) the royalty imposed by section 85 with respect to the attestant le paiement de la redevance imposée par Page 36 UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON c Placer Mining Act Loi sur l’extraction de l’or PART 1 PARTIE 1 Section 87 Article 87 gold has been paid; failure to produce the certificate on l’article 85 à l’égard de cet or. La non-production du demand is evidence that the royalty has not been paid. certificat constitue alors une preuve de non-paiement de la redevance. (4) Where any peace officer believes on reasonable (4) Si un agent de la paix a des motifs raisonnables de grounds that any person has committed or is about to croire qu’une personne a commis, ou est sur le point commit an offence described in subsection (1) or has in de commettre, une infraction décrite au their possession or in their belongings any gold in paragraphe (1), ou qu’elle a en sa possession, ou parmi respect of which the royalty imposed by section 85 has les effets lui appartenant, de l’or pour lequel la not been paid, that peace officer may without warrant redevance imposée à l’article 85 n’a pas été payée, cet search that person and their belongings and any agent peut, sans mandat, fouiller cette personne et ses articles believed to be their belongings and may seize effets personnels ainsi que tous objets tenus pour des any gold found on that person or in their belongings. effets lui appartenant, et peut saisir tout or trouvé sur cette personne ou parmi les effets en question. (5) No female shall be searched pursuant to this (5) Aucune personne du sexe féminin ne peut être section except by a suitable woman who is a peace fouillée conformément au présent article si ce n’est par officer or is authorized by the peace officer to make the une femme qualifiée qui exerce les fonctions d’agent de search. la paix ou qui est autorisée par un agent de la paix à effectuer la perquisition. (6) Any gold seized pursuant to subsection (4) may be (6) Tout or saisi en conformité avec le paragraphe (4) detained for a period of six months and, if before the peut être détenu pendant six mois et, si des procédures expiration of that period any proceedings with respect relatives à cet or sont intentées sous le régime de la to the gold are taken under this Part, may be further présente partie avant l’expiration de cette période, il detained until those proceedings are finally concluded. peut être en outre détenu jusqu’à la fin des procédures. (7) For the purpose of this section, “peace officer” (7) Pour l’application du présent article, « agent de la means a peace officer as defined in section 2 of the paix » s’entend au sens de l’article 2 du Code criminel. Criminal Code. [S.Y. 2003, c. 13, s. 86] [L.Y. 2003, ch. 13, art. 86] 87 Fees (Droits) 87 Fees 87 Droits The fees to be charged in connection with the Les droits à percevoir relativement à l’administration administration of this Part are those set out in de la présente partie sont énoncés à l’annexe 2. Schedule 2. [S.Y. 2003, c. 13, s. 87] [L.Y. 2003, ch. 13, art. 87] 88 Moneys collected (Deniers perçus) 88 Moneys collected 88 Deniers perçus All fees, fines, royalties or other moneys collected Les droits, les amendes, les redevances et tous autres under this Part become part of the Consolidated deniers perçus sous l’autorité de la présente partie font Revenue Fund. désormais partie du Trésor. [S.Y. 2003, c. 13, s. 88] [L.Y. 2003, ch. 13, art. 88] 89 Misrepresentation, removal of legal posts, etc. (Faux exposé, enlèvement de bornes légales, etc.) 89 Misrepresentation, removal of legal 89 Faux exposé, enlèvement de bornes posts, etc. légales, etc. (1) If it is proved to the satisfaction of a mining (1) Le registraire minier peut, à sa discrétion, recorder that any person has ordonner qu’une personne soit privée du droit d’obtenir (a) been guilty of misrepresentation in the une concession, ou le renouvellement d’une concession statement they have sworn to in recording any d’un claim, pour toute période qu’il juge utile, s’il est claim or in any of the statements required établi, à la satisfaction du registraire minier, que cette c UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON Page 37 Placer Mining Act Loi sur l’extraction de l’or PART 1 PARTIE 1 Section 90 Article 90 under this Part to be made under oath, or personne satisfait à l’une des conditions suivantes : (b) removed, or disturbed with intent to remove, a) elle s’est rendue coupable de fausse assertion or defaced any legal post or stake or other dans l’exposé qu’elle a affirmé par serment lors mark placed under the provisions of this Part, de l’inscription d’un claim, ou dans l’une des the mining recorder may order that the person be déclarations que la présente partie lui prescrit debarred from the right to obtain a grant or renewal of de faire sous serment; a grant of a claim for any length of time that the b) elle a enlevé ou dérangé à dessein d’enlever, ou mining recorder deems advisable. elle a dégradé une borne, un pieu ou toute autre marque légale, placée en exécution des dispositions de la présente partie. (2) A mining recorder shall forthwith, on making any (2) Dès qu’il rend une telle décision, le registraire decision under subsection (1), notify every other minier doit en aviser sans délai tous les autres mining recorder of the decision. registraires miniers. (3) An appeal lies from any decision of a mining (3) Il peut être interjeté appel de cette décision du recorder under subsection (1) to the Minister. registraire minier devant le ministre. [S.Y. 2003, c. 13, s. 89] [L.Y. 2003, ch. 13, art. 89] 90 Punishment (Peines) 90 Punishment 90 Peines Any person who wilfully contravenes this Part, or Toute personne qui, délibérément, agit en refuses to obey any lawful order of any official, court, contravention avec la présente partie, ou qui refuse or board having jurisdiction under this Part in mining d’obéir à un ordre légal d’un fonctionnaire, d’un disputes, is, on summary conviction, liable to a fine not tribunal ou d’un conseil ayant compétence, aux termes exceeding two hundred and fifty dollars or to de la présente partie, en matière de différends miniers, imprisonment for a term not exceeding three months. est, sur déclaration de culpabilité par procédure sommaire, passible d’une amende maximale de 250 $ ou d’un emprisonnement maximal de trois mois. [S.Y. 2003, c. 13, s. 90] [L.Y. 2003, ch. 13, art. 90] 91 Application of Act (Application de la loi) 91 Application of Act 91 Application de la loi (1) No person shall be granted or acquire a claim or (1) Nul ne peut acquérir un claim ou un droit dans ce any right in a claim, or carry on placer mining, on claim, obtenir la concession d’un claim ou exploiter un lands in the Yukon, except in accordance with this Part. placer sur des terres au Yukon, si ce n’est conformément à la présente partie. (2) This section does not affect any rights (2) Le présent article n’a pas d’effet sur les droits suivants : (a) that have been acquired under the regulations a) les droits acquis sous le régime du règlement for the disposal of mining locations in the pour la concession des emplacements miniers Yukon to be worked by the hydraulic or other au Yukon devant être exploités suivant la mining process, approved by Order in Council méthode hydraulique ou toute autre méthode dated December 3, 1898, as amended; d’exploitation minière approuvée par le décret en date du 3 décembre 1898 et ses modifications; Page 38 UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON c Placer Mining Act Loi sur l’extraction de l’or PART 1 PARTIE 1 Section 92 Article 92 (b) that have been or may after August 1, 1906 be b) les droits qui ont été, ou qui peuvent être, acquired under the regulations governing the acquis après le 1er août 1906 sous le régime issue of leases to dredge for minerals in the du règlement régissant les concessions de baux beds of rivers in the Yukon, approved by Order de dragage des minéraux dans le lit des in Council dated January 18, 1898, or under rivières du Yukon, approuvé par décret en date any amendments to it; du 18 janvier 1898, ou ses modifications; (c) that may have been otherwise lawfully granted c) les droits par ailleurs légitimement concédés before August 1, 1906; or avant le 1er août 1906; (d) that may have been acquired under the d) les droits qui peuvent avoir été acquis sous authority of a lease to prospect. l’autorité d’un bail de prospection. [S.Y. 2003, c. 13, s. 91] [L.Y. 2003, ch. 13, art. 91] 92 Lease to prospect (Bail pour la recherche) 92 Lease to prospect 92 Bail pour la recherche (1) The Minister may grant a lease to prospect for the (1) Le ministre peut accorder un bail autorisant des purposes of placer mining on lands that are under the recherches en vue de l’exploitation d’un placer situé sur administration and control of the Commissioner, or the des terres placées sous la maîtrise et la gestion du mining rights of which are available for disposal under Commissaire, ou dont les droits d’exploitation minière this Part, on receipt of an application accompanied by peuvent être cédés sous le régime de la présente evidence satisfactory to the Minister of the applicant’s partie, sur réception d’une demande accompagnée de financial ability and intention to incur the expenditure la preuve satisfaisante que le requérant est necessary to thoroughly prospect the area described in financièrement capable et qu’il a l’intention d’engager the application. les dépenses nécessaires pour prospecter à fond l’étendue décrite dans la demande. (2) The location of the lands in respect of which a lease (2) La localisation des terres en cause est marquée sur has been granted under subsection (1) shall be marked le sol, de la manière prescrite par la présente partie, et in the ground in the manner prescribed by this Part, la demande d’un bail est présentée selon le and application for the lease shall be submitted in Form formulaire 6 de l’annexe 1. 6 of Schedule 1. (3) While a lease granted under subsection (1) remains (3) Tant que le bail demeure en vigueur, le locataire in force, the lessee is not eligible to make application n’est pas admis à soumettre une demande pour un for another lease. nouveau bail. (4) The term of a lease granted under subsection (1) (4) La durée du nouveau bail est d’un an, renouvelable shall be one year, renewable for two additional periods pour deux périodes supplémentaires d’une année of one year each, if the lessee on or before the chacune, si le locataire, à l’expiration de l’année ou termination of the year furnishes the Minister with avant cette date, procure au ministre la preuve qu’il a evidence to show that the lessee has incurred the engagé les dépenses prescrites pour les travaux de prescribed expenditure in prospecting operations and prospection, et qu’il s’est conformé d’autre part à la has otherwise complied with this Part and with the présente partie, ainsi qu’aux termes et aux conditions terms and conditions of the lease. du bail. (5) For the purposes of subsection (4) and sections 94 (5) Pour l'application du paragraphe (4) et des to 96, subsections 42(3) to (5) apply, with such articles 94 à 96, les paragraphes 42(3) à (5) modifications as the circumstances require, in respect s'appliquent, avec les modifications nécessaires, aux of the prescribed expenditure referred to in dépenses prescrites mentionnées au paragraphe (4). subsection (4). c UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON Page 39 Placer Mining Act Loi sur l’extraction de l’or PART 1 PARTIE 1 Section 93 Article 93 (6) The rental of the lands leased under this section (6) Le taux de la redevance des terres données à bail shall be at the rate of twenty-five dollars a mile or est de 25 $ par mille ou par fraction de mille, payable fraction of a mile, payable to the Commissioner in d’avance chaque année au Commissaire. advance for each year. [S.Y. 2003, c. 13, s. 92] [L.Y. 2003, ch. 13, art. 92] 93 Application for lease of abandoned ground (Demande de bail d’un terrain abandonné) 93 Application for lease of abandoned 93 Demande de bail d’un terrain abandonné ground (1) If the lands described in an application for a lease (1) Si les terres incluses dans la demande de bail under subsection 92(1) comprise abandoned ground, comprennent un terrain abandonné, c’est-à-dire, si la that is to say, if the whole or any portion of the creek totalité, ou si une partie du ruisseau ou de la rivière où or river on which the lands applied for are situated has sont situées les terres demandées a été antérieurement previously been staked out and recorded under this jalonnée et inscrite sous le régime de la présente loi, Act, the regulations that preceded it or the hydraulic des règlements antérieurs à cette loi ou du règlement mining regulations approved by Order in Council dated concernant la méthode hydraulique d’exploitation December 3, 1898, but the grants of which have been minière approuvé par le décret du 3 décembre 1898; permitted to lapse, or have been cancelled or forfeited, mais si l’on a laissé périmer, annuler ou confisquer ces they shall not exceed five miles in length, and concessions, les terres concernées ne peuvent dépasser une longueur de cinq milles et : (a) in the case of a creek, shall be measured along a) s’il s’agit d’un ruisseau, elles doivent être the base line in the manner prescribed in this mesurées le long de la ligne de base, de la Part, the side and end boundaries of the manière prescrite par la présente partie, les location of the lands being those defined in this limites latérales et terminales de l’emplacement Part; and étant celles définies dans la présente partie; (b) in the case of a river, shall be on one side b) s’il s’agit d’une rivière, elles doivent se trouver thereof only and shall extend back from the sur un côté seulement de cette rivière et foot of the natural banks a distance of one s’étendre du pied des rives naturelles sur une thousand feet measured from the base line, the distance de 1 000 pieds, mesurée à partir de la end boundaries being lines drawn at each end ligne de base, les limites terminales étant des of the location at right angles to the base line. lignes tirées à chaque extrémité de l’emplacement, à angles droits avec cette ligne de base. (2) Locations of lands other than on a creek or river (2) Les emplacements qui ne sont pas situés sur un shall not exceed one thousand feet in width and five ruisseau ou sur une rivière ne peuvent dépasser 1 000 miles in length measured along the line parallel to the pieds de large et cinq milles de long, mesurés base line of the creek or river and shall be made only parallèlement à la ligne de base du ruisseau, ou de la on abandoned ground as defined in subsection (1). rivière, et ne peuvent se trouver que sur un terrain abandonné défini au paragraphe (1). [S.Y. 2003, c. 13, s. 93] [L.Y. 2003, ch. 13, art. 93] Page 40 UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON c Placer Mining Act Loi sur l’extraction de l’or PART 1 PARTIE 1 Section 94 