MINISTERIAL INSTRUCTIONS Nº 01/CAB.M/017 OF 28/04/2017 DETERMINING INSPECTION OF TYPES OF BUILDINGS IN RELATION TO THEIR ANTICIPATED RISKS
These instructions govern inspections of building types based on their anticipated risks.
AI-assisted research synopsis — verify against the official legal text below.
- Jurisdiction
- Rwanda
- Instrument
- Regulation
- Citation
- 01/CAB.M/017 OF 28/04/2017
- Status
- In force
- Version
- Undated source snapshot
- Language
- mul
- Updated
- Official source
- View official record ↗
Statute overview
About this statute
These instructions govern inspections of building types based on their anticipated risks. This article says the building classes based on occupancy are set out in Annex I. This article classifies buildings into five fire-resistance categories. A building is assessed using six risk factors. The provision says the risk matrix is set out in Annex II and classifies risks into three levels: low, medium, and high.
Search within this statute
Search all stored provisions in this version.
Legal text
Provisions of MINISTERIAL INSTRUCTIONS Nº 01/CAB.M/017 OF 28/04/2017 DETERMINING INSPECTION OF TYPES OF BUILDINGS IN RELATION TO THEIR ANTICIPATED RISKS
Showing 12 of 12
- 1 Verify source ↗
Icyo aya mabwiriza
AI-assisted research summary: These instructions govern inspections of building types based on their anticipated risks.
Ingingo ya mbere: Icyo aya mabwiriza agamije Article One: Purpose of these Instructions Article premier: Objet des présentes instructions Ingingo hakurikijwe ibizikorerwamo ya 2: Ibyiciro by’inyubako Ingingo hagendewe ku kwirinda inkongi z’umuriro Ibyiciro by’inyubako ya 3: Ingingo ya mbere: Icyo aya mabwiriza agamije Article One: Purpose of these Instructions Article premier: Objet des présentes instructions Aya mabwiriza agenga igenzurwa ry’ubwoko bw’inyubako hakurikijwe ingaruka zateza. These Instructions govern the inspection of types of buildings in relation to their anticipated risks. Les présentes instructions déterminent l’inspection des types de bâtiments en rapport avec leurs risques potentiels. 36 Ingingo hakurikijwe ibizikorerwamo ya 2: Ibyiciro by’inyubako by’inyubako Ibyiciro hakurikijwe ibizikorerwamo buri ku mugereka wa I w’aya mabwiriza. Ingingo hagendewe ku kwirinda inkongi z’umuriro Ibyiciro by’inyubako ya 3: Official Gazette n°19 of 08/05/2017 - 2 Verify source ↗
Classes of buildings according to
AI-assisted research summary: This article says the building classes based on occupancy are set out in Annex I.
Article 2: Classes of buildings according to occupancy Article 2: Catégories de bâtiments selon l’occupation Article 2: Classes of buildings depending on their occupancy Article 2: Catégories de bâtiments selon l’occupation Classes of buildings depending on their occupancy are attached to these Instructions as Annex I. Les catégories de bâtiments selon l’occupation sont à l’annexe I des présentes instructions. - 3 Verify source ↗
Classes of buildings depending on
AI-assisted research summary: This article classifies buildings into five fire-resistance categories.
Article 3: Classes of buildings depending on fire resistance Article 3: Catégories de bâtiments selon la résistance au feu Article 3: Classes of buildings depending on fire resistance Article 3: Catégories de bâtiments selon la résistance au feu Hakurikijwe uguhangana n’inkongi z’umuriro, inyubako ziri mu byiciro bitanu (5) bukurikira: Depending on fire resistance, five (5) classes of buildings are as follows: Selon la résistance au feu, les cinq (5) catégories de bâtiments sont les suivants: 1° Icyiciro cya I: Izafatwa n’inkongi 1° Class I: Fire resistive least combustible; 1° Catégorie I: Résistant au feu le moins combustible; z’umuriro ku buryo bugoye; 2° Icyiciro cya II: Izitafatwa n’inkongi y’umuriro; 3° Icyiciro cya III: Izisanzwe; 2° Class II: Non-combustible; 2° Catégorie II: Non combustible; 3° Class III: Ordinary; 3° Catégorie III: Ordinaire; 4° Icyiciro cya biremereye; IV: Izigizwe n’ibiti 4° Class IV: Heavy timber; 4° Catégorie IV: Bois massif; 5° Icyiciro cya V: Izubakishijwe ibiti zafatwa n’inkongi z’umuriro ku buryo bworoshye. 5° Class V: Wood frame most combustible. combustible. 5° Catégorie V: Charpente en bois le plus Mu buryo burambuye ibyiciro byavuzwe mu gika cya mbere cy’iyi ngingo buri ku mugereka wa III w’aya mabwiriza. The details of the classes mentioned in Paragraph one of this Article are on Annex III of these Instructions. Les détails des catégories mentionnées a l’alinéa premier du présent article figurent à l'annexe III des présentes instructions. 37 - 4 Verify source ↗
Ibipimo by’ingaruka
AI-assisted research summary: A building is assessed using six risk factors.
