Schedule of Representation Work (Quartz Mining), 2003
This schedule sets assessment-work rates and filing/reporting rules for quartz claims, including some work that needs prior approval and some safety-related requirements.
- Jurisdiction
- Canada — Yukon
- Instrument
- Regulation
- Version
- Undated source snapshot
- Language
- en
- Official source
- View official record ↗
Statute overview
About this statute
This page preserves the statute’s identified version, provision structure, official source link, and stored legal text for reading and research.
Search within this statute
Search all stored provisions in this version.
Legal text
Provisions of Schedule of Representation Work (Quartz Mining), 2003
Showing 1 of 1
- § Verify source ↗
Schedule of Representation Work (Quartz Mining), 2003
This schedule sets assessment-work rates and filing/reporting rules for quartz claims, including some work that needs prior approval and some safety-related requirements.
QUARTZ MINING ACT LOI SUR L’EXTRACTION DU QUARTZ SCHEDULE OF REPRESENTATION WORK ANNEXE DES TRAVAUX OBLIGATOIRES (QUARTZ MINING), 2003 (EXTRACTION DU QUARTZ) 2003 O.I.C. 2003/251 DÉCRET 2003/251 Effective Date: Date d'entrée en vigueur : September 16, 2003 16 septembre 2003 September 30, 2022 Schedule of Representation Work (Quartz Mining), 2003 Annexe des travaux obligatoires (extraction du quartz) 2003 ORDER-IN-COUNCIL DÉCRET EN CONSEIL O.I.C. 2003/251 DÉCRET 2003/251 QUARTZ MINING ACT LOI SUR L’EXTRACTION DU QUARTZ SCHEDULE OF REPRESENTATION WORK ANNEXE DES TRAVAUX OBLIGATOIRES (QUARTZ MINING), 2003 (EXTRACTION DU QUARTZ) 2003 Pursuant to section 56 of the Quartz Mining Act, the Le commissaire en conseil exécutif, conformément à Commissioner in Executive Council orders as follows l’article 56 de la Loi sur l’extraction du quartz, décrète : 1. The annexed Schedule of Representation Work 1. Est établie l’Annexe des travaux obligatoires (Quartz Mining), 2003 is hereby established. (extraction du quartz) 2003 paraissant en annexe. 2. The Schedule of Representation Work (Quartz 2. L’Annexe des travaux obligatoires (extraction du Mining) is revoked. quartz) est révoquée. Dated at Whitehorse, Yukon, this September 16, 2003. Fait à Whitehorse, au Yukon, le 16 septembre 2003. Commissioner of Yukon/Commissaire du Yukon Page ii YUKON REGULATIONS RÈGLEMENTS DU YUKON c September 30, 2022 Schedule of Representation Work (Quartz Mining), 2003 Annexe des travaux obligatoires (extraction du quartz) 2003 Section 1. Article 1. OQ.UIA.CR. T2Z0 0M3I/N2I5N1G ACT DLOÉIC RSEUTR 2 L0’E0X3T/2R5A1CT ION DU QUARTZ SCHEDULE OF REPRESENTATION WORK ANNEXE DES TRAVAUX OBLIGATOIRES (QUARTZ MINING), 2003 (EXTRACTION DU QUARTZ) 2003 SECTION 56(1), QUARTZ MINING ACT LOI SUR L’EXTRACTION DU QUARTZ, PARAGRAPHE 56(1) Revised 1 May 2003 Révision du 1er mai 2003 The following schedule prescribes: La présente annexe établit: A rates for determining the value of assessment A les taux servant à déterminer la valeur de work done on quartz mineral claims; l’évaluation effectuée sur un claim minier de quartz; B conditions governing the acceptance of other types B les conditions régissant l’acceptation de tout autre of work and reporting requirements; type de travaux ainsi que les exigences pour soumettre des renseignements; C conditions governing the acceptance of and C les conditions régissant l’acceptation de travaux reporting requirements for work requiring prior qui requièrent l’approbation préalable du registraire approval of the Mining Recorder; and minier et les exigences de soumission de renseignements qui s’y rapportent; [Paragraph C amended by O.I.C. 2015/20] D the valuing of work done on a claim in the 2016- D Détermination de la valeur des travaux effectués 2017 double-value year. au cours de l’année à valeur doublée 2016-2017. [Paragraph D added by O.I.C. 2015/20] [Rubrique D ajoutée par Décret 2015/20] [Paragraph D amended by O.I.C. 2016/133] [Rubrique D modifée par Décret 2016/133] Please refer to Grouping Guidelines when filing Veuillez consulter les directives de regroupement lors assessment work. de l’enregistrement de travaux obligatoires. c YUKON REGULATIONS RÈGLEMENTS DU YUKON Page 1 September 30, 2022 Schedule of Representation Work (Quartz Mining), 2003 Annexe des travaux obligatoires (extraction du quartz) 2003 Section 1. Article 1. Government of Yukon Gouvernement du Yukon A - Rates A - Taux A renewal application in the form of a sworn affidavit Une demande de renouvellement doit être déposée au as prescribed by Schedule I, Form 4, Quartz Mining Act bureau de district du registraire minier sous forme de together with the fees, and a sketch or map of the déclaration assermentée, tel que prescrit par l’Annexe individual claim(s) on which the work was performed, I, Formulaire 4, de la Loi sur l’extraction du quartz, showing the location of the work relative to claim accompagnée des droits ainsi que d’un croquis ou boundaries, must be submitted to the office of the d’une carte indiquant la localisation des travaux District Mining Recorder. relativement aux limites du claim, pour chaque claim minier sur lequel des travaux ont été effectués. 1. Stripping & Trenching 1. Creusement de tranchées et enlèvement du mort- terrain (i) Excavation through earth, gravel or loose (i) Dans la terre, le gravier ou toute matière non material (overburden). consolidée (parties à déblayer) By mechanical means $1.00 per cubic yard À l’aide de moyens mécaniques 1 $ la verge cube By hand $20.00 per cubic yard À la main 20 $ la verge cube (ii) Excavation through bedrock. (ii) Dans le roc By mechanical means $3.00 per cubic yard À l’aide de moyens mécaniques 3 $ la verge cube By hand $30.00 per cubic yard À la main 30 $ la verge cube 2. Shafts & Adits 2. Creusement de puits et de galeries (i) By hand first 6 feet from the surface (i) À la main, jusqu’à six pieds à partir de la $100.00 total surface 100 $ le tout (ii) Each additional foot - overburden (ii) Pour chaque pied supplémentaire – matière $50.00 per foot non consolidée 50 $ le pied (ii) Each additional foot – bedrock (iii) Pour chaque pied supplémentaire – dans le roc $100.00 per foot 100 $ le pied Shafts must have an opening of at least 3’ x 3’. Les puits doivent avoir une ouverture minimale de 3 pieds sur 3 pieds. 