Article 94 94 Evidence of expenditure (Preuve de la dépense) 94 Evidence of expenditure 94 Preuve de la dépense Prior to the termination of each year, the lessee shall Avant l’expiration de chaque année, le locataire doit furnish evidence satisfactory to the Minister, supported fournir la preuve, appuyée d’un affidavit, et à la by affidavit, that the lessee has incurred during the satisfaction du ministre, qu’il a engagé au cours de year an expenditure at the rate of at least one l’année, sur l’établissement même, une dépense d’au thousand dollars for each mile or fraction of a mile moins 1 000 dollars pour chaque mille ou fraction de leased to the lessee in prospecting operations by mille à lui donné à bail, en travaux de prospection recognised methods on the location itself, or for any utilisant des méthodes reconnues, ou pour toute autre purpose that to the Minister may seem essential or fin que le ministre peut juger essentielle ou nécessaire necessary for the economical development of the lands à la mise en valeur économique de l’étendue donnée à leased, and if the evidence is not furnished before the bail. Si cette preuve n’est pas fournie avant l’expiration termination of the year, or is not satisfactory, the de l’année, ou si elle n’est pas satisfaisante, le locataire lessee is not entitled to a renewal of the lease. n’a pas droit au renouvellement de son bail. [S.Y. 2003, c. 13, s. 94] [L.Y. 2003, ch. 13, art. 94] 95 Lessee may stake out claims (Le locataire peut marquer les claims) 95 Lessee may stake out claims 95 Le locataire peut marquer les claims Prior to the termination of a lease granted under Avant l’expiration du bail, le locataire peut, s’il le section 92, the lessee may, if he or she desires, désire, jalonner personnellement, de la manière personally stake out in the manner prescribed in this prescrite dans la présente partie, des claims Part placer mining claims comprising the whole or any d’exploitation de placers comprenant la totalité ou une portion of the lands leased, and on furnishing the partie des terres louées; après avoir fourni au ministre Minister with satisfactory evidence to show that he or une preuve satisfaisante qu’il a engagé, dans l’année she has incurred during the year for which the lease pour laquelle le bail a été émis, les dépenses déjà was issued the expenditure already provided for in the prescrites pour la mise en valeur de la tenure, il peut development of the leasehold, he or she may submit an soumettre une demande selon le formulaire 1 de application in Form 1 of Schedule 1 and obtain a grant l’annexe 1, et obtenir une concession en son nom in his or her own name for each of the claims so staked propre pour chacun des claims ainsi jalonnés faisant and applied for, in which case the unrecorded portion l’objet d’une demande, auquel cas, la partie non of the location immediately reverts to the inscrite de l’emplacement est immédiatement Commissioner and becomes available for disposal retournée au Commissaire qui en dispose selon la under this Part. présente partie. [S.Y. 2003, c. 13, s. 95] [L.Y. 2003, ch. 13, art. 95] 96 Lease on creek or river not already prospected (Bail sur ruisseau ou rivière non déjà exploré) 96 Lease on creek or river not already 96 Bail sur ruisseau ou rivière non déjà prospected exploré (1) If a creek or river on which an applicant desires to (1) Si un ruisseau ou une rivière où un requérant acquire a lease to prospect has not already been désire acquérir un bail de prospection n’a pas déjà été prospected, that is to say, if mining claims have not prospecté, c’est-à-dire, si les claims miniers n’ont pas previously been staked, recorded and abandoned along encore été jalonnés, inscrits et abandonnés le long any part of the creek or river, the term of the lease d’une partie de ce ruisseau ou de cette rivière, le bail that may be granted shall be for one year only, not qui peut être accordé ne dure qu’un an; il ne bénéficie subject to renewal, and the lands leased shall not pas du renouvellement; les terres louées ne peuvent exceed one mile in length, marked out and measured dépasser un mille de long, jalonnées et mesurées de la in the manner above prescribed, and subject to all the manière prescrite ci-dessus, et elles sont subordonnées conditions above set out in so far as they can be made à toutes les conditions susmentionnées, dans la mesure to apply. où ces dernières peuvent s’appliquer. c UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON Page 41 Placer Mining Act Loi sur l’extraction de l’or PART 1 PARTIE 1 Section 97 Article 97 (2) Prior to the termination of the year referred to in (2) Avant l’expiration de l’année visée au subsection (1), the lessee of the lands may, if he or she paragraphe (1), le locataire de cet emplacement peut, desires, stake out within the limits of the lands leased a s’il le désire, jalonner, dans les limites des terres claim not exceeding in size a discovery claim and, on louées, un claim dont les dimensions ne peuvent furnishing evidence satisfactory to the Minister to show dépasser celle d’un premier claim, tel que défini dans that he or she has incurred during the year for which la présente partie, et, après avoir fourni au ministre the lease was issued the expenditure already provided une preuve satisfaisante qu’il a engagé, dans l’année for in the development of the leasehold, he or she may pour laquelle le bail a été émis, la dépense déjà submit application and obtain a grant for the claim so prescrite pour la mise en valeur de la tenure, il peut staked and applied for, in which case the unrecorded adresser une demande et obtenir une concession pour portion of the location immediately reverts to the le claim ainsi jalonné faisant l’objet d’une demande, Commissioner and becomes available for disposal auquel cas la partie non inscrite de l’emplacement est under this Part, and only one discovery claim shall be immédiatement retournée au Commissaire qui peut en allowed on the creek or river referred to in that disposer selon la présente partie, et un seul claim de subsection. découverte est accordé sur ce ruisseau ou sur cette rivière. [S.Y. 2003, c. 13, s. 96] [L.Y. 2003, ch. 13, art. 96] 97 Fees (Droits) 97 Fees 97 Droits (1) The fee for the issue of a lease, or for the renewal (1) Le droit à acquitter pour l’émission d’un bail, ou thereof, is twenty-five dollars for each mile or fraction pour son renouvellement, est de 25 $ par mille, ou of a mile described in the lease, payable in advance to fraction de mille, décrit dans le bail, payable d’avance the mining recorder for the district or to the au registraire minier du district, ou au Commissaire. Commissioner. (2) A lessee shall not assign, transfer or sublet the (2) Le locataire ne peut céder, transférer ou sous-louer rights described in a lease, or any portion thereof, les droits décrits dans le bail, ou une partie de ces without the consent in writing of the Minister being droits, sans avoir obtenu le consentement préalable du first had and obtained. ministre par écrit. [S.Y. 2003, c. 13, s. 97] [L.Y. 2003, ch. 13, art. 97] 98 Order prohibiting entry (Décret interdisant l’entrée) 98 Order prohibiting entry 98 Décret interdisant l’entrée (1) Where, in the opinion of the Commissioner in (1) Si le commissaire en conseil exécutif juge qu’un Executive Council, any lands may be required for a terrain peut être nécessaire à un port, à un aérodrome, harbour, airfield, road, bridge, or other public work or à une route, à un pont ou à d’autres ouvrages publics, for a park, historic site, or town site, the settlement of ou bien à un parc, à un lieu historique ou à un aboriginal land claims, or any other public purpose, the emplacement urbain, ou encore pour le règlement des Commissioner in Executive Council may, by order, revendications territoriales des autochtones, ou à toute prohibit entry on that land for the purpose of locating a autre fin d’utilité publique, il peut, par décret, interdire claim or prospecting for gold or other precious de pénétrer sur ce terrain aux fins de localiser un minerals or stones except on such terms and conditions claim, ou de prospecter pour découvrir de l’or, d’autres as the Commissioner in Executive Council may minéraux précieux ou des pierres précieuses, sauf aux prescribe. conditions qu’il peut fixer par décret. (2) An order under subsection (1) shall (2) Le décret visé au paragraphe (1) comporte les éléments suivants : (a) indicate the public work or public purpose for a) la mention des ouvrages ou des fins pour which the lands may be required; and lesquels les terrains peuvent être nécessaires; Page 42 UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON c Placer Mining Act Loi sur l’extraction de l’or PART 2 PARTIE 2 Section 99 Article 99 (b) set out the terms and conditions, if any, on b) l’énoncé des conditions éventuelles permettant which entry for the purpose of locating a claim d’aller sur le terrain pour y localiser un claim or prospecting for gold or other precious ou d’y prospecter pour découvrir de l’or, minerals or stones is permitted. d’autres minéraux précieux ou des pierres précieuses. [S.Y. 2003, c. 13, s. 98] [L.Y. 2003, ch. 13, art. 98] PART 2 (PARTIE 2) PART 2 PARTIE 2 LAND USE AND RECLAMATION (UTILISATION ET REMISE EN ÉTAT DES TERRES) LAND USE AND RECLAMATION UTILISATION ET REMISE EN ÉTAT DES TERRES 99 Interpretation (Définitions) 99 Interpretation 99 Définitions (1) The definitions in this subsection apply in this Part (1) Les définitions qui suivent s'appliquent à la présente partie. “applicable operating conditions”, in respect of a « activités minières » placer land use operation of a class, means a) l'exploitation du placer, (a) if the operation takes place in a special b) autre activité, ou autre groupe d'activités, dont operating area, the operating conditions that cette exploitation est le but unique ou principal. the Chief has established under “placer land use operation” subsection 101.01(1) for operations of that « activités minières désignées de type 1 » S’entend class in the special operating area, and au sens de l’alinéa 101b). “designated Class 1 placer (b) in any other case, the operating conditions, if land use operation” any, prescribed under paragraph 116(b) for operations of that class; « conditions « conditions d’exploitation applicables » À l’égard d’exploitation applicables » d’un type d’activités minières, s’entend : “approved operating plan” means an operating plan a) si l’exploitation a lieu dans une zone spéciale that the Chief has approved under paragraph 102(3)(a) d’exploitation, des conditions d’exploitation or (4)(a); « plan d’exploitation approuvé » établies par le directeur, en vertu du paragraphe 101.01(1), pour ce type “Chief” means the Chief of Placer Land Use designated d’exploitation dans cette zone spéciale; under subsection 111(1); « directeur » b) dans les autres cas, des conditions “class” means any of the classes of operations listed in d’exploitation, s’il y a lieu, prévues aux paragraph 101(a); « type » règlements d’application de l’alinéa 116b) pour “Class 1 Notification” of a designated Class 1 placer ce type d’exploitation. “applicable operating land use operation means a written notice of the conditions” planned operation, given to the Chief under « directeur » Le directeur minier désigné en vertu du subparagraph 102(1)(a)(i); « notification de type 1 » paragraphe 111(1). “Chief” “Class 2 Notification” of a Class 2 placer land use « exploitant » Une personne qui se livre à une activité operation means a written notice of the planned minière ou qui a l’intention de s’y livrer. “operator” operation, given to the Chief under « exploitation » S’entend d’activités minières. paragraph 102(2)(a); « notification de type 2 » “operation” “designated Class 1 placer land use operation” has « inspecteur » Inspecteur désigné en vertu du the meaning assigned in paragraph 101(b); « activités paragraphe 111(1). “inspector” minières désignées de type 1 » « notification » Selon le contexte, une notification de “First Nation”, in respect of a designated Class 1 placer type 1 ou une notification de type 2. “Notification” land use operation, means a Yukon First Nation (as defined in An Act Approving Yukon Land Claim Final c UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON Page 43 Placer Mining Act Loi sur l’extraction de l’or PART 2 PARTIE 2 Section 99 Article 99 Agreements) whose existing or asserted aboriginal or « notification de type 1” À l’égard d’activités minières treaty rights may be affected by the operation; de type 1, s’entend d’un avis écrit relativement aux « Première nation » activités minières projetées, donné au directeur en vertu du sous-alinéa 102(1)a)(i). “Class 1 Notification” “inspector” means an inspector designated under subsection 111(1); « inspecteur » « notification de type 2 » À l’égard d’activités minières de type 2, s’entend d’un avis écrit “Notification” means, according to the context, a relativement aux activités minières projetées, donné au Class 1 Notification or a Class 2 Notification; directeur en vertu de l’alinéa 102(2)a). “Class 2 « notification » Notification” “operation” means a placer land use operation; « période de révision » À l’égard d’activités minières « exploitation » désignées de type 1, la période qui commence à la date “operating plan” means an operating plan required by où le directeur reçoit une notification de type 1 subsection 102(3) or (4); « plan d'exploitation » concernant l’exploitation et se termine : “operator” means a person who engages, or who a) soit à la date où le directeur donne un avis en proposes to engage, in an operation; « exploitant » vertu de l’alinéa 103(2)b) permettant l’exploitation, soit à la date où il donne un avis “placer land use operation” means en vertu du sous-alinéa 103(2)c)(ii) refusant (a) placer mining, and une telle exploitation; (b) any other activity or group of activities b) soit, si le directeur ne donne aucun des avis undertaken for the sole or principal purpose of mentionnés à l’alinéa a), à la dernière des placer mining; « activités minières » échéances suivantes : “review period” of a designated Class 1 placer land use (i) le dernier jour de la période prescrite à cette operation means the period that begins on the day the fin en vertu de l’alinéa 116c.01), Chief receives a Class 1 Notification of the operation (ii) lorsque le directeur prolonge la période de and that ends révision en vertu de l’alinéa 103(2)a), le dernier jour de ce prolongement. “review (a) on the day the Chief gives notice under period” paragraph 103(2)(b) allowing the operation to be carried out or notice under « plan d'exploitation » Plan d'exploitation visé aux subparagraph 103(2)(c)(ii) refusing to allow paragraphes 102(3) ou (4). “operating plan” it, or « plan d’exploitation approuvé » Un plan (b) if the Chief gives neither of the notices d’exploitation approuvé par le directeur en vertu des described in paragraph (a), on the later of alinéas 102(3)a) ou (4)a).