Ingingo ya 4: Ibipimo by’ingaruka Article 4: Risk factors Article 4: Facteurs de risque Ingingo ya 4: Ibipimo by’ingaruka Article 4: Risk factors Article 4: Facteurs de risque Official Gazette n°19 of 08/05/2017 Inyubako bitandatu cy’ingaruka gifite hagereranywa cy’ingaruka kigashobora kumenyekana. ibipimo isuzumwa hakurikijwe (6) by’ingaruka. Buri gipimo rusange ibigenderwaho igipimo bityo inyubako A building is assessed in accordance with six (6) risk factors. Each risk factor contains broad criteria against which to compare buildings so that risk level can be established. Un bâtiment est évalué selon six (6) facteurs de risques. Chaque facteur de risques contient des critères généraux en vue comparer les bâtiments de manière à permettre d’établir le niveau de risques. Ibipimo bitandatu (6) by’ingaruka ni ibi: The six (6) risk factors are: Les six (6) facteurs de risque sont: 1° icyiciro cy’inyubako; 1° category of the building; 1° la catégorie de bâtiment; 2° ubwoko bw’imikoreshereze; 2° class of occupancy; 2° la classe d’occupation; 3° gushyira mu hakurikijwe n’ibishushanyombonera; byiciro inyubako ibiteganywa 3° zoning according to the master plan provisions; 3° zonage selon d’urbanisme; les provisions du plan 4° ubwoko bw’inyubako hakurikijwe 4° class of buildings depending on fire 4° la classe de bâtiments en fonction de la uguhangana n’inkongi y’umuriro; resistance; résistance au feu; 5° imiterere y’ikirere; 5° climatic conditions; 5° les conditions climatiques; 6° uburambe n’ubumenyi bw’uwahanze 6° experience and knowhow of the architect 6° l’expérience et savoir-faire de l’architecte n’uwayubatse. and engineer. et ingénieur. - 5 Verify source ↗
Urwunge rw’ingaruka
AI-assisted research summary: The provision says the risk matrix is set out in Annex II and classifies risks into three levels: low, medium, and high.
Ingingo ya 5: Urwunge rw’ingaruka Article 5: Risk matrix Article 5: Matrice des risques Ingingo ya 5: Urwunge rw’ingaruka Article 5: Risk matrix Article 5: Matrice des risques rugaragaza rw’ingaruka Urwunge igipimo n’ingano by’ingaruka ruri ku mugereka wa II w’aya mabwiriza kandi rugendeye ku gipimo cy’ingaruka zivugwa mu ngingo ya 4 y’aya mabwiriza. The risk matrix indicating risk factor and risk level is on Annex II of these Instructions and is based on the risk factors provided for under Article 4 of these Instructions. La matrice des risques indiquant le facteur de risque et le niveau de risque est à l’annexe II des présentes instructions et est basée sur le facteur de risques prévus à l'article 4 des présentes instructions. 38 Official Gazette n°19 of 08/05/2017 Urwunge rw’ingaruka zivugwa muri aya mabwiriza rugaragazwa mu byiciro bitatu (3) by’ingaruka zikurikira: The risk matrix referred to in these Instructions is identified in the following three (3) risk categories: La matrice de risques mentionnée dans les présentes instructions est identifiée en trois (3) catégories de risques suivants: 1° izoroheje; 2° iziciritse ; 3° n’izikomeye. 1° low; 2° medium and; 3° high. 1° faible, 2° moyen et; 3° élevé. - 6 Verify source ↗
Igenwa