3. Diamond Drilling & Rotary Drilling 3. Forage au diamant et forage rotatif (i) Diamond drilling, rotary drilling, reverse (i) Le forage au diamant, le forage rotatif, la circulation and auger drilling will be accepted circulation inverse et le forage avec tarière as assessment work on the basis of actual costs sont reconnus comme travaux obligatoires for the purpose of renewing quartz mining selon le coût réel aux fins de renouveler les claims provided that the application is claims miniers de quartz, à condition que la accompanied by a complete set of drill logs demande soit accompagnée des carnets detailing each hole; and an accurate map complets de forage contenant la description showing the location of the drill holes relative de chaque trou de forage ainsi qu’une carte to the local topography and boundaries of the précise indiquant l’emplacement des trous claim. The report must indicate the location par rapport aux limites topographiques where drill core has been stored. (Plans or locales et aux limites du claim. Le rapport maps submitted must indicate the scale, show doit indiquer le lieu où les carottes de forage survey or traverse lines, reference points, sont entreposées (les plans ou les cartes Page 2 YUKON REGULATIONS RÈGLEMENTS DU YUKON c September 30, 2022 Schedule of Representation Work (Quartz Mining), 2003 Annexe des travaux obligatoires (extraction du quartz) 2003 Section 3. Article 3. contours, and a legend providing a full soumis doivent indiquer l’échelle, les levés description of all symbols employed.) ou les lignes de passage, les tracés des ponts de référence et une légende présentant une description complète de tous les symboles utilisés.) (ii) Assay reports will be given assessment work (ii) On accordera aux rapports d’essais un crédit credit and must accompany the renewal taxé; ces rapports doivent accompagner une application; if no assays were performed, a demande de renouvellement comportant la reason for their absence should be provided. raison pour laquelle il n’y a pas eu d’essais, s’il y a lieu. (iii) Diamond drill core may be delivered to the core (iii) Les carottes de forage au diamant peuvent être library provided that it is properly identified, livrées à un entrepôt réservé à cette fin. Les filed in core boxes, accompanied by the drill carottes doivent être identifiées adéquatement, logs, map, and assay reports, and the approval placées dans des boîtes destinées à cette fin, for the delivery has been obtained from the accompagnées des carnets de forage, des Chief Geologist. The Chief Geologist will cartes et des rapports d’essais ainsi que de determine the amount of assessment work l’autorisation de livraison de la part du credit to be given to compensate for the cost of géologue en chef. Ce dernier détermine le transporting the core to the library. The normal crédit taxé qui doit être accordé pour rate for this service is $1.00 per foot of core, compenser les coûts de transport des carottes except in cases where the actual cost is more. jusqu’à l’entrepôt. Le taux normal pour un tel service est de 1 $ le pied, à moins que le coût réel ne soit plus élevé. General Information Renseignements généraux Where the actual cost of work is greater than rates Si le coût réel des travaux est plus élevé que les taux prescribed by this schedule, the Mining Recorder may, prescrits dans la présente annexe, le registraire minier at his/her discretion, approve any portion (or all) of the peut approuver les coûts à sa discrétion, en tout ou en costs, provided that the costs shown on the renewal partie, à condition que les coûts inscrits dans la application are supported by a certified statement of demande de renouvellement soient appuyés par des proper account, and, if requested, by copies of receipts, états certifiés établis selon les méthodes habituelles de vouchers, etc. comptabilité ou, si cela est requis, par la copie des reçus, des pièces justificatives, etc. All work performed on quartz claims must conform Les travaux exécutés sur les claims de quartz doivent with Workplace Health and Safety Regulation in être conformes au Règlement sur la sécurité sur les connection with Mine Safety and Section 10 of the lieux de travail, pour ce qui concerne les normes de Quartz Mining Act. sécurité dans les mines, et à l’article 10 de la Loi sur l’extraction du quartz. [General Information amended by O.I.C. 2022/119] [Renseignements généraux modifié par Décret 2022/119] If using explosives to move material, it is necessary to Dans le cas d’utilisation d’explosifs pour déplacer des obtain a Blasting Permit from the Workers’ Safety and matériaux, la Commission de la sécurité et de Compensation Board. Please note that assessment l’indemnisation des travailleurs, gouvernement du credit will not be given for blasting activities. Yukon doit remettre un permis de travail aux explosifs. Remarque : les travaux aux explosifs ne donnent pas lieu à un crédit taxé. [General Information amended by O.I.C. 2022/119] [Renseignements généraux modifié par Décret 2022/119] For verification purposes, it is in the best interest of the Aux fins de contrôle, le demandeur aura avantage à c YUKON REGULATIONS RÈGLEMENTS DU YUKON Page 3 September 30, 2022 Schedule of Representation Work (Quartz Mining), 2003 Annexe des travaux obligatoires (extraction du quartz) 2003 Section 4. Article 4. applicant to file work within a reasonable length of déposer un constat de ses travaux dans un délai time after it is performed. raisonnable après la fin des travaux. Misrepresentation in any of the statements sworn by an Un demandeur qui fait état de faits trompeurs lors applicant when filing work for the purpose of renewing d’une déclaration sous serment, dans le cadre du dépôt quartz claims may result in the refusal of an d’un constat des travaux aux fins de renouvellement application for