Part document.segment-5
Placer Mining Act (Extraction de l’or) — segment 5
- document.segment-5 Verify source ↗
Placer Mining Act (Extraction de l’or) — segment 5
This Part sets rules for placer mining classes, notifications, operating plans, inspections, security, and enforcement.
“approved operating plan” (i) the last day of the period prescribed for this « Première nation » À l’égard d’une activité minière purpose under paragraph 116(c.01), and désignée de type 1, une Première nation du Yukon, au (ii) where the Chief extends the review period sens de la Loi approuvant les ententes définitives avec under paragraph 103(2)(a), the last day of les premières nations du Yukon, dont les droits the extension; « période de révision » ancestraux ou issus de traités, existants ou “special operating area” means an area prescribed revendiqués, sont susceptibles d’être touchés par under paragraph 116(c.02); « zone spéciale l’exploitation. “First Nation” d’exploitation » « type » Les types d’activités minières énumérés à l’alinéa 101a). “class” « zone spéciale d’exploitation » Une zone désignée en vertu de l’alinéa 116c.02). “special operating area” Page 44 UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON c Placer Mining Act Loi sur l’extraction de l’or PART 2 PARTIE 2 Section 100 Article 100 (2) This Part, any provision of this Part, the regulations (2) La présente partie et les règlements d'application made under section 116, and any provision of those de l'article 116, ou toute disposition de cette partie ou regulations, apply in respect of lands or categories of de ces règlements, s'appliquent aux terres situées au lands, situated within the Yukon, only to the extent that Yukon, ou aux catégories de celles-ci, seulement dans the regulations made under paragraph 116(a) so la mesure prévue par les règlements d'application de provide. l'alinéa 116a). (3) Without limiting the generality of (3) Sans que soit limitée la portée générale de paragraph 116(a), regulations made under that l'alinéa 116a), les règlements pris en vertu de cet paragraph may describe a category of lands by alinéa peuvent définir une catégorie de terres en reference to activities taking place, or not taking place, fonction des activités qui y sont exercées ou non, soit on those lands, either generally or before, at or after a de façon générale, soit à une date ou à un moment specified time. donnés. (4) For greater certainty (4) Il est entendu : (a) a Notification or an operating plan includes, a) qu’une notification ou un plan d’exploitation unless the context indicates otherwise, any comprend, selon le contexte, toute modification amendment that the Chief or an inspector qui lui est apportée par le directeur ou par un makes to it in accordance with this Part; and inspecteur, conformément à la présente partie; (b) nothing in this Part, the regulations made b) que, sauf dans la mesure autorisée par une under it or an approved operating plan autre loi, ses règlements ou un décret ou arrêté authorizes a person to contravene any other pris sous son régime, la présente partie, ses Act or any regulation or order made under it, règlements ou un plan d’exploitation approuvé except as provided in that other Act, regulation n’ont pas pour effet d’autoriser une personne à or order. contrevenir à cette autre loi ou aux règlements, décrets ou arrêtés pris sous son régime, ou à ne pas s’y conformer. (5) The Minister may, by written designation, transfer (5) La personne ou l'organisme désigné par écrit par le any function of the Minister or the Chief under this Part ministre peut exercer les attributions que la présente to any person or body named in the designation, partie confère au ministre ou au directeur, sous subject to any terms and conditions specified in the réserve des modalités précisées dans l'acte de designation, and a person or body so designated may transfert. perform that function in accordance with the designation. [S.Y. 2013, c. 18, s. 2] [S.Y. 2003, c. 13, s. 99] [L.Y. 2013, ch. 18, art. 2] [L.Y. 2003, ch. 13, art. 99] 100 Purpose of Part 2 (Objet de la partie 2) 100 Purpose of Part 2 100 Objet de la partie 2 The purpose of this Part is to ensure the development La présente partie a pour objet de veiller au and viability of a sustainable, competitive and healthy développement et à la viabilité d’une industrie de placer mining industry that operates in a manner that l’extraction de l’or qui soit durable, concurrentielle et upholds the essential socio-economic and saine dont le fonctionnement protège les valeurs socio- environmental values of the Yukon and respects the économiques et environnementales fondamentales du aboriginal and treaty rights referred to in section 35 of Yukon, et respecte les droits ancestraux et issus de the Constitution Act, 1982. traités visés à l’article 35 de la Loi constitutionnelle de 1982. [S.Y. 2013, c. 18, s. 3] [L.Y. 2013, ch. 18, art. 3] 101 Classes of placer land use (Types d’activités) 101 Classes of placer land use 101 Types d’activités For the purposes of this Part Pour l’application de la présente partie : c UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON Page 45 Placer Mining Act Loi sur l’extraction de l’or PART 2 PARTIE 2 Section 101.01 Article 101.01 (a) there are Class 1 placer land use operations, a) il y a des activités minières de type 1, de Class 2 placer land use operations, Class 3 type 2, de type 3 et de type 4, conformément placer land use operations and Class 4 placer aux critères prévus dans les règlements land use operations, in accordance with the d’application de l’alinéa 116c); criteria prescribed by the regulations made under paragraph 116(c); and (b) a Class 1 placer land use operation is a b) des activités minières de type 1 sont des designated Class 1 placer land use operation if activités minières désignées de type 1 si elles it takes place in an area prescribed under ont lieu dans une zone désignée en vertu de subparagraph 116(c.01)(i). sous-l’alinéa 116c.01)(i). [S.Y. 2013, c. 18, s. 3] [L.Y. 2013, ch. 18, art. 3] 101.01 Special operating areas (Zones spéciales d’exploitation) 101.01 Special operating areas 101.01 Zones spéciales d’exploitation (1) Where a special operating area is prescribed under (1) Le directeur doit fixer des conditions d’exploitation paragraph 116(c.02), the Chief must establish qui s’appliqueront à toute exploitation dans une zone operating conditions, for operations within the special spéciale d’exploitation désignée en vertu de operating area, that in the Chief’s opinion will protect l’alinéa 116c.02) et qui, à son avis, contribueront à the environmental, socio-economic, cultural and protéger les valeurs environnementales, socio- historical values of the special operating area. économiques, culturelles et historiques de la zone spéciale d’exploitation. (2) In establishing operating conditions under (2) Le directeur, lorsqu’il fixe des conditions subsection (1), the Chief d’exploitation en vertu du paragraphe (1) : (a) must comply with the requirements, if any, a) doit respecter les exigences, s’il y a lieu, prescribed under paragraph 116(c.03); prescrites en vertu de l’alinéa 116c.03); (b) must, for each operating condition, specify the b) doit préciser la date où chaque condition date on which, subject to subsection (3), it d’exploitation commence à s’appliquer, sous starts to apply; réserve du paragraphe (3); (c) may establish different operating conditions for c) peut établir des conditions d’exploitation different classes of operation; and différentes pour des types d’exploitation différents; (d) may incorporate by reference any operating d) peut incorporer par renvoi toute condition condition prescribed under paragraph 116(b). d’exploitation prévue en vertu de l’alinéa 116b). (3) An operating condition established under (3) Une condition d’exploitation établie en vertu du subsection (1) applies on and after the date the Chief paragraphe (1) s’applique à compter de la date que le specifies for it under paragraph (2)(b), except that the directeur précise en vertu de l’alinéa (2)b), à moins Chief may modify or waive the application of the qu’il ne modifie l’application de la condition operating condition to an operation that began before d’exploitation ou n’y renonce à l’égard d’une that date. exploitation qui a débuté avant cette date. [S.Y. 2013, c. 18, s. 4] [L.Y. 2013, ch. 18, art. 4] 102 Classes 1 to 4 (Types 1 à 4) 102 Classes 1 to 4 102 Types 1 à 4 (1) No person shall engage in a Class 1 placer land use (1) Nul ne peut exercer des activités minières de operation except type 1, à moins de remplir l’une des conditions suivantes : Page 46 UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON c Placer Mining Act Loi sur l’extraction de l’or PART 2 PARTIE 2 Section 102 Article 102 (a) in the case of a designated Class 1 placer land a) dans le cas d’activités minières désignées de use operation type 1 : (i) after the person gives the Chief a Class 1 (i) après avoir remis au directeur une Notification in accordance with the notification de type 1, conformément aux regulations made under paragraph 116(d), règlements d’application de l’alinéa 116d), (ii) after the operation’s review period ends, and (ii) lorsque la période de révision de l’exploitation est écoulé, (iii) in accordance with (iii) conformément : (A) the Notification, and (A) à la notification, (B) subject to any contrary provision in the (B) aux conditions d’exploitation applicables, Notification, the applicable operating sauf disposition contraire à la conditions; or notification; (b) in any other case, in accordance with the b) dans les autres cas, conformément aux applicable operating conditions. conditions d’exploitation applicables. (2) No person shall engage in a Class 2 placer land use (2) Nul ne peut exercer des activités minières de operation except type 2, à moins : (a) after the person gives the Chief a Class 2 a) d’avoir remis au directeur une notification de Notification of the operation in accordance with type 2 à l’égard de l’exploitation, the regulations made under conformément au règlement d’application du paragraph 116(d); and paragraphe 116d); (b) in accordance with b) de le faire conformément : (i) the Notification, and (i) à la notification, (ii) subject to any contrary provision in the (ii) aux conditions d’exploitation applicables, Notification, the applicable operating sauf disposition contraire à la notification. » conditions.” (3) No person shall engage in a Class 3 placer land use (3) Quiconque exerce des activités minières de type 3 operation except doit, à la fois : (a) in accordance with an operating plan approved a) se conformer au plan d'exploitation approuvé by the Chief on written application by that par le directeur, soumis par le demandeur avec person; la demande écrite; (b) subject to any contrary provision in the b) se conformer, sous réserve de toute disposition operating plan, in accordance with the contraire du plan d'exploitation, aux conditions applicable operating conditions; d'exploitation applicables; (c) after notifying the public of the planned placer c) aviser le public, au préalable, des activités land use operation, if so required by the Chief, projetées, si le directeur l'exige et in the manner directed by the Chief; and conformément aux instructions de ce dernier; (d) after a public consultation, if any, required by d) tenir la consultation publique préalable the Chief and held in accordance with the éventuellement exigée par le directeur, directions of the Chief. conformément aux instructions de celui-ci. (4) No person shall engage in a Class 4 placer land use (4) Quiconque exerce des activités minières de type 4 operation except doit, à la fois : c UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON Page 47 Placer Mining Act Loi sur l’extraction de l’or PART 2 PARTIE 2 Section 103 Article 103 (a) in accordance with an operating plan approved a) se conformer au plan d'exploitation approuvé by the Chief, on written application by that par le directeur, soumis par le demandeur avec person, after paragraphs (c) and (d) have been la demande écrite, après observation des complied with; alinéas c) et d); (b) subject to any contrary provision in the b) se conformer, sous réserve de toute disposition operating plan, in accordance with the contraire du plan d'exploitation, aux conditions applicable operating conditions; d'exploitation applicables; (c) after notifying the public of the planned placer c) aviser le public, au préalable, des activités land use operation, in the manner directed by projetées, conformément aux instructions du the Chief; and directeur; (d) after a public consultation, if any, required by d) tenir la consultation publique préalable the Chief and held in accordance with the éventuellement exigée par le directeur, directions of the Chief. conformément aux instructions de celui-ci. (5) For the purposes of paragraphs (3)(c) and (d) and (5) Pour l'application des alinéas (3)c) et d) et (4)c) et (4)(c) and (d), the Chief shall act in accordance with d), le directeur se conforme aux règlements any regulations made under paragraph 116(h). d'application de l'alinéa 116h). [S.Y. 2013, c. 18, s. 5] [S.Y. 2003, c. 13, s. 102] [L.Y. 2013, ch. 18, art. 5] [L.Y. 2003, ch. 13, art. 102] 103 Designated Class 1 operations (Activités minières désignées de type 1) 103 Designated Class 1 operations 103 Activités minières désignées de type 1 (1) After receiving a Class 1 Notification of a (1) Après réception d’une notification de type 1 pour designated Class 1 placer land use operation, the Chief des activités minières désignées de type 1, le directeur must, before the end of the operation’s review period doit, avant l’expiration de la période de révision : (a) review the operation as described in the Class 1 a) réviser l’exploitation, telle que décrite à la Notification to determine its adverse notification de type 1, pour déterminer ses environmental or socio-economic effects, effets environnementaux et socio-économiques if any; négatifs, s’il y a lieu; (b) initiate consultations with each First Nation by b) entamer des consultations avec chaque notifying it and inviting it to provide written Première nation en l’avisant et en l’invitant à comments to the Chief regarding any adverse soumettre des commentaires écrits au effects the operation as described in the Class 1 directeur à l’égard de tout effet négatif qui peut Notification may have on its existing or être causé par l’exploitation, telle que décrite à asserted aboriginal or treaty rights; and la notification de type 1, sur ses droits ancestraux ou issus de traités, existants ou revendiqués; (c) determine whether the operation as described c) déterminer si l’exploitation décrite à la in the Class 1 Notification will appropriately notification de type 1 va atténuer de façon mitigate the adverse effects referred to in appropriée les effets négatifs mentionnés aux paragraphs (a) and (b). alinéas a) et b). (2) At any time during the review period of a (2) En tout temps pendant la période de révision designated Class 1 placer land use operation (including, d’activités minières désignées de type 1 (y compris tout for greater certainty, any extension of the review prolongement de la période de révision en vertu de period under paragraph (a)) l’alinéa a) : Page 48 UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON c Placer Mining Act Loi sur l’extraction de l’or PART 2 PARTIE 2 Section 104 Article 104 (a) if the Chief reasonably considers that additional a) le directeur peut, en donnant un avis à time is needed to review the operation, to l’exploitant d’activités minières et à chaque consult First Nations or to make the Première nation, prolonger la période de determination described in paragraph (1)(c), révision d’un nombre raisonnable de jours s’il the Chief may, by giving notice to the operator juge raisonnablement