О внесении изменений в постановление Правительства Российской Федерации от 27 декабря 2004 г. № 861

This amendment changes the electricity connection rules, including deadlines for network organizations, document reissuance, technical-condition checks, and a ban on imposing extra services or obligations not set out in the rules.

Jurisdiction
Russia
Instrument
Regulation
Citation
130
Version
Undated source snapshot
Language
ru
Official source
View official record ↗
document reissuance electric grid connection electricity network connection inspection and testing payment schedule technical conditions verification

Statute overview

About this statute

This amendment changes the electricity connection rules, including deadlines for network organizations, document reissuance, technical-condition checks, and a ban on imposing extra services or obligations not set out in the rules. Сетевая организация и заявитель должны соблюдать сроки и порядок осмотра, проверки и оформления документов по технологическому присоединению; заявитель также вносит части платы в установленные сроки.

LexChat organizes source-backed legal information for research. Verify amendments, commencement, and current legal force with the official publisher before relying on it.