renewal, the debarment of the applicant des claims de quartz, peut se voir interdire l’obtention from the right to obtain and renew claims, and/or ou le renouvellement des claims, ou faire l’objet de criminal charges against the applicant. poursuites criminelles. For further advice or clarification on this part, or any Pour obtenir d’autres conseils ou des éclaircissements part of this schedule, please consult the staff at the sur la présente partie, ou toute autre partie, de la office of the District Mining Recorder. présente annexe, veuillez vous adresser au personnel du bureau de district du registraire minier. B - Geological, Geophysical, and Geochemical Surveys B - Levés et études géologiques, géochimiques et & Studies géophysiques General Information Renseignements généraux This section includes guidelines and conditions Le présent article comprend les directives et les governing acceptance of geological, geophysical, and conditions régissant la réception des levés et des geochemical surveys and studies on quartz claims. études géologiques, géochimiques et géophysiques des claims de quartz. Reports will be confidential for a period of 5 years from Les rapports restent confidentiels pendant cinq ans à the date that they are received at the office of the partir de la date de leur dépôt au bureau du registraire Mining Recorder, or 6 months after the lapsing date of minier ou pendant une période de six mois suivant la the claims on which the report is concerned, whichever date d’expiration des claims faisant l’objet des date is first. rapports, si cette date est plus récente. Conditions Governing Acceptance Conditions régissant la réception Geotechnical work used for assessment work purposes Les travaux géotechniques reliés aux travaux on quartz claims must meet the following conditions: obligatoires sur les claims de quartz doivent remplir les conditions suivantes : 4. The work must be performed under the supervision 4. être effectués sous la surveillance d’un professionnel of a qualified professional or a person who has received qualifié ou d’une personne ayant reçu l’autorisation prior approval from the Mining Recorder; préalable du registraire minier; 5. A full hardcopy report of the survey must be 5. faire l’objet d’un rapport complet des levés, sur submitted in duplicate to the District Mining Recorder, papier, à soumettre au registraire minier de district en or one hardcopy report may be substituted with an double exemplaire; un de ces exemplaires peut être electronic version of the report in Portable Document soumis sous forme électronique, en format PDF Format (.pdf) version 4 or higher. Plans or maps in the (Portable Document Format), version 4 ou plus récente; electronic version must be printable at full scale. les plans ou les cartes en version électronique doivent pouvoir s’imprimer en entier sur une page; Some or all of the costs incurred in conducting Les coûts engagés, en tout ou en partie, lors de levés geological, geophysical, and geochemical surveys will géologiques, géochimiques et géophysiques, peuvent be considered if the costs are: faire l’objet d’un remboursement, aux conditions suivantes : 6. Incurred within the Yukon Territory in performing 6. avoir été engagés dans le territoire du Yukon lors de the survey; l’exécution de l’étude; 7. Incurred when performing assays, tests and 7. avoir été engagés lors de l’exécution des essais, des Page 4 YUKON REGULATIONS RÈGLEMENTS DU YUKON c September 30, 2022 Schedule of Representation Work (Quartz Mining), 2003 Annexe des travaux obligatoires (extraction du quartz) 2003 Section 7. Article 7. analyses, compiling maps and plans and preparing the tests et des analyses, lors du tracé des cartes et des report plans et lors de la rédaction du rapport; 8. Supported by a certified statement of proper 8. être appuyés par des états certifiés présentant les account and, if requested, by copies of receipts, données comptables appropriées et, si cela est requis, invoices, vouchers, etc. de la copie des reçus, des pièces justificatives, des factures, etc. Report Requirements: Exigences reliées au rapport : 9. Reports must be securely bound in a binder with 9. Le rapport doit être inséré dans un classeur en maps or plans secured in the binder or placed in a prenant soin de bien placer les cartes et les plans qui pocket which is attached to the binder, lui sont annexés dans le classeur, ou de les mettre dans une pochette attachée au classeur; 10. At least one plan or map showing the location of 10. Le rapport doit comprendre, au minimum, une the claims on which the study was performed must be carte ou un plan indiquant l’emplacement des claims included in the report; the plan must show the qui ont fait l’objet d’une étude; le plan doit indiquer les relationship of the study’s claims to major relations entre les claims et les accidents topographical features and adjacent claims, and the topographiques ainsi que les claims adjacents; il doit names and grant numbers of the claims; aussi porter le nom et le numéro de la concession faisant l’objet de l’étude; 11. Plans or maps which accompany reports must 11. Les cartes et les plans accompagnant les rapports indicate the scale, show survey or traverse lines, and doivent indiquer l’échelle, les levés ou les lignes de the direction of survey or traverse, have a north arrow, passage ainsi que la direction de ces dernières, la reference points, contours, and a legend providing a flèche du Nord, les points de référence, les courbes de full description of all symbols employed; niveau ainsi qu’une légende présentant une description complète de tous les symboles utilisés; 12. The method of control and the amount of line- 12. La méthode de contrôle et le nombre de coupes de cutting must be indicated in the report (if applicable); lignes doivent figurer dans le rapport, s’il y a lieu; et all cut and surveyed lines and tie-ins must appear on at toutes les lignes coupées et arpentées ainsi que les least one plan. lignes secondaires doivent être indiquées sur au moins un des plans. 