qu’une plus longue of the operation and each First Nation, extend période est nécessaire pour réviser the review period by any reasonable number l’exploitation, consulter les Premières nations of days; ou rendre une décision en application de l’alinéa (1)c); (b) if the Chief determines under paragraph (1)(c) b) le directeur peut, en donnant un avis à that the operation as described in its l’exploitant d’activités minières et à chaque Notification (either initially or as amended Première nation, permettre l’exploitation s’il under subparagraph (c)(i)) will appropriately détermine en vertu de l’alinéa (1)c) que cette mitigate the adverse effects referred to in dernière, telle que décrite dans sa notification paragraphs (1)(a) and (b), the Chief may, by (soit dans sa version initiale, soit modifiée en giving notice to the operator and each First vertu du sous-alinéa c(i), va atténuer de façon Nation, allow the operation to be carried appropriée les effets négatifs mentionnés aux out; and alinéas (1)a) et b); (c) if the Chief determines under paragraph (1)(c) c) le directeur peut, s’il détermine en vertu de that the operation as initially described in the l’alinéa (1)c) que l’exploitation, telle que décrite Notification will not appropriately mitigate the à l’origine dans la notification, n’atténuera pas adverse effects, the Chief may, after seeking de façon appropriée les effets négatifs, après the operator’s views avoir consulté l’exploitant : (i) amend the Notification to vary the manner in (i) modifier la notification pour changer la façon which the operation is to be carried out, or de procéder de l’exploitation, (ii) by giving notice, including written reasons, (ii) refuser de permettre l’exploitation, après to the operator and each First Nation, refuse avoir donné un avis motivé par écrit à to allow the operation to be carried out. l’exploitant et à chaque Première nation. (3) Any notice that the Chief gives under subsection (1) (3) Un avis donné par le directeur en vertu des or (2) must be given in the form and manner, if any, paragraphes (1) ou (2) doit l’être en la forme et selon that are prescribed under paragraph 116(f)(i) for such les modalités, s’il y a lieu, prescrits en vertu de a notice. l’alinéa 116f)(i). (4) Unless the Chief refuses under (4) À moins que le directeur ne refuse la réalisation subparagraph (2)(c)(ii) to allow a designated Class 1 d’activités minières désignées de type 1 en vertu du placer land use operation to be carried out, the sous-alinéa (2)c)(ii), l’exploitant peut, sous réserve des operator of the operation may, subject to the dispositions de la présente loi et de ses règlements, provisions of this Act and the regulations, begin the entreprendre l’exploitation à la fin de la période de operation after the operation’s review period ends. révision. [S.Y. 2013, c. 18, s. 6] [L.Y. 2013, ch. 18, art. 6] 104 Certificate of Completion (Attestation d’achèvement des activités) 104 Certificate of Completion 104 Attestation d’achèvement des activités (1) In the case of a designated Class 1 placer land use (1) S'il estime que des activités minières désignées de operation or Class 2 placer land use operation in type 1 ou des activités minières de type 2 pour respect of which security was required, where the Chief lesquelles une garantie a été exigée sont terminées et is satisfied that the operation has been terminated and que l'exploitant s'est conformé à toutes les dispositions that the operator has complied with all provisions of de la notification, de la présente partie et de ses the Notification and of this Part and the regulations règlements, le directeur, sur demande écrite de c UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON Page 49 Placer Mining Act Loi sur l’extraction de l’or PART 2 PARTIE 2 Section 105 Article 105 made thereunder, the Chief shall, on written l'exploitant, lui délivre, en la forme réglementaire, une application by the operator, issue to the operator a attestation d'achèvement des activités. Certificate of Completion to that effect, in the prescribed form. (2) In the case of a Class 3 or Class 4 placer land use (2) S'il estime que les activités minières de type 3 ou 4 operation, where the Chief is satisfied that the sont terminées et que le titulaire du plan d'exploitation operation has been terminated and that the holder of s'est conformé à toutes les dispositions de celui-ci, de the approved operating plan has complied with all la présente partie et de ses règlements, le directeur, provisions of the plan and of this Part and the sur demande écrite du titulaire, lui délivre, en la forme regulations made thereunder, the Chief shall, on réglementaire, une attestation d'achèvement des written application by the holder, issue to the holder a activités. Certificate of Completion to that effect, in the prescribed form. (3) A document purporting to be a Certificate of (3) Le document présenté comme attestation Completion is admissible in evidence in any court d'achèvement des activités est admissible en preuve without proof of the signature or official character of devant tout tribunal, sans qu'il soit nécessaire de the person appearing to have signed it, and is, unless prouver l'authenticité de la signature qui y est apposée the contrary is shown, proof of the matters asserted ou la qualité officielle du signataire; sauf preuve in it. contraire, l'attestation fait preuve de son contenu. [S.Y. 2013, c. 18, s. 7] [S.Y. 2003, c. 13, s. 104] [L.Y. 2013, ch. 18, art. 7] [L.Y. 2003, ch. 13, art. 104] 105 Form and Content of applications (Forme et teneur des demandes) 105 Form and Content of applications 105 Forme et teneur des demandes An application for La demande d'approbation d'un plan d'exploitation, de (a) approval of an operating plan; cession d'un tel plan ou d'attestation d'achèvement des activités est présentée conformément aux règlements (b) assignment of an approved operating plan; or d'application de l'alinéa 116d) et accompagnée du (c) a Certificate of Completion montant des droits applicables en vertu des règlements must be in accordance with the regulations made d'application de l'alinéa 116l). under paragraph 116(d) and must be accompanied by [L.Y. 2003, ch. 13, art. 105] any applicable fee that is required by virtue of regulations made under paragraph 116(l). [S.Y. 2003, c. 13, s. 105] 106 Security may be required (Demande de garantie) 106 Security may be required 106 Demande de garantie (1) Where there is a risk of significant adverse (1) Si des activités minières de désignées de type 1 ou environmental effect from a planned designated Class 1 de type 2, 3 ou 4 risquent d'entraîner des effets placer land use operation or Class 2, Class 3 or Class 4 environnementaux négatifs importants, le directeur placer land use operation, the person giving the peut exiger, soit de la personne qui a donné la Notification, the applicant for approval of an operating notification, soit de l'auteur d'une demande plan, the holder of an approved operating plan, or the d'approbation d'un plan d'exploitation, soit du titulaire prospective assignee of an approved operating plan, as d'un tel plan ou de son éventuel cessionnaire, qu'il the case may be, may be required by the Chief to fournisse une garantie au ministre, et qu’il la furnish and maintain security with the Minister, in an maintienne en permanence, pour le montant prévu par amount specified in, or determined in accordance with, les règlements d'application de l'alinéa 116m), ou the regulations made under paragraph 116(m) and in a déterminé en conformité avec ceux-ci, et sous la forme form prescribed by or pursuant to those regulations or prévue par ces règlements, ou sous toute autre forme a form satisfactory to the Minister. que le ministre juge acceptable. (2) In assessing, under subsection (1), whether there (2) Pour déterminer s’il existe un risque d’effets Page 50 UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON c Placer Mining Act Loi sur l’extraction de l’or PART 2 PARTIE 2 Section 107 Article 107 is a risk of significant adverse environmental effect, the environnementaux négatifs importants aux termes du past performance of the person giving the Notification, paragraphe (1), il peut être tenu compte des activités the applicant, holder or prospective assignee, as the antérieures menées par les personnes visées dans ce case may be, may be considered. paragraphe. (3) Security furnished under subsection (1) may be (3) Le ministre peut utiliser la garantie pour applied by the Minister to reimburse the Commissioner, rembourser au Commissaire, en tout ou en partie, les either fully or partially, for reasonable costs incurred by frais qu'entraîne l'application du paragraphe 113(7) ou the Commissioner pursuant to subsection 113(7) du paragraphe 114(1), sous réserve du paragraphe (4). or 114(1), subject to subsection (4). (4) Subsection (3) applies in respect of costs incurred (4) Le paragraphe (3) s'applique aux frais engagés au pursuant to subsection 114(1) only to the extent that titre du paragraphe 114(1) uniquement dans la mesure the incurring of those costs was based on où ils découlent de l’application du sous- subparagraph 114(1)(b)(i). alinéa 114(1)b)(i). (5) The amount of security that the Minister may apply (5) Le ministre ne peut utiliser, au titre du pursuant to subsection (3) in respect of any particular paragraphe (3) et pour quelque motif que ce soit, un incident or matter may not exceed in the aggregate the montant qui excède celui de la garantie. amount of the security referred to in subsection (1). (6) Where (6) La partie de la garantie qui, selon le ministre, n'est (a) a Certificate of Completion has been issued; or pas nécessaire pour l'application du paragraphe (3) est remise sans délai : (b) an approved operating plan has been assigned; a) en cas de délivrance d'une attestation any portion of the security that, in the Minister's d'achèvement des activités, au titulaire de opinion, will not be required under subsection (3) shall celle-ci; forthwith be returned to the certificate holder (where paragraph (a) applies) or the assignor (where b) en cas de cession d'un plan d'exploitation paragraph (b) applies). approuvé, au cédant. [S.Y. 2013, c. 18, s. 8] [S.Y. 2003, c. 13, s. 106] [L.Y. 2013, ch. 18, art. 8] [L.Y. 2003, ch. 13, art. 106] 107 Minor amendments (Modifications mineures) 107 Minor amendments 107 Modifications mineures If an operator of a designated Class 1 placer land use L'inspecteur peut, par avis, modifier la notification, si operation or of a Class 2 placer land use operation l’exploitant qui exerce des activités minières désignées requests an inspector, orally or in writing, to amend de type 1 ou des activités minières de type 2 lui the operation’s Notification in a minor way, and the demande, oralement ou par écrit, d'apporter une inspector is satisfied that the requested amendment modification mineure à la notification de l’exploitation, poses no risk of significant adverse environmental et si l’inspecteur estime que cela ne risque pas effect, the inspector may issue a variation notice d'entraîner des effets environnementaux négatifs. amending the Notification. [S.Y. 2013, c. 18, s. 9] [L.Y. 2013, ch. 18, art. 9] 108 Operating plans (Renouvellement) 108 Operating plans 108 Renouvellement The Chief may, on written application by the holder of Le directeur peut, sur demande écrite du titulaire, an approved operating plan, approve an amendment approuver la modification ou le renouvellement d'un to, or renewal of, that plan. plan d'exploitation. c UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON Page 51 Placer Mining Act Loi sur l’extraction de l’or PART 2 PARTIE 2 Section 109 Article 109 (2) Sections 102, 105, and 106 apply, with such (2) Les articles 102, 105 et 106 s'appliquent, avec les modifications as the circumstances require, in respect adaptations nécessaires, à la modification ou au of an amendment to, or renewal of, an approved renouvellement d'un plan d'exploitation. operating plan pursuant to this section. [S.Y. 2003, c. 13, s. 108] [L.Y. 2003, ch. 13, art. 108] 109 Minor amendments - Class 3 or 4 (Modification mineure ⎯ type 3 ou 4) 109 Minor amendments - Class 3 or 4 109 Modification mineure ⎯ type 3 ou 4 Where an operator of a Class 3 or Class 4 placer land L'inspecteur peut, par avis, modifier les conditions du use operation requests an inspector, orally or in plan, si la personne qui exerce des activités minières writing, to amend the operating plan in a minor way, de type 3 ou 4 lui demande, oralement ou par écrit, and the inspector is satisfied that the requested d'apporter une modification mineure aux conditions du amendment poses no risk of significant adverse plan d'exploitation, et s'il estime que cela ne risque pas environmental effect, the inspector may issue a d'entraîner des effets environnementaux négatifs variation notice amending the operating plan. importants. [S.Y. 2003, c. 13, s. 109] [L.Y. 2003, ch. 13, art. 109] 110 Assigning an approved operating plan (Plan d’exploitation approuvé : cession) 110 Assigning an approved operating plan 110 Plan d’exploitation approuvé : cession (1) The Chief shall, on written application by the holder (1) Le directeur, sur demande écrite du titulaire, of an approved operating plan, authorise the autorise la cession du plan d'exploitation approuvé si : assignment of that plan if a) d'une part, l'éventuel cessionnaire s'engage par (a) the prospective assignee écrit à se conformer au plan et fournit la (i) undertakes in writing to comply with the garantie exigée conformément à l'article 106; plan, and b) d'autre part, il estime que la cession (ii) furnishes any security that is required from n'entraînera vraisemblablement pas de the prospective assignee pursuant to contravention à une condition du plan, ou à une section 106; and disposition de la présente partie, ou de ses règlements. (b) the Chief is satisfied that the assignment would not be likely to result in a contravention of any condition of the plan or of any provision of this Part or the regulations. (2) Except as provided in this section, an approved (2) Sauf dans la mesure prévue par le présent article, operating plan is not assignable. le plan d'exploitation est incessible. [S.Y. 2003, c. 13, s. 110] [L.Y. 2003, ch. 13, art. 110] 111 Inspectors and Chief (Inspecteurs et directeur) 111 Inspectors and Chief 111 Inspecteurs et directeur (1) The Minister may designate as an inspector, or as (1) Le ministre peut désigner toute personne qu’il juge the Chief of Placer Land Use, for the purposes of this qualifiée à titre d'inspecteur ou au poste de directeur Part, any person that the Minister considers qualified. minier pour l'application de la présente partie. (2) The Minister shall furnish every inspector with a (2) Le ministre remet à chaque inspecteur un certificat certificate of designation as an inspector, and on attestant sa qualité et que ce dernier présente, sur entering any place an inspector shall, if so requested, demande, au responsable du lieu qu'il visite. produce the certificate to the person in charge of the place. [S.Y. 2003, c. 13, s. 111] [L.Y. 2003, ch. 13, art. 111] Page 52 UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON c Placer Mining Act Loi sur l’extraction de l’or PART 2 PARTIE 2 Section 112 Article 112 112 Powers of inspectors (Pouvoir) 112 Powers of inspectors 112 Pouvoir (1) Subject to this section, an inspector may at any (1) Sous réserve des autres dispositions du présent reasonable time, for the purpose of ensuring article, dans le but de faire observer la présente partie, compliance with this Part, l'inspecteur peut, à toute heure convenable : (a) enter any place in which the inspector believes a) pénétrer dans tout lieu où il a des motifs on reasonable grounds that an activity to which raisonnables de croire qu'une activité assujettie this Part applies is being, or has been, carried à la présente partie est en cours, ou qu’elle a out; and eu lieu; (b) conduct such inspections as the inspector b) procéder à toute inspection qu'il estime deems necessary, including examining books, nécessaire, notamment examiner et reproduire records or documents and making copies tout livre ou tout autre document, prendre des thereof or taking extracts therefrom, taking échantillons de minéraux ou d'autres samples of minerals or other substances, substances, effectuer des essais et prendre des conducting tests and taking measurements. mesures. (2) No inspector may enter, without the consent of the (2) Il est interdit à l'inspecteur de pénétrer dans un occupant, any place that is designed to be used and is lieu conçu et utilisé de façon temporaire ou being used as a permanent or temporary dwelling permanente comme local d'habitation, sans obtenir le place. consentement de l'occupant. (3) Before exercising powers under paragraph (1)(b), (3) L'inspecteur doit, avant d'exercer les pouvoirs an inspector shall make reasonable efforts to ascertain prévus à l'alinéa (1)b), s'efforcer de déterminer si un whether anyone responsible for the place entered is responsable est présent sur les lieux et, le cas échéant, present and, if so, the inspector shall announce the l'informer de son arrivée. inspector's arrival to that person. (4) The person in charge of any place referred to in (4) Le responsable du lieu visité, et toute personne qui this section, and every person found in it, shall give an s'y trouve, sont tenus de prêter à l'inspecteur toute inspector all reasonable assistance to enable the l'assistance possible dans l'exercice de ses fonctions et inspector to carry out the inspector's duties under this de lui donner les renseignements qu'il peut Part, and shall furnish the inspector with such valablement exiger pour l'application de la présente information with respect to the administration of this partie. Part as the inspector may reasonably request. [S.Y. 2003, c. 13, s. 112] [L.Y. 2003, ch. 13, art. 112] 113 Directions by inspectors (Instructions données par un inspecteur) 113 Directions by inspectors 113 Instructions données par un inspecteur (1) Where an inspector believes on reasonable grounds (1) L'inspecteur peut ordonner la prise des mesures that an operator qu'il juge raisonnable d'imposer, notamment la (a) has contravened, or may be about to cessation de toute activité, pour empêcher la contravene, this Part; or contravention ou supprimer le danger inutile ou en empêcher la continuation ou la répétition, s'il a des (b) has or is engaged in an activity that is resulting motifs raisonnables de croire qu'un exploitant : in, or may result in, unnecessary danger to persons, property or the environment, a) soit a contrevenu, ou est sur le point de contrevenir, à la présente partie; the inspector may direct the operator to take such reasonable measures as the inspector may specify, b) soit a exercé, ou exerce, une activité qui including the cessation of an activity, to prevent the présente, ou qui peut présenter, un danger contravention or the unnecessary danger or their inutile pour les personnes, les biens ou continuation or repetition. l'environnement. c UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON Page 53 Placer Mining Act Loi sur l’extraction de l’or PART 2 PARTIE 2 Section 113 Article 113 (2) Where an inspector is unable to give a direction to (2) Si l’inspecteur n’a pas pu donner des instructions à the operator after making reasonable efforts to do so, l'exploitant, en dépit d'efforts sérieux en ce sens, il the inspector may post the direction in a conspicuous peut les afficher sur les lieux, dans un endroit bien en place on the operator's premises, whereupon the vue; l'exploitant est alors réputé les avoir reçues. direction is deemed to have been given to the operator. (3) Where an inspector gives a direction to a person (3) Le directeur peut en tout temps, de sa propre under this section, the Chief initiative, réviser la décision de l'inspecteur, et la (a) if so requested by the person at any time, shall personne qui a reçu les instructions peut, en tout forthwith review the direction and shall, after temps, lui demander de le faire, auquel cas le directeur completion of that review, confirm, alter or procède sans délai à la révision; à l'issue de celle-ci, il revoke the direction; or confirme, modifie ou révoque la décision. (b) may, at any time, on the Chief's own initiative, review the direction and shall, after completion of any such review, confirm, alter or revoke the direction. (4) Where the person referred to in subsection (3) (4) Le ministre : requests the Minister to review a decision of the Chief made under that subsection, the Minister (a) shall, if the request is made within ninety days a) révise sans délai la décision prise par le after the person was notified of the Chief's directeur en vertu du paragraphe (3) si la decision, forthwith review the decision; demande lui en est faite par l'intéressé dans les 90 jours suivant la date à laquelle celui-ci a été avisé de la décision; (b) may, if the request is made after the ninety b) peut réviser la décision si la demande lui en est day period mentioned in paragraph (a), review faite après l'expiration du délai prévu à the decision; and l'alinéa a); (c) shall, after completion of a review referred to c) après la révision prévue aux alinéas a) ou b), in paragraph (a) or (b), confirm or alter the confirme ou modifie la décision ou lui en decision or substitute a new decision therefor. substitue une nouvelle. (5) An inspector, on being satisfied that the situation (5) L'inspecteur révoque sans délai sa décision that led to giving a direction to cease an activity no d'ordonner la cessation des activités s'il estime que les longer exists, shall forthwith revoke that direction. circonstances qui y ont donné lieu n'existent plus. (6) A person to whom a direction is given under this (6) La personne qui reçoit des instructions section shall comply with the direction. conformément au présent article doit s'y conformer. (7) Where a person to whom a direction is given under (7) Si la personne ne se conforme pas aux instructions, this section does not comply with the direction, an l'inspecteur peut lui-même, avec le consentement du inspector may, with the consent of the Chief, take the directeur, prendre les mesures qui y sont visées et measures set out in the direction and may, for that pénétrer à cette fin dans tout lieu, sous réserve du purpose, enter any place, subject to subsection 112(2). paragraphe 112(2). (8) Any portion of the reasonable costs incurred by the (8) Les frais engagés par le Commissaire au titre du Commissioner pursuant to subsection (7) that is not paragraphe (7) constituent une créance de ce dernier, recoverable from the security referred to in section 106 et son recouvrement peut être poursuivi contre le (a) because of the non-existence or inadequacy of destinataire des instructions, faute de pouvoir être that security; recouvrés en vertu de la garantie visée à l'article 106 pour l'un des motifs suivants : (b) because all or a portion of that security has been returned pursuant to subsection 106(6); a) garantie inexistante ou insuffisante; Page 54 UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON c Placer Mining Act Loi sur l’extraction de l’or PART 2 PARTIE 2 Section 114 Article 114 or b) garantie remise, en tout ou en partie, aux (c) for any other reason termes du paragraphe 106(6); may be recovered from the person to whom the c) tout autre motif. direction under this section was given, as a debt due to [L.Y. 2003, ch. 13, art. 113] the Commissioner. [S.Y. 2003, c. 13, s. 113] 114 Termination or abandonment (Fermeture ou abandon) 114 Termination or abandonment 114 Fermeture ou abandon (1) Where an inspector believes, on reasonable (1) L'inspecteur, après avoir déployé des efforts grounds, that sérieux pour communiquer avec la personne visée, (a) a person has terminated, temporarily or peut prendre les mesures raisonnables pour empêcher, permanently, or has abandoned a placer land neutraliser, diminuer ou réparer tout effet négatif sur use operation; and les personnes, les biens ou l'environnement; il peut pénétrer dans tout lieu à cette fin, s'il a des motifs (b) either raisonnables de croire, sous réserve du (i) the person has contravened a condition of an paragraphe 112(2), : approved operating plan, or any provision of a) d'une part, que la personne a mis fin, de façon this Part or the regulations, whether or not temporaire ou permanente, aux activités the condition or provision relates to minières ou qu’elle les a abandonnées; termination or abandonment, or b) d'autre part, que, selon le cas : (ii) a danger to persons, property or the environment may result from the past placer (i) la personne a contrevenu à une condition du land use operation or from its termination or plan d'exploitation, à une disposition de la abandonment, présente partie ou de ses règlements, que la condition ou la disposition ait trait, ou non, à the inspector may, after making reasonable efforts to la fin ou à l'abandon des activités, contact the person, take any reasonable measures to prevent, counteract, mitigate or remedy any resulting (ii) les activités minières antérieures, la fin ou adverse effect on persons, property or the l'abandon des activités risquent d'entraîner environment, and for that purpose may enter any un danger pour les personnes, les biens ou place, subject to subsection 112(2). l'environnement. (2) Any portion of the reasonable costs incurred by the (2) Les frais engagés par le Commissaire au titre du Commissioner pursuant to subsection (1) that is not paragraphe (1) constituent une créance de ce dernier recoverable from the security referred to in section 106 et dont le recouvrement peut être poursuivi contre la (a) because of the non-existence or inadequacy of personne visée au sous-alinéa (1)b)(i), faute de pouvoir that security; être recouvrés sur la garantie visée à l'article 106 pour l'un des motifs suivants : (b) because all or a portion of that security has been returned pursuant to subsection 106(6); a) garantie inexistante ou insuffisante; or b) garantie remise, en tout ou en partie, aux (c) for any other reason termes du paragraphe 106(6); may be recovered from the person referred to in c) tout autre motif. subsection (1) as a debt due to the Commissioner, to [L.Y. 2003, ch. 13, art. 114] the extent that the incurring of those costs was based on subparagraph (1)(b)(i). [S.Y. 2003, c. 13, s. 114] c UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON Page 55 Placer Mining Act Loi sur l’extraction de l’or PART 2 PARTIE 2 Section 115 Article 115 115 Obstruction (Entrave) 115 Obstruction 115 Entrave (1) No person shall wilfully obstruct or otherwise (1) Il est interdit d'entraver volontairement l'action de interfere with an inspector or the Chief when the l'inspecteur ou du directeur dans l'exercice des inspector or Chief is engaged in carrying out functions fonctions que lui confère la présente partie. under this Part. (2) No person shall knowingly make a false or (2) Il est interdit de faire, sciemment, oralement ou misleading statement, either orally or in writing, to an par écrit, une déclaration fausse ou trompeuse à inspector or the Chief when the inspector or Chief is l'inspecteur ou au directeur dans l'exercice des engaged in carrying out functions under this Part. fonctions que lui confère la présente partie. [S.Y. 2003, c. 13, s. 115] [L.Y. 2003, ch. 13, art. 115] 116 Regulations (Règlements) 116 Regulations 116 Règlements The Commissioner in Executive Council may make Le commissaire en conseil exécutif peut, par regulations règlement : (a) prescribing lands and categories of lands in a) déterminer les terres, ou les catégories de respect of which this Part, any provision of this terres, auxquelles s’applique tout ou partie de Part, the regulations, or any provision of the la présente partie ou de ses règlements; regulations, applies; b) prévoir les conditions d'exploitation applicables (b) prescribing operating conditions applicable to aux activités minières de type 1, 2, 3 ou 4, ou à Class 1, 2, 3, or 4 placer land use operations or toute activité, ou à tout groupe d'activités qui to any activity or group of activities included in en fait partie; any such operation; c) prévoir les critères de classification des (c) prescribing the criteria that determine whether activités minières de type 1, 2, 3 ou 4; a placer land use operation is a Class 1, 2, 3, c.01) établir : or 4 placer land use operation; (i) des zones à l’intérieur desquelles des (c.01) prescribing activités minières de type 1 sont des (i) areas within which a Class 1 placer land use activités minières désignées de type 1, operation is a designated Class 1 placer land (ii) une période aux fins de la définition de use operation, and « période de révision » à l’article 99; (ii) a period for the purposes of the definition c.02) établir des zones à titre de zones spéciales “review period” in section 99; d’exploitation; (c.02) prescribing areas as special operating areas; c.03) prévoir les formalités, les normes ou d’autres (c.03) prescribing procedures, standards or other exigences concernant l’établissement par le requirements in respect of the Chief’s directeur de conditions d’exploitation establishment of operating conditions for s’appliquant aux exploitations à l’intérieur des operations within special operating areas; zones spéciales d’exploitation; (d) prescribing the form of any Notification and of d) établir les formulaires des notifications et des applications referred to in section 105, the demandes visées à l'article 105, déterminer les information to be submitted in connection with renseignements à fournir à l'appui de ces avis a Notification or such application, and the form et de ces demandes, et fixer la forme de leur in which any of that information is to be présentation; submitted; e) régir le délai minimal d'envoi des notifications (e) respecting the minimum time interval between de type 2; giving a Class 2 Notification and commencing f) pour l’application de l’article 103 : to engage in the Class 2 placer land use (i) établir la formule et prévoir les modalités qui operation; s’appliquent lorsque le directeur doit : Page 56 UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON c Placer Mining Act Loi sur l’extraction de l’or PART 2 PARTIE 2 Section 116 Article 116 (f) for the purposes of section 103, (A) notifier une Première nation d’activités (i) prescribing the form and manner in which minières désignées de type 1, the Chief must (B) donner un avis mentionné au (A) notify a First Nation of a designated paragraphe 103(2), Class 1 placer land use operation, or (ii) prévoir les circonstances dans lesquelles un (B) give any notice referred to in avis mentionné au sous-alinéa (i) est réputé subsection 103(2), or reçu; (ii) prescribing circumstances in which a notice g) établir les formules à utiliser, en plus de celles referred to in subparagraph (i) is deemed to établies en vertu des alinéas d) ou f); have been received; h) pour l'application du paragraphe 102(5), (g) prescribing forms, in addition to any forms notamment en ce qui concerne son application, prescribed under paragraph (d) or (f); conformément au paragraphe 108(2), aux modifications et aux renouvellements, (h) for the purposes of subsection 102(5), and for déterminer :
Part document.segment-6
Placer Mining Act (Extraction de l’or) — segment 6
- document.segment-6 Verify source ↗
Placer Mining Act (Extraction de l’or) — segment 6
This provision lists offences and penalties for several placer mining contraventions, requires bilingual public notices or instruments, sets a two-year limitation period for section 117 prosecutions, and preserves existing rights and duties.