13. Where data is collected in computer-readable form 13. Lorsque des données sont recueillies dans un and transferred to computer-readable files, copies of format lisible par ordinateur et transférées dans des these files must be: fichiers lisibles également par ordinateur, les copies de ces fichiers : (i) Accompanied by a documentation file which is (i) doivent être accompagnées d’un fichier de to include a list of all data files, their type documentation qui comprend la liste de tous les (whether geochemical, geological, or fichiers de données, leur type (géochimique, geophysical), their format (text, tables of data, géologique ou géophysique ), leur format vector files, raster files, profile data), lists of (texte, tableaux de données, fichiers vectoriels, variables for each file with variable labels and fichiers de données ligne par ligne, données de units and value labels and units of value labels profil), des listes de variables comportant des as appropriate; codes de valeurs et des unités variables, et les unités des codes de valeur, au besoin; (ii) In a format that is compatible to the (ii) doivent avoir un format compatible avec le department’s current computer system; système informatique en vigueur au ministère; c YUKON REGULATIONS RÈGLEMENTS DU YUKON Page 5 September 30, 2022 Schedule of Representation Work (Quartz Mining), 2003 Annexe des travaux obligatoires (extraction du quartz) 2003 Section 14. Article 14. (iii) All spatially related data are to be (iii) doivent comprendre les données spatiales et geographically referenced by either latitude and comporter des références géographiques, soit longitude or UTM coordinates or by grid par leur latitude et leur longitude, soit par leurs coordinates accompanied by a base map (see coordonnées MTU ou par des coordonnées de item 11) to a degree of precision appropriate to quadrillage, ainsi qu’une carte de base (voir the scale of the survey. article 11) possédant un degré de précision approprié à l’échelle des levés. 14. The front cover must indicate: 14. La page de couverture doit indiquer : (i) The nature of the report (i.e. geological, (i) la nature du rapport, par exemple, levés geophysical, etc.); géologiques, géophysiques, etc.; (ii) The name and grant numbers of the claims or (ii) le nom et le numéro de concession des claims groups of claims to which the report refers, the ou des groupes de claims dont traite le rapport, claims sheet number(s) and the location of the le numéro de feuille de chaque claim et property described by precise latitude and l’emplacement de la propriété décrit à l’aide de longitude or UTM coordinates, sa latitude et de sa longitude exactes ou des coordonnées MTU; (iii) The registered owner of the claims and the (iii) le nom du propriétaire enregistré des claims et name of the Mining District in which they are le nom du district minier où ils se situent; located; (iv) The name and the author and, if not the same (iv) le nom de l’auteur et, s’il s’agit d’une personne person, the name of the person under whose différente, le nom de la personne sous la supervision the work was performed; direction de laquelle les travaux ont été exécutés; (v) The dates between which the work was (v) les dates de début et de fin des travaux. performed. 15. The report must include: 15. Le rapport comprend : (i) A table of contents, (i) une table des matières; (ii) A list of the claims by name and grant number (ii) une liste des claims, par ordre de nom et de being renewed, the name of the holder of the numéro de concession renouvelée, le nom du claims and the name of the person or company détenteur des claims et le nom de la personne for whom the work was done; ou de la société pour le compte de laquelle les travaux ont été exécutés; (iii) A detailed description of the data collected (iii) une description détaillée des données recueillies during the study, the manner in which it was durant l’étude et de la façon dont elles ont été collected, and an interpretation of the data recueillies, une interprétation des données regarding the geological implications, together concernant ses conséquences géologiques, ainsi with conclusions and recommendations (all que des conclusions et des recommandations information obtained from other sources must (toute information obtenue d’autres sources he fully disclosed); doit être divulguée); (iv) A complete description of methods employed (iv) une description complète des méthodes and equipment used; employées et de l’équipement utilisé; (v) A description of methods of assaying or (v) la description des méthodes d’analyse et des analysing and assay certificates as an appendix essais, ainsi que la copie des certificats d’essais at the end of the report when assays are annexés à la fin du rapport, si l’on a procédé à performed; des essais; Page 6 YUKON REGULATIONS RÈGLEMENTS DU YUKON c September 30, 2022 Schedule of Representation Work (Quartz Mining), 2003 Annexe des travaux obligatoires (extraction du quartz) 2003 Section 16. Article 16. (vii) Plans showing the location of mineralization, (vi) les plans indiquant l’emplacement des trenches, drill holes, other workings, and where minerais, des tranchées, des forages, des sample were taken for geological or evaluation autres travaux, ainsi que les emplacements où surveys; les échantillons ont été prélevés à des fins de levés géologiques ou d’évaluation; (viii) A signed statement of qualifications of the (vii) un énoncé des qualités, y compris toute supervisor and, if not the same person, the formation pertinente, l’expérience de travail et author of the report, including any relevant les affiliations professionnelles, signé par le training, experience and any professional superviseur, ou par l’auteur du rapport s’il affiliations. s’agit d’une personne différente. 