the purposes of that subsection in its (i) les circonstances dans lesquelles l’avis au application, pursuant to subsection 108(2), to amendments and renewals, respecting public des activités minières projetées est exigé, (i) the circumstances in which notice to the public of a planned placer land use operation (ii) les circonstances dans lesquelles la tenue is, or is not, required, d'une consultation publique est exigée, (ii) the circumstances in which a public (iii) la façon de notifier au public les activités consultation is, or is not, required, minières projetées ou la tenue de la consultation publique, (iii) the manner of notifying the public of a planned placer land use operation or about a (iv) les modalités de la tenue de la consultation public consultation, publique, (iv) the manner in which a public consultation (v) la ou les personnes chargées de la tenue de shall be held, and la consultation publique; (v) the person or persons who shall conduct a i) prévoir les modalités, notamment de durée ou public consultation; de durée maximale, des plans d'exploitation, y compris les modalités de remise en état des (i) prescribing conditions, including duration or lieux; maximum duration, of operating plans, including conditions requiring reclamation of j) régir l'exercice par le directeur du pouvoir the site; d'approbation, de modification et de renouvellement des plans d'exploitation; (j) respecting the exercise by the Chief of the power to approve operating plans, and k) régir la procédure et les délais à respecter pour amendments and renewals of them; l'approbation des plans d'exploitation, leur modification ou leur renouvellement, pour la (k) respecting the procedure and the time limits to révision des instructions de l'inspecteur visées be observed in respect of the approval of au paragraphe 113(3) et des décisions du operating plans, and amendments and directeur visées au paragraphe 113(4) ainsi que renewals of them, the review of inspectors' pour la délivrance des attestations directions under subsection 113(3) and of the d'achèvement des activités prévues aux Chief's decisions under subsection 113(4), and paragraphes 104(1) et (2); the issue of Certificates of Completion under subsections 104(1) and (2); l) fixer les droits à payer pour le dépôt d'une demande, y compris la demande de révision (l) prescribing fees to be paid for making any prévue aux paragraphes 113(3) et (4), ainsi que application, or for requesting a review les modalités, temporelles et autres, de leur mentioned in subsection 113(3) or (4), and paiement; prescribing the times at which and the manner m) régir : c UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON Page 57 Placer Mining Act Loi sur l’extraction de l’or PART 2 PARTIE 2 Section 116 Article 116 in which such fees must be paid; (i) le montant de la garantie prévue à (m) respecting l'article 106, et, éventuellement, habiliter le directeur à en fixer le montant, compte tenu (i) the amount of security that may be required du plafond précisé ou déterminé en to be furnished and maintained under conséquence, section 106, which regulations may empower the Chief to fix the amount of the security (ii) la révision du montant de la garantie fixé subject to a maximum specified in, or par le directeur, determined in accordance with, those (iii) les modalités et les conditions de celle-ci; regulations, n) régir la remise partielle de la garantie dans les (ii) the review of any amount of security fixed cas non prévus au paragraphe 106(6); by the Chief, and o) régir : (iii) the form and the terms of the security; (i) les circonstances dans lesquelles une (n) respecting partial returns of security in contravention à l'article 102, au situations other than those referred to in paragraphe 113(6) ou à une condition d'un subsection 106(6); plan d'exploitation en vue de prendre des (o) respecting mesures d'urgence ne constitue pas une infraction, (i) the circumstances in which a contravention of section 102, subsection 113(6) or a (ii) la façon d'informer le directeur, ou un condition of an approved operating plan, in inspecteur, de la prise de ces mesures, order to take emergency measures, is not an (iii) les obligations de remise en état du offence, périmètre touché, par la personne (ii) the reporting of such emergency measures responsable de ces mesures; to the Chief or an inspector, and p) prévoir les livres à tenir par le ministre, le (iii) the duties, in respect of the reclamation of directeur, l'inspecteur et l'exploitant; prévoir the area affected by those measures, of the leur forme, le lieu de leur tenue et leur période person who took those measures; de conservation; (p) prescribing the records to be kept by the q) prévoir les modalités d'exercice des fonctions Minister, the Chief, inspectors and operators, de l'inspecteur et du directeur ainsi que la and the form in which, the place in which and façon de préparer leurs rapports dans le cadre the period of time for which such records must de celles-ci; be kept; r) régir la teneur des instructions données par (q) prescribing the manner in which inspectors and l'inspecteur en vertu du paragraphe 113(1); the Chief must carry out their functions, and régir le délai pour s'y conformer et les respecting the making of reports by them in conséquences de la demande de révision, relation to their carrying out of their functions; prévue aux paragraphes 113(3) et (4), sur celui-ci; (r) respecting the content of directions given by inspectors under subsection 113(1), the time s) pour l'application des paragraphes 106(3) period within which such directions must be et 113(8), régir les conséquences de la complied with, and the effect on that time modification ou de l'annulation des instructions period of a request for a review of the direction en vertu du paragraphe 113(3) ou celles de la under subsection 113(3) or (4); modification ou de la substitution d'une décision en vertu du paragraphe 113(4); (s) respecting the effect of t) exiger un préavis public avant l'exercice des (i) an alteration or revocation of a direction attributions du ministre, visées au under subsection 113(3), or paragraphe 113(4), par une personne autre que (ii) an alteration or substitution of a decision le ministre et régir les circonstances dans under subsection 113(4) lesquelles un tel avis est obligatoire ainsi que la on the operation of subsections 106(3) and 113(8); façon de le donner; Page 58 UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON c Placer Mining Act Loi sur l’extraction de l’or PART 2 PARTIE 2 Section 117 Article 117 (t) requiring that public notice be given before the u) d'une façon générale, prendre toute mesure Minister's functions under subsection 113(4) nécessaire à l'application de la présente partie. may be exercised by a person other than the [L.Y. 2016, ch. 5, art. 42] [L.Y. 2013, ch. 18, art. 10] Minister, and respecting the circumstances in [L.Y. 2003, ch. 13, art. 116] which such public notice must be given, and the manner of giving that public notice; and (u) generally for carrying out the purposes and provisions of this Part. [S.Y. 2013, c. 18, s. 10] [S.Y. 2003, c. 13, s. 116] 117 Contraventions (Infractions) 117 Contraventions 117 Infractions (1) Any person who contravenes any of (1) Quiconque contrevient à l'un des subsections 102(1) to (3), or any condition of an paragraphes 102(1) à (3), ou aux conditions d'un plan approved operating plan of a Class 3 placer land use d'exploitation applicable à des activités minières de operation, is guilty of an offence and liable on type 3, commet une infraction et est passible, sur summary conviction to a fine not exceeding five déclaration de culpabilité par procédure sommaire, thousand dollars. d’une amende maximale de 5 000 $. (2) Any person who contravenes subsection 102(4), or (2) Quiconque contrevient au paragraphe 102(4), ou any condition of an approved operating plan of a aux conditions d'un plan d'exploitation applicable à des Class 4 placer land use operation, is guilty of an offence activités minières de type 4, commet une infraction et and liable on summary conviction to a fine not est passible, sur déclaration de culpabilité par exceeding twenty thousand dollars. procédure sommaire, d’une amende maximale de 20 000 $. (3) Any person who contravenes subsection 113(6) is (3) Quiconque contrevient au paragraphe 113(6) guilty of an offence and liable on summary conviction commet une infraction et est passible, sur déclaration to a fine not exceeding five thousand dollars. de culpabilité par procédure sommaire, d’une amende maximale de 5 000 $. (4) Any person who contravenes subsection 112(4) or (4) Quiconque contrevient au paragraphe 112(4), ou à section 115 is guilty of an offence and liable on l'article 115, commet une infraction et est passible, sur summary conviction to a fine not exceeding ten déclaration de culpabilité par procédure sommaire, thousand dollars. d’une amende maximale de 10 000 $. (5) Any (5) Commet une infraction et est passible, sur (a) person who contravenes a regulation made déclaration de culpabilité par procédure sommaire, under paragraph 116(o) relating to the d’une amende maximale de 2 000 $ : reporting of emergency measures or the a) quiconque contrevient à un règlement reclamation of the area; and d'application de l'alinéa 116o) concernant la (b) operator who contravenes a regulation made façon d'informer l'inspecteur de la prise de under paragraph 116(p) mesures d'urgence ou la remise en état du périmètre touché par celles-ci; is guilty of an offence and liable on summary conviction to a fine not exceeding two thousand dollars. b) l'exploitant qui contrevient à un règlement d'application de l'alinéa 116p). (6) Where an offence under this section is committed (6) Il est compté une infraction distincte pour chacun on, or continued for, more than one day, it is deemed des jours au cours desquels toute infraction prévue au to be a separate offence for each day on which it is présent article se commet ou se poursuit. committed or continued. [S.Y. 2003, c. 13, s. 117] [L.Y. 2003, ch. 13, art. 117] c UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON Page 59 Placer Mining Act Loi sur l’extraction de l’or PART 2 PARTIE 2 Section 118 Article 118 118 Limitation period (Prescription) 118 Limitation period 118 Prescription Proceedings in respect of an offence under section 117 Les poursuites visant une infraction à l'article 117 may be instituted at any time within, but not later peuvent être entreprises à tout moment avant leur than, two years after the time when the Minister délai de prescription de deux ans à compter de la date becomes aware of the subject-matter of the à laquelle le ministre a eu connaissance des éléments proceedings. constitutifs de l'infraction. (2) A document purporting to have been issued by the (2) Le document censé être délivré par le ministre et Minister, certifying the day on which the Minister attestant la date où ces éléments sont parvenus à sa became aware of the subject-matter of any connaissance fait foi, en l'absence de preuve contraire, proceedings, is admissible in evidence in any court sans qu'il soit nécessaire de prouver l'authenticité de la without proof of the signature or official character of signature qui y est apposée ou la qualité officielle du the person appearing to have signed it, and is, unless signataire. the contrary is shown, proof of the matters asserted in it. [S.Y. 2003, c. 13, s. 118] [L.Y. 2003, ch. 13, art. 118] 119 Action to enjoin not prejudiced (Injonction) 119 Action to enjoin not prejudiced 119 Injonction (1) Despite that a prosecution has been instituted in (1) Même après l'engagement de poursuites visant respect of an offence under section 117, the Minister of l'une quelconque des infractions prévues à l'article 117, Justice may commence and maintain proceedings to le ministre de la Justice peut engager des procédures enjoin conduct that constitutes an offence under that en vue de faire cesser la cause de l'infraction. section. (2) No civil remedy for any act or omission is (2) Les recours civils restent ouverts dans le cas de suspended or affected by reason only that the act or tout acte ou omission constituant une infraction à omission is an offence under section 117. l'article 117. [S.Y. 2003, c. 13, s. 119] [L.Y. 2003, ch. 13, art. 119] 120 Language (Langues) 120 Language 120 Langues (1) Any notice or advertisement or other matter that is (1) Tout avis, toute publicité et toute autre affaire dont required or authorized by this Act to be published by or la publication est exigée ou autorisée par la présente under the authority of the Government of the Yukon or loi pour le compte, ou sous l’autorité, du gouvernement a public officer primarily for the information of the du Yukon, ou d’un fonctionnaire, et ce, principalement public shall dans le but de renseigner le public, doivent : (a) wherever possible, be printed in English in at a) dans la mesure du possible, être imprimés en least one publication in general circulation anglais dans au moins une publication de within each region where the matter applies diffusion générale paraissant entièrement ou that appears wholly or mainly in English, and principalement en anglais, dans la région où be printed in French in at least one publication s’appliquent les affaires en question, et être in general circulation within each region where imprimés en français dans au moins une the matter applies that appears wholly or publication de diffusion générale paraissant mainly in French, equal prominence being entièrement ou principalement en français, given to each version; and dans la région où s’appliquent les affaires en question, égale importance étant donnée à chaque version; Page 60 UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON c Placer Mining Act Loi sur l’extraction de l’or PART 3 PARTIE 3 Section 121 Article 121 (b) where there is no publication in general b) dans une région où il n’existe aucune circulation within a region where the matter publication de diffusion générale paraissant applies that appears wholly or mainly in entièrement ou principalement en français, être French, be printed in both English and French imprimés en anglais et en français dans au in at least one publication in general circulation moins une publication de diffusion générale, within that region, equal prominence being égale importance étant donnée à chaque given to each version. version. (2) Any instrument directed to or intended for the (2) Les actes qui s’adressent au public et qui sont notice of the public, purporting to be made or issued censés émaner du gouvernement du Yukon ou d’un by or under the authority of the Government of the fonctionnaire ou sous son autorité en vertu de la Yukon or a public officer pursuant to this Act, shall be présente loi, sont établis ou délivrés en anglais et en made or issued in both English and French. français. [S.Y. 2003, c. 13, s. 120] [L.Y. 2003, ch. 13, art. 120] PART 3 (PARTIE 3) PART 3 PARTIE 3 TRANSITIONAL PROVISIONS (DISPOSITIONS TRANSITOIRES) TRANSITIONAL PROVISIONS DISPOSITIONS TRANSITOIRES 121 Existing rights and duties continued (Droits existants) 121 Existing rights and duties continued 121 Droits existants All rights and duties accrued or accruing under the Les droits et les obligations acquis en vertu de la Loi Yukon Placer Mining Act (Canada) in lands or precious sur l’extraction de l’or dans le Yukon (Canada) touchant minerals that come under the administration and les terres ou les minéraux précieux sous la maîtrise et control of the Commissioner continue in effect as rights la gestion du Commissaire demeurent en vigueur à and duties under and subject to this Act. titre de droits et obligations, en vertu et sous réserve des dispositions de la présente loi. [S.Y. 2003, c. 13, s. 121] [L.Y. 2003, ch. 13, art. 121] 122 Miners Lien Act amended (Modification à la Loi sur les privilèges miniers) 122 Miners Lien Act amended 122 Modification à la Loi sur les privilèges miniers (1) This section amends the Miners Lien Act. (1) Le présent article modifie la Loi sur les privilèges miniers. (2) In section 1 of the said Act the definition “‘mine’ or (2) La définition de « mine » ou « claim minier », à ‘mining claim’” is amended by repealing the l’article 1 de la même loi, est modifiée par abrogation expression “Yukon Placer Mining Act (Canada)” and de l’expression « ou de la Loi sur l’extraction de l’or substituting for it the expression “Yukon Placer Mining dans le Yukon » et son remplacement par l’expression Act (Canada) or Placer Mining Act.” « ,de la Loi sur l’extraction de l’or dans le Yukon (Canada) ou de la Loi sur l’extraction de l'or ». [S.Y. 2003, c. 13, s. 122] [L.Y. 2003, ch. 13, art. 122] 123 Securities Act amended (Modification à la Loi sur les valeurs mobilières) 123 Securities Act amended 123 Modification à la Loi sur les valeurs mobilières (1) This section amends the Securities Act. (1) Le présent article modifie la Loi sur les valeurs mobilières. c UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON Page 61 Placer Mining Act Loi sur l’extraction de l’or PART 3 PARTIE 3 Section 124 Article 124 (2) In section 1 of the said Act paragraph (p) of the (2) L’alinéa p) de la définition de « valeur » ou definition “security” is amended by repealing the « valeur mobilière », à l’article 1 de la même loi, est expression “Yukon Placer Mining Act (Canada)” and modifié par abrogation de l’expression « Loi sur substituting for it the expression “Yukon Placer Mining l’extraction de l’or dans le Yukon (Canada) » et son Act (Canada) or Placer Mining Act.” remplacement par l’expression « Loi sur l’extraction de l’or dans le Yukon (Canada), ou de la Loi sur l’extraction de l'or ». [S.Y. 2003, c. 13, s. 123] [L.Y. 2003, ch. 13, art. 123] 124 Workers’ Compensation Act amended (Modification à la Loi sur les accidents du travail) 124 Workers’ Compensation Act amended 124 Modification à la Loi sur les accidents du travail (1) This section amends the Workers’ (1) Le présent article modifie la Loi sur les accidents Compensation Act. du travail. (2) In subsection 72(5) of the said Act the expression (2) Le paragraphe 72(5) de la même loi est modifié par “Yukon Placer Mining Act” is repealed and the abrogation de l’expression « Loi sur l’extraction de l’or expression “Yukon Placer Mining Act (Canada) or Placer dans le Yukon » et son remplacement par l’expression Mining Act” is substituted for it. « Loi sur l’extraction de l’or dans le Yukon (Canada) ou de la Loi sur l’extraction de l'or ». [S.Y. 2003, c. 13, s. 124] [L.Y. 2003, ch. 13, art. 124] 125 Coming into force (Entrée en vigueur) 125 Coming into force 125 Entrée en vigueur This Act comes into force when the repeal of the Yukon La présente loi entre en vigueur lors de l’abrogation de Placer Mining Act (Canada) takes effect and will then la Loi sur l’extraction de l’or dans le Yukon (Canada) et apply to matters that were governed by the Yukon régira alors les objets de la Loi sur l’extraction de l’or Placer Mining Act (Canada) before this Act came into au Yukon (Canada) avant sa prise d’effet. force. [S.Y. 2003, c. 13, s. 125] [L.Y. 2003, ch. 13, art. 125] Page 62 UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON c Placer Mining Act Loi sur l’extraction de l’or SCHEDULE 1 ANNEXE 1 SCHEDULE 1 FORM 1 (Section 27) APPLICATION FOR GRANT FOR PLACER MINING AND AFFIDAVIT OF APPLICANT No. I, (or we), ____________, of ____________ hereby apply, under the Placer Mining Act, for a grant of a claim for placer mining as defined in that Act, in (here describe locality) and I (or we) make oath and say: 1. That to the best of my (or our) knowledge and belief the land is such as can be located under section 17 of the Placer Mining Act. 2. That I (or we) did on the ____________ day of ____________, 20____, mark out on the ground, in accordance in every particular with the provisions of the Placer Mining Act, the claim for which I (or we) make this application, and in so doing I (or we) did not encroach on any other claim or mining location previously laid out by any other person. 3. That the length of the said claim, as nearly as I (or we) could measure, is _______ feet, and that the description attached, signed by me (or us), sets out in detail, to the best of my (or our) knowledge and ability, its position. 4. That I (or we) staked out the claim by planting two legal posts numbered 1 and 2, respectively, and that No. 1 is ____________ discovery. 5. That I (or we) make this application in good faith to acquire the claim for the sole purpose of mining to be prosecuted by myself (or us) or by myself (or ourselves) and associates or by my (or our) assigns. Sworn before me at ____________, Yukon, this ____________ day of ____________, 20____ A commissioner for taking affidavits in Yukon (or as the case may be). c UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON Page 63 Placer Mining Act Loi sur l’extraction de l’or SCHEDULE 1 ANNEXE 1 ANNEXE 1 FORMULAIRE 1 (article 27) DEMANDE D’UNE CONCESSION D’UN CLAIM D’EXPLOITATION DE PLACER ET AFFIDAVIT DU REQUÉRANT No Je, (Nous), sousigné(e)(s), ____________, de ____________, par les présentes demande (demandons), en vertu de la Loi sur l’extraction de l’or, la concession d’un claim d’exploitation de placer tel qu’il est défini dans cette loi, dans (mentionner ici la localité), et je jure et dis (nous jurons et disons) : 1. Que, à ma (notre) connaissance, le terrain est tel qu’il peut être établi sous l’autorité de l’article 17 de la Loi sur l’extraction de l’or. 2. Que le ____________ 20____, j’ai (nous avons), jalonné sur le terrain, conformément en tout point aux dispositions de la Loi sur l’extraction de l’or, le claim pour lequel je fais (nous faisons) cette demande, et que, ce faisant, je n’ai (nous n’avons) empiété sur aucun autre claim ou emplacement minier antérieurement indiqué par une autre personne. 3. Que, ayant effectué les meilleures mesures possibles, la longueur de ce claim est de _______ pieds, et que la description annexée à la présente, signée par moi (nous), énonce en détail sa situation, au mieux de mes (nos) connaissance et de ma (notre) capacité. 4. Que j’ai (nous avons) marqué le claim en y plantant deux bornes légales numérotées 1 et 2, respectivement, et que la borne no 1 est ____________ découverte. 5. Que je fais (nous faisons) cette demande de bonne foi pour acquérir le claim dans le seul but de l’exploiter moi- même (nous mêmes), ou seul(s) avec mes (nos) associés, ou qu’il le soit par mes (nos) ayants droit. Assermenté devant moi à ___________, Yukon, le ____________ 20____ Le commissaire nommé pour recevoir des affidavits au Yukon (ou selon le cas). Page 64 UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON c Placer Mining Act Loi sur l’extraction de l’or SCHEDULE 1 ANNEXE 1 FORM 2 (Section 27) APPLICATION FOR RENEWAL OF GRANT FOR PLACER MINING AND AFFIDAVIT OF APPLICANT No. I, (or we), ____________, of ____________ (agent for ____________ of ____________, if such be the fact) hereby apply under the Placer Mining Act for a renewal of a grant to the placer mining claim ____________, in the ____________ mining district, which grant is number .____________, and was issued to ____________, on the ____________ day of ____________, 20____, and I make oath and say: 1. That I am (or we are) (the agent of ____________, if deponent is an agent of the owner) the owner (or owners) of placer mining claim ____________, in the ____________ mining district, and hold (or that they hold) a grant for the said claim dated the ____________ day of ____________, 20____ 2. That work has been done on the said claim to the value of at least two hundred dollars, in accordance with the schedule of representation work prepared by the Commissioner, between the ____________ day of ____________, 20____, and the ____________ day of ____________, 20____ The following is a detailed statement of that work: ____________. Sworn before me at ____________, Yukon, this ____________ day of ____________, 20____ A commissioner for taking affidavits in Yukon (or as the case may be). c UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON Page 65 Placer Mining Act Loi sur l’extraction de l’or SCHEDULE 1 ANNEXE 1 FORMULAIRE 2 (article 27) DEMANDE DE RENOUVELLEMENT DE LA CONCESSION D’UN CLAIM D’EXPLOITATION DE PLACER ET AFFIDAVIT DU REQUÉRANT No Je, (Nous), soussigné(e)(s), ____________, de ____________ (agent(s) pour ____________. de ____________, si tel est le cas) par les présentes demande (demandons), en vertu de la Loi sur l’extraction de l’or, le renouvellement de l’acte de concession du claim d’exploitation de placer ____________, dans le district minier ____________; cet acte de concession porte le numéro ____________ et a été délivré à ____________, le ____________ 20____, et je jure et dis (nous jurons et disons) : 1. Que je suis (nous sommes) (l’agent ou les agents de ____________, si le témoin est un agent du propriétaire), le propriétaire (les propriétaires) du claim d’exploitation de placer ____________, dans le district minier ____________, et que je possède (nous possédons), (qu’il possède ou qu’ils possèdent) un acte de concession de ce claim, en date du ____________ 20____. 2. Qu’il a été fait, sur ce claim, des travaux pour une valeur d’au moins 200 $, conformément au tableau des travaux obligatoires dressé par le Commissaire, entre le ____________ 20____ et le ____________ 20____. Suit un état détaillé de ces travaux : ____________________________________ Assermenté devant moi, à ____________, Yukon, le ____________.20____. Le commissaire nommé pour recevoir des affidavits au Yukon (ou selon le cas). Page 66 UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON c Placer Mining Act Loi sur l’extraction de l’or SCHEDULE 1 ANNEXE 1 FORM 3 (Sections 27 and 32) GRANT FOR PLACER MINING No. Department of Economic Development, 20____ In consideration of the payment of ____________ dollars, being the fee prescribed by Schedule 2 to the Placer Mining Act, by ____________, of ____________, accompanying their application No. ____________ dated ____________, 20____, for a mining claim in (here insert description of locality). The Minister hereby grants to the said ____________ for a term of ____________ years from the date of this grant, the exclusive right of entry on the claim (here describe in detail the claim granted) for the miner-like working thereof, and the construction and maintenance of structures, including a residence, that are required for the miner-like working thereof, and the exclusive right to all the proceeds realized therefrom, on which, however, the royalty prescribed by the Placer Mining Act shall be paid. The said ____________ shall be entitled to the use of so much of the water naturally flowing through or past their claim, and not already lawfully appropriated, as shall be necessary for the due working thereof, and to drain their claim, free of charge. This grant does not convey to the said ____________ any right of ownership in the soil covered by the said claim, and the said grant shall lapse and be forfeited unless section 41 of the Placer Mining Act is strictly complied with. The rights hereby granted are those laid down in the Placer Mining Act and no more, and subject to all the provisions of that Act, whether they are expressed in this grant or not. _______________ Mining Recorder c UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON Page 67 Placer Mining Act Loi sur l’extraction de l’or SCHEDULE 1 ANNEXE 1 FORMULAIRE 3 (articles 27 et 32) ACTE DE CONCESSION D’UN CLAIM D’EXPLOITATION DE PLACER No Ministère de l’Expansion économique 20____ En contrepartie du paiement de la somme de ____________ $, qui est le droit prévu à l’annexe 2 de la Loi sur l’extraction de l’or, par ____________, de ____________, et qui accompagne son (leur) demande no____________ en date du ____________ 20____, d’un claim minier dans (décrire la localité). Par les présentes, le ministre concède à ____________, pour une période de ____________ans à compter de la date de cette concession, le droit exclusif d’entrer sur le claim (décrire ici en détail le claim concédé) pour l’exploiter en mineur, y construire des installations notamment, une maison d’habitation nécessaires