16. Geological survey reports must include: Detailed 16. Les rapports des levés géologiques doivent geological information concerning rock types, comprendre, dans la mesure du possible, des données structures, veins and mineralized zones occurring on géologiques détaillées sur les types de roche, la the claims; and results which outline grades, structure des roches, les veines rocheuses et les zones characteristics and reserves for properties tested, minéralisées se trouvant dans les claims; les résultats whenever possible. Any prospecting conducted as part démontrant la teneur, les caractéristiques et les of a geological survey must include details of the work réserves des propriétés qui ont fait l’objet des essais. activity indicating the dates worked and a description La prospection effectuée dans le cadre de levés of the work accomplished. géologiques doit indiquer le détail des activités reliées aux travaux ainsi que la date et la description de ces travaux. 17. Geophysical survey reports must include: 17. Les rapports des levés géophysiques doivent Reference to available geology, copies of geophysical comprendre la liste des ouvrages de géologie readings or profiles, and pertinent calculations. disponibles, la copie des cotes ou des profils géophysiques ainsi que les calculs appropriés. 18. Geochemical survey reports must include: A 18. Les rapports des levés géochimiques doivent summary of all previous relevant investigations, and comprendre un résumé de toutes les études details of surface evaluation and, if applicable, antérieures pertinentes, les détails de l’évaluation en underground work. surface et, s’il y a lieu, des travaux souterrains. 19. Line Cutting and Picketing: Must be for the purpose 19. Les coupes de lignes et le piquetage doivent avoir of geological, geophysical, or geochemical surveys; line pour objet des levés géologiques, géophysiques et cutting costs are acceptable under a separate géochimiques. Les coûts reliés aux coupes de lignes application, as preparatory work, when the actual sont admissibles en vertu d’une demande distincte, à survey takes place in a different anniversary year from titre de travaux préliminaires, lorsque les levés réels the date of the claims being renewed. sont exécutés au cours d’une année subséquente à celle du renouvellement des claims. 20. GPS Location Surveys: Must be for the purpose of 20. Les levés de positionnement SPG (système de geological, geophysical, or geochemical surveys; must positionnement global) doivent avoir pour objet les be accompanied by a claim sheet or map in a scale or levés géologiques, géophysiques et géochimiques; ils format acceptable to the department and include all doivent être accompagnés d’une feuille de claim ou GPS technical data; prior approval may be obtained d’une carte à l’échelle ou dans un format acceptable from the Mining Recorder to submit a proposal to use par le ministère, et comprendre les données techniques these costs under a separate application, as SPG Une autorisation préalable peut être obtenue du preparatory work, when the actual survey takes place registraire minier afin de soumettre une proposition in a different anniversary year from the date of the pour reporter ces coûts dans une demande distincte, à claims being renewed. titre de travaux préliminaires, lorsque les levés réels sont exécutés au cours d’une année subséquente à celle du renouvellement des claims. c YUKON REGULATIONS RÈGLEMENTS DU YUKON Page 7 September 30, 2022 Schedule of Representation Work (Quartz Mining), 2003 Annexe des travaux obligatoires (extraction du quartz) 2003 Section 21. Article 21. Surveys, Road & Airstrip Construction, Road Arpentage, construction de chemins et de pistes Maintenance, Mobilization & Reclamation Work d’atterrissage, entretien des chemins, mobilisation et travaux de remise en état The Mining Recorder may require that costs associated Le registraire minier peut déclarer que les coûts reliés with conventional mineral exploration methods are aux méthodes classiques d’exploration et d’activités given priority over costs associated with legal and minières ont priorité sur les coûts reliés aux levés location line surveys, road and airstrip construction, officiels et aux levés des lignes d’emplacement, aux road maintenance, mobilization and reclamation work. levés de positionnement SPG (système de This work must be supported by a certified statement positionnement global), à la construction des chemins of proper account and if requested, by copies of et des pistes d’atterrissage, à l’entretien des chemins receipts, invoices, vouchers, etc. ainsi qu’aux travaux de mobilisation et de remise en état. Ces travaux doivent être appuyés par des états certifiés établis selon les méthodes habituelles de comptabilité et, si cela est requis, par la copie des reçus, des pièces justificatives, des factures, etc. 21. Legal and Location Line Surveys: 21. Levés officiels et levés des lignes d’emplacement : The Mining Recorder may, at his/her discretion, S’il le juge utile, le registraire minier peut approuver, approve any portion (or all) of the costs of a legal en tout ou en partie, le coût des levés officiels, à location survey provided that it has been gazetted in condition que ces coûts soient publiés conformément à the manner prescribed by the Quartz Mining Act and la Loi sur l’extraction du quartz et qu’ils soient approved by the Surveyor General for Canada; or any approuvés par l’arpenteur général du Canada. Le juge portion (or all) of the costs of a location line survey peut également approuver, en tout ou en partie, les defining the boundaries of a claim or a group of claims coûts de levé des lignes d’emplacement qui établissent if performed by a Canada Land Surveyor or a qualified les limites d’un claim ou d’un groupe de claims s’ils survey technician. The costs eligible for consideration sont exécutés par un arpenteur du Canada ou par un towards assessment work credit for legal or location technicien qualifié en arpentage. Les coûts admissibles line surveys will include line-cutting and picketing pour examen en vue d’un crédit taxé, suite aux levés costs. officiels et aux levés des lignes d’emplacement, comprennent les coûts concernant les coupes de lignes et le piquetage. 22. Roads & Airstrip Construction: 22. Construction des chemins et des pistes d’atterrissage: The Mining Recorder may, at his/her discretion, S’il le juge utile, le registraire minier peut approuver, approve any portion (or all) of the costs of road or en tout ou en partie, les coûts de la construction des airstrip construction, provided that the applicant has chemins ou des pistes d’atterrissage, à condition que le obtained the necessary land use permit and/or any demandeur obtienne les permis d’utilisation du sol other required authorization(s), and only if the Mining nécessaires, ou toute autre autorisation, et à condition Recorder is satisfied that the road or airstrip is que le registraire soit convaincu que le chemin ou la required to provide access to a claim or claims. piste d’atterrissage est nécessaire pour accéder au claim. 23. Road Maintenance: 23. Entretien des chemins : The Mining Recorder may, at his/her discretion, S’il le juge utile, le registraire minier peut approuver approve a portion of the cost of road maintenance une partie des coûts de l’entretien des chemins exécuté performed to keep access routes to mining claims pour permettre l’accès aux claims miniers, dans le but open, in support of current mineral exploration, d’appuyer l’exploration minière en cours, à condition provided that the applicant has obtained the necessary que le demandeur obtienne les permis d’utilisation du land use permit and/or any other required sol nécessaires ou toute autre autorisation. Les crédits Page 8 YUKON REGULATIONS RÈGLEMENTS DU YUKON c September 30, 2022 Schedule of Representation Work (Quartz Mining), 2003 Annexe des travaux obligatoires (extraction du quartz) 2003 Section 24. Article 24. authorization(s). Credit for road maintenance cannot accordés pour l’entretien des chemins ne peuvent exceed 50% of the total value of the work program in dépasser 50 % de la valeur totale du programme des any given year. travaux au cours d’une année donnée. 24. Mobilization: 24. Mobilisation : The Mining Recorder may, at his/her discretion, S’il le juge utile, le registraire minier peut approuver approve all or a portion of mobilization costs in support les coûts de mobilisation, en tout ou en partie, pour of current mineral exploration provided that the appuyer l’exploration minière en cours, à condition que applicant has obtained the necessary land use permit le demandeur obtienne les permis d’utilisation du sol and/or any other required authorization(s). Mobilization nécessaires ou toute autre autorisation. La mobilisation must occur within the Yukon Territory. doit avoir lieu dans le territoire du Yukon. 25. Reclamation Work: 25. Travaux de remise en état : The Mining Recorder may, at his/her discretion approve S’il le juge utile, le registraire minier peut approuver, the actual costs, or a portion of the actual costs for the en tout ou en partie, les coûts réels du remblayage des backfilling of trenches, contouring, reseeding, tranchées, d’un système de contournement, le demobilization and removal of equipment, cleanup and réensemencement, la démobilisation et l’enlèvement de removal of campsite, etc. for assessment work. l’équipement et du campement, le nettoyage, etc., dans le cadre des travaux obligatoires. C – Work Requiring Prior Approval from Mining C – Travaux nécessitant l’autorisation préalable du Recorder registraire minier General Information Renseignements généraux This section includes guidelines and conditions La présente division comprend les directives et les governing acceptance of surveys performed in support conditions régissant la réception des levés exécutés of mineral exploration that require prior approval from dans le but d’appuyer l’exploitation minière qui the Mining Recorder. The Mining Recorder’s approval requièrent l’autorisation préalable du registraire may require that costs associated with conventional minier. L’autorisation de ce dernier peut comporter mineral exploration methods are given priority over l’exigence que les coûts reliés aux méthodes classiques costs associated with evaluation, environmental, d’exploitation minière soient prioritaires par rapport heritage and archaeological surveys. aux coûts reliés à l’évaluation environnementale ainsi qu’aux levés archéologiques et patrimoniaux. Prior Approval From the Mining Recorder Must Be L’autorisation préalable du registraire minier doit être Obtained in order to use costs of any of these activities obtenue pour pouvoir utiliser à titre de crédit taxé les as assessment work credit on quartz claims. coûts reliés à ces activités sur les claims de quartz. A detailed proposal outlining the work program must Aux fins de la présente division, une proposition be submitted to the Mining Recorder in order to obtain détaillée avec description du programme des travaux prior approval for the purposes of this section. est soumise au registraire minier pour obtenir une autorisation préalable. Evaluation Surveys, Environmental, Heritage, Levés d’évaluation, études environnementale, Archaeological Studies archéologiques et patrimoniales 26. Evaluation Surveys: 26. Levés d’évaluation : The Mining Recorder may, at his/her discretion, S’il le juge utile, le registraire minier peut approuver, approve any portion (or all) of the report writing costs en tout ou en partie, les coûts de rédaction du rapport of Evaluation Surveys. The report must adhere to the sur les levés d’évaluation. Le rapport doit respecter les general conditions governing acceptance as outlined conditions générales régissant la réception, tel below. They must also include previous relevant qu’indiqué ci-dessous, et inclure toute enquête investigation supported by original data (assay pertinente déjà exécutée, justifiée par des données c YUKON REGULATIONS RÈGLEMENTS DU YUKON Page 9 September 30, 2022 Schedule of Representation Work (Quartz Mining), 2003 Annexe des travaux obligatoires (extraction du quartz) 2003 Section 27. Article 27. certificates, unpublished reports, etc.). originales (certificat d’essais, rapports non publiés, etc.). 