à cette fin, et les entretenir, avec le droit exclusif à tous les produits qui en proviennent, sur lesquels devra toutefois être payée la redevance prévue par la Loi sur l’extraction de l’or. Dans la mesure nécessaire à l’exploitation convenable de son (leur) claim, ____________ a (ont) droit à l’usage de l’eau dont le cours naturel passe, traverse ou longe ce claim et qui n’est pas encore légalement prise, et a (ont) droit d’assécher gratuitement son (leur) claim. La présente concession ne transmet à ____________ aucun droit de propriété sur le sol que couvre ce claim, et cette concession deviendra nulle et tombera en déchéance à moins que les prescriptions de l’article 41 de la Loi sur l’extraction de l’or ne soient strictement observées. Les droits concédés par la présente sont les droits établis dans la Loi sur l’extraction de l’or à l’exclusion de tout autre; ils sont subordonnés à toutes les dispositions de cette loi, que celles-ci soient énoncées dans la présente ou non. __________________ Le registraire minier Page 68 UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON c Placer Mining Act Loi sur l’extraction de l’or SCHEDULE 1 ANNEXE 1 FORM 4 (Section 58) GRANT OF RIGHT TO DIVERT WATER AND CONSTRUCT DITCHES No. Minister of ____________, ____________, 20____ In consideration of the sum of ____________ dollars paid on the date application is made for this grant, the Minister, in accordance with the Placer Mining Act, hereby grants to ____________ for the term of ____________ years from the date of this grant, the right to divert, take (sell, to be inserted in a grant to sell water) and use the water from ____________ to the extent of ____________ inches, and no more, to be distributed as follows: and the right-of-way through and entry on the following mining grounds: for the purpose of constructing ditches and flumes to convey the water, provided that at least the sum of ____________ dollars shall be expended on the ditches and flumes within one year from the date of this grant, and provided that the ditches and flumes are constructed and in working order within ____________ from the date of this grant: Provided that this grant shall be deemed to be appurtenant to placer claim No. ____________, and shall cease and determine whenever the claim has been worked out or abandoned or the occasion for the use of the water on the claim has permanently ceased: (If the right to sell water is granted, insert the following) Provided also, that the price charged for the water shall be subject to the control of the Minister, and the water shall be supplied to all claim owners who apply therefor in a fair proportion and without any discrimination. Provided also, that this grant is subject to all the provisions of the Placer Mining Act in that behalf whether the same are expressed in this grant or not. It is expressly a condition of this grant that the same is issued subject to all rights subsisting at this date to the water in respect to which this grant is issued. Water to be flumed and tailings to be handled to the satisfaction of a mining inspector. _______________ Mining Recorder c UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON Page 69 Placer Mining Act Loi sur l’extraction de l’or SCHEDULE 1 ANNEXE 1 FORMULAIRE 4 (article 58) CONCESSION DU DROIT DE DÉTOURNER L’EAU ET DE CONSTRUIRE DES FOSSÉS No Ministre ________________________, ____________ 20____ En contrepartie de la somme de ____________ $ payée le jour où demande de la présente concession a été présentée, le ministre, conformément à la Loi sur l’extraction de l’or, concède à ____________, pour une période de ____________ ans à compter de la date des présentes, le droit de détourner, de prendre, (vendre, mot à insérer dans un acte de concession qui permet de vendre de l’eau) et d’utiliser de l’eau du ____________ jusqu’à concurrence de ____________ pouces, au maximum, à distribuer comme suit : avec le droit de passer et d’aller sur les terrains miniers suivants : dans le but de construire des fossés et des conduites d’amenée, pourvu que la somme d’au moins ____________ $ soit dépensée pour ces fossés et conduites d’amenée au cours de l’année qui suit la date des présentes, et pourvu que ces fossés et conduites d’amenée soient construits et en état de fonctionnement dans les ____________ qui suivent la date des présentes. Il est entendu que la présente concession doit être considérée comme attachée au claim no……….. et qu’elle s’éteindra et prendra fin lorsque ce claim aura été épuisé ou abandonné, ou qu’il n’y aura plus jamais lieu de se servir de cette eau sur ce claim. (Si le droit de vendre de l’eau est accordé, insérer ce qui suit :) Il est aussi entendu que le prix de vente de l’eau sera soumis au contrôle du ministre, et que l’eau sera fournie, dans une raisonnable proportion et sans distinction, à tous les propriétaires de claims qui en feront la demande. Il est aussi entendu que la présente concession est subordonnée à toutes les dispositions de la Loi sur l’extraction de l’or sous ce rapport, que ces dispositions soient énoncées dans les présentes ou non. La présente concession a pour condition formelle d’être accordée entièrement sous réserve de tous droits actuellement existants relatifs à l’eau pour laquelle cette concession est accordée. L’eau doit être conduite et les résidus doivent être déchargés à la satisfaction de l’inspecteur des exploitations minières. __________________ Le registraire minier Page 70 UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON c Placer Mining Act Loi sur l’extraction de l’or SCHEDULE 1 ANNEXE 1 FORM 5 (Section 75) TUNNEL OR DRAIN LICENCE No. To all whom it may concern: Take notice that ____________, the owner of placer claim ____________, in ____________ Mining District, having given security to the amount of ____________ for any damage they may do, has this day obtained a licence from me to run a tunnel (or drain) from ____________ to their claim. The licence is granted on these express conditions: (set out conditions, if any). Dated at ____________, the ____________ day of ____________, 20____ _______________ Mining Recorder c UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON Page 71 Placer Mining Act Loi sur l’extraction de l’or SCHEDULE 1 ANNEXE 1 FORMULAIRE 5 (article 75) PERMIS POUR CANAL SOUTERRAIN OU CONDUITE No À toutes les personnes intéressées : Sachez que ____________, propriétaire du claim d’exploitation de placer ____________ dans le district minier ____________, après avoir fourni une caution d’un montant de ____________ $ pour tout dommage qu’il pourra causer, a, ce jour, obtenu de mes services un permis l’autorisant à pratiquer un canal souterrain (ou une conduite) depuis ____________ jusqu’à son claim. Ce permis est assujetti aux conditions formelles suivantes : (énoncer les conditions, s’il y a lieu). Fait à ____________, le ____________ 20____ __________________ Le registraire minier Page 72 UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON c Placer Mining Act Loi sur l’extraction de l’or SCHEDULE 1 ANNEXE 1 FORM 6 (Section 92) APPLICATION FOR A LEASE TO PROSPECT AND AFFIDAVIT OF THE APPLICANT I, ____________, of ____________, hereby apply under the Placer Mining Act for a lease to prospect in the manner defined in that Act on that portion of ____________ creek (or river), which may be described as follows: and I make oath and say: 1. That to the best of my knowledge and belief the land is such as may be located for prospecting purposes under the Placer Mining Act. 2. That I did on the ____________ day of ____________, 20____, mark out on the ground in accordance in every particular with the Placer Mining Act the location for which I make this application. 3. That the length of the location, as nearly as I could measure it, is ____________ feet, and that the description above given in detail sets out to the best of my knowledge and ability its position. 4. That I staked out the location by planting two legal posts, numbered 1 and 2, respectively, and that No. 1 is the down stream post of the location. 5. That no placer mining claims are now recorded on the tract applied for, and that no placer mining operations are now being conducted thereon. 6. That I make this application in good faith to acquire a prospecting lease for the sole purpose of prospecting and mining to be prosecuted by myself, or by myself and associates, or by my assigns. Sworn before me at ____________, Yukon, this ____________ day of ____________, 20____ A commissioner for taking affidavits in Yukon (or as the case may be). c UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON Page 73 Placer Mining Act Loi sur l’extraction de l’or SCHEDULE 1 ANNEXE 1 FORMULAIRE 6 (article 92) DEMANDE D’UN BAIL DE PROSPECTION ET AFFIDAVIT DU REQUÉRANT Je soussigné ____________, de ____________, demande par les présentes, en vertu des dispositions de la Loi sur l’extraction de l’or, un bail autorisant des recherches, de la manière que définit cette loi, sur cette partie du ruisseau (ou de la rivière) ____________ qui peut être décrite comme suit : et je déclare sous serment : 1. Qu’à ma connaissance, le terrain est tel qu’il peut être localisé pour des fins de prospection en vertu des dispositions de la Loi sur l’extraction de l’or. 2. Que le ____________ 20____, j’ai marqué sur le terrain, conformément en tout point aux dispositions de la Loi sur l’extraction de l’or, l’emplacement qui fait l’objet de la présente demande. 3. Que la longueur de l’emplacement, aussi exactement que j’aie pu la mesurer, est de ____________ pieds, et que la description détaillée susmentionnée établit la situation du mieux que je sache et qu’il me soit possible de le faire. 4. Que j’ai jalonné l’emplacement et planté deux bornes légales numérotées respectivement 1 et 2, et que la borne no 1 est la borne d’aval de l’emplacement. 5. Qu’aucun claim d’exploitation de placer n’est actuellement enregistré sur l’étendue de terrain demandée, et qu’il ne s’y fait présentement aucune opération minière. 6. Que je fais cette demande de bonne foi pour acquérir un bail de prospection dans le seul but de faire des recherches et d’exploiter la mine moi-même, ou seul avec mes associés, ou mes ayants droit. Assermenté devant moi à ____________, Yukon, le ____________ 20____. Le commissaire nommé pour recevoir des affidavits au Yukon (ou selon le cas). Page 74 UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON c Placer Mining Act Loi sur l’extraction de l’or SCHEDULE 1 ANNEXE 1 FORM 7 (Section 52) GROUPING CERTIFICATE Fee paid: $________________________ Mining District In accordance with section 52 of the Placer Mining Act, the owners of the following claims are permitted to group those claims together for the performance of work: ____________. Dated at ____________, this ____________ day of ____________, 20____ ________________ Mining Recorder c UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON Page 75 Placer Mining Act Loi sur l’extraction de l’or SCHEDULE 1 ANNEXE 1 FORMULAIRE 7 (article 52) CERTIFICAT DE GROUPEMENT Droits payés : ____________ $, District minier ____________.. Conformément à l’article 52 de la Loi sur l’extraction de l’or, il est permis aux propriétaires des claims suivants de grouper ces claims pour l’exécution des travaux : ________________________ Fait à ____________, le ____________ 20____. __________________ Le registraire minier Page 76 UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON c Placer Mining Act Loi sur l’extraction de l’or SCHEDULE 2 ANNEXE 1 SCHEDULE 2 (Section 87) FEES 1. For grant of a claim for one year $10.00 2. For grant of a claim for five years 50.00 3. For renewal of grant of a claim: For one year 10.00 For two years 20.00 For three years 30.00 For four years 40.00 For five years 50.00 4. Recording an abandonment 2.00 5. For a grouping certificate: (a) Ten claims or under 5.00 (b) Over ten claims 5.00 For each claim over ten 1.00 6. Registration of any document 2.00 If it affects more than one claim, for each additional claim 1.00 7. For filing any document 1.00 8. Abstract of Title: For first entry 1.00 For each additional entry 0.10 9. For copies of any documents recorded: Up to three folios 3.00 For each additional folio 0.50 10. For grant of water: Of 50 inches or less 10.00 From 50 to 200 inches 25.00 From 200 to 1,000 inches 50.00 For each additional 1,000 inches or fraction 50.00 c UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON Page 77 Placer Mining Act Loi sur l’extraction de l’or SCHEDULE 2 ANNEXE 2 ANNEXE 2 (article 87) DROITS 1. Concession d’un claim pour un an 10 00 $ 2. Concession d’un claim pour cinq ans 50 00 $ 3. Renouvellement de la concession d’un claim : pour un an 10 00 $ pour deux ans 20 00 $ pour trois ans 30 00 $ pour quatre ans 40 00 $ pour cinq ans 50 00 $ 4. Inscription d’un abandon 2 00 $ 5. Certificat de groupement : a) dix claims ou moins 5 00 $ b) au-delà de dix claims 5 00 $ Pour chaque claim au-delà de dix 1 00 $ 6. Inscription de tout document 2 00 $ S’il porte sur plus d’un claim, pour chaque claim supplémentaire 1 00 $ 7. Réception d’un document de dépôt 1 00 $ 8. Relevé des titres : pour la première inscription 1 00 $ pour chaque inscription supplémentaire 0 10 $ 9. Transcription de documents inscrits : jusqu’à trois feuillets 3 00 $ pour chaque feuillet supplémentaire 0 50 $ 10. Concession hydraulique : de 50 pouces ou moins 10 00 $ de 50 à 200 pouces 25 00 $ de 200 à 1 000 pouces 50 00 $ par 1 000 pouces additionnels ou fraction de 1 000 pouces 50 00 $ Page 78 UNOFFICIAL CONSOLIDATION OF THE STATUTES OF YUKON CODIFICATION NON OFFICIELLE DES LOIS DU YUKON c
Provision text is displayed from LexChat’s stored statute record. Use the official source links to verify amendments, commencement, and current legal force.
Ask AI about this statute
Placer Mining Act (Extraction de l’or)
Sign in to ask AI about this statute
Sign in to start authenticated, citation-grounded statute research.
Sign inLexChat organizes source-backed legal information for research. Verify amendments, commencement, and current legal force with the official publisher before relying on it.