27. Environmental, Heritage, Archaeological Studies: 27. Études environnementales, archéologiques et patrimoniales : The Mining Recorder may, at his/her discretion approve S’il le juge utile, le registraire minier peut approuver, any portion (or all) of the costs to perform an en tout ou en partie, les coûts nécessaires à l’exécution Environmental, Heritage or Archaeological study which d’une étude environnementale, archéologique ou may be required prior to entry for mining purposes. patrimoniale pouvant s’avérer nécessaires avant le This work must be required by a government agency or début des opérations minières. Ces travaux peuvent requested by the Mining Recorder. To apply such s’avérer nécessaires s’ils sont requis par une agence studies for credit for the renewal of quartz claims, the gouvernementale ou par le registraire minier. Pour que work must meet the following general conditions: ces études soient créditées aux fins du renouvellement des claims de quartz, les travaux doivent respecter les conditions générales suivantes : 28. General Conditions 28. Conditions générales (i) The work must be performed under the (i) Les travaux doivent être effectués sous la supervision of a qualified professional or a surveillance d’un professionnel qualifié ou d’une person who has received prior approval by the personne ayant reçu l’autorisation préalable du Mining Recorder; registraire minier;minier; The cost of the study will be considered for assessment Les coûts de l’étude peuvent être appliqués aux travaux work purposes if the costs are: obligatoires aux conditions suivantes : (ii) Incurred within the Yukon Territory in (ii) avoir été engagés dans le territoire du Yukon performing the study; lors de l’exécution de l’étude (iii) Incurred when performing analyses, compiling (iii) avoir été engagés lors de l’exécution des essais, maps and plans, and preparing the report; des tests et des analyses, lors du tracé des cartes et des plans, ou lors de la rédaction du rapport; (iv) Supported by a certified statement of proper (iv) être appuyés par des états certifiés présentant account, and if requested, by copies of receipts, les données comptables appropriées et, si cela invoices, vouchers, etc. est requis, de la copie des reçus, des pièces justificatives, des factures, etc. The report requirements: Exigences reliées au rapport : (v) Reports must be submitted in duplicate to the (v) Un rapport complet des levés, sur papier, doit District Mining Recorder, or one hardcopy être soumis au registraire minier de district, en report may be substituted with an electronic double exemplaire; un de ces exemplaires peut version of the report in Portable Document être soumis sous forme électronique, en format Format (.pdf) version 4 or higher. Plans or PDF (Portable Document Format), version 4 ou maps in the electronic version must be plus récente; les plans ou les cartes en version printable at full scale. électronique doivent pouvoir s’imprimer en entier sur une page. (vi) Reports must be securely bound in a binder (vi) Le rapport doit être inséré dans un classeur en with maps or plans secured in the binder or prenant soin de bien placer les cartes et les placed in a pocket which is attached to the plans qui lui sont annexés dans le classeur ou binder; de les mettre dans une pochette attachée au classeur. Page 10 YUKON REGULATIONS RÈGLEMENTS DU YUKON c September 30, 2022 Schedule of Representation Work (Quartz Mining), 2003 Annexe des travaux obligatoires (extraction du quartz) 2003 Section 28. Article 28. (vii) At least one plan or map showing the location (vii) Le rapport doit comprendre, au minimum, une of the claims on which the study was carte ou un plan indiquant l’emplacement des performed must be included in the report; the claims ayant fait l’objet de l’étude; le plan doit plan must show the relationship of the studied indiquer les relations entre les claims et les claims to major topographical features and accidents topographiques ainsi que les claims adjacent claims and the names and grant adjacents; il doit aussi porter le nom et le numbers of the claims; numéro de concession faisant l’objet de l’étude. (viii) Plans or maps which accompany reports must (viii) Les cartes et les plans accompagnant les indicate the scale, show surveyor traverse lines, rapports doivent indiquer l’échelle, les levés ou and the direction of survey or traverse, have a les lignes de passage ainsi que la direction de north arrow, reference points, contours and a ces dernières, la flèche du Nord, les points de legend providing a full description of all référence, les courbes de niveau et une légende symbols employed; présentant une description complète de tous les symboles utilisés. (ix) The method of control and the amount of line- (ix) La méthode de contrôle et le nombre de coupes cutting must be indicated in the report; all cut de lignes doivent être indiqués dans le rapport; and surveyed lines and tie-ins must appear on toutes les lignes coupées et arpentées ainsi que a least one plan. les lignes secondaires doivent être indiquées sur au moins un plan. (x) The front cover of the report must indicate: (x) La page de couverture du rapport doit indiquer : (i) The nature of the report (ie. evaluation, (i) la nature du rapport (par exemple, environmental, archaeological, heritage, environnement, évaluation, archéologie, etc.); patrimoine, etc.); (ii) The name and grant numbers of the claims (ii) le nom et le numéro de concession des or groups of claims to which the report claims ou des groupes de claims dont traite refers, the claim sheet number and the le rapport, le numéro de feuille de chaque location of the property described by precise claim et l’emplacement de la propriété décrit latitude and longitude or UTM coordinates; à l’aide de sa latitude et de sa longitude exactes ou des coordonnées MTU; (iii) The registered owner of the claims and the (iii) le nom du propriétaire enregistré des claims name of the Mining District in which they are et le nom du district minier où ils se situent. located; (iv) The name of the author and, if not the same, (iv) le nom de l’auteur et, s’il s’agit d’une the name of the person under whose personne différente, le nom de la personne supervision the work was performed; sous la direction de laquelle les travaux ont été exécutés; (v) The dates between which the work was (v) les dates de début et de fin des travaux. performed. (xi) The report must include: (xi) Le rapport comprend : (i) A table of contents; (i) une table des matières; c YUKON REGULATIONS RÈGLEMENTS DU YUKON Page 11 September 30, 2022 Schedule of Representation Work (Quartz Mining), 2003 Annexe des travaux obligatoires (extraction du quartz) 2003 Section 29. Article 29. (ii) A list of the claims by name and grant (ii) une liste des claims, par ordre de nom et de number being renewed, the name of the numéro de concession renouvelée, le nom du holder of the claims and the name of the détenteur des claims et le nom de la person or company for whom the work was personne ou de la société pour le compte de done; laquelle les travaux ont été exécutés; (iii) A detailed description of the data collected (iii) une description détaillée des données during the study, the manner in which it was recueillies durant l’étude et de la façon dont collected, and an interpretation of the data elles ont été recueillies, une interprétation regarding the evaluation, archaeological, des données concernant ses conséquences environmental, or heritage implications, sur l’archéologie, l’environnement et le together, with conclusions and patrimoine, ainsi que des conclusions et des recommendations (all information obtained recommandations (toute information from other sources shall be fully disclosed); obtenue d’autres sources doit être divulguée); (iv) A signed statement of qualifications of the (iv) un énoncé des qualités, y compris toute supervisor and, if not the same person, the formation pertinente, l’expérience de travail author of the report, including any relevant et les affiliations professionnelles, signé par training, experience and any professional le superviseur, ou par l’auteur du rapport s’il affiliations. s’agit d’une personne différente. C – Work Done in the Double-Value Year C – Travaux effectués au cours de l’année à valeur doublée 29.(1) In this section 29.(1) Les définitions qui suivent s’appliquent au présent article. “Gwich’in Comprehesive Land Claim Agreement” « Entente sur la revendication territoriale globale des means the agreement defined in the Gwich’in Land Gwich'in » L’entente définie dans la Loi sur le Claim Settlement Act (Canada); « Entente sur la règlement de la revendication territoriale des Gwich’in revendication territoriale globale des Gwich'in » (Canada). “Gwich’in Comprehesive Land Claim Agreement” “settlement land” has the same meaning as in An Act « terres visées par le règlement » S’entend au sens de Approving Yukon Land Claim Final Agreements; la Loi approuvant les ententes définitives avec les « terres visées par le règlement » premières nations du Yukon. “settlement land” “Tetlit Gwich’in Yukon land” has the same meaning as « terres gwich'in tetlit au Yukon » S’entend au sens in Appendix C of the Gwich’in Comprehensive Land de l’annexe C de l’Entente sur la revendication Claim Agreement. « terres gwich'in tetlit au Yukon » territoriale globale des Gwich'in. “Tetlit Gwich’in Yukon land” [Section 29 added by O.I.C. 2015/20] [Article 29 ajouté par Décret 2015/20] [Subsection 29(1) replaced by O.I.C. 2016/133] [Paragraphe 29(1) remplacé par Décret 2016/133] (2) For the purpose of determining the value of work (2) Pour déterminer la valeur des travaux effectués done on a claim during the 2016-2017 double-value sur un claim au cours de l’année à valeur year, being the 366-day period that begins on February doublée 2016-2017, à savoir la période de 366 jours 1, 2016 débutant le 1er février 2016 : (a) the following categories of claims are created a) les catégories de claims qui suivent sont pursuant to subsection 56(4) of the Act établies conformément au paragraphe 56(4) de la loi : Page 12 YUKON REGULATIONS RÈGLEMENTS DU YUKON c September 30, 2022 Schedule of Representation Work (Quartz Mining), 2003 Annexe des travaux obligatoires (extraction du quartz) 2003 Section 29. Article 29. (i) double-value claims, and (i) les claims à valeur doublée, (ii) single-value claims; (ii) les claims à valeur simple; (b) a claim is a double-value claim if it is in good b) un claim est un claim à valeur doublée s’il est standing and no part of the claim is located en règle et qu’aucune partie du claim n’est within localisée dans l’une ou l’autre des terres suivantes : (i) settlement land, or (i) les terres visées par le règlement, (ii) Teltlit Gwich’in Yukon land; (ii) les terres gwich'in tetlit au Yukon; (c) a claim that is not a double-value claim is a c) le claim qui n’est pas un claim à valeur doublée single-value claim; and est un claim à valeur simple; (d) pursuant to paragrarph 56(4)(b) of the Act, the d) conformément à l’alinéa 56(4)b) de la loi, le Mining Recorder will multiply the assessed registraire minier multiplie l’évaluation ou le value or approved cost of work, as the case coût approuvé des travaux, selon le cas, may be, done on a claim by effectués sur un claim : (i) in the case of a double-value claim, two, and (i) s’agissant d’un claim à valeur doublée, par deux, (ii) in the case of a single-value claim, one. (ii) s’agissant d’un claim à valeur simple, par un. [Subsection 29(2) added by O.I.C. 2016/133] [Paragraphe 29(2) ajouté par Décret 2016/133] c YUKON REGULATIONS RÈGLEMENTS DU YUKON Page 13 September 30, 2022
Provision text is displayed from LexChat’s stored statute record. Use the official source links to verify amendments, commencement, and current legal force.
Ask AI about this statute
Schedule of Representation Work (Quartz Mining), 2003
Sign in to ask AI about this statute
Sign in to start authenticated, citation-grounded statute research.
Sign inLexChat organizes source-backed legal information for research. Verify amendments, commencement, and current legal force with the official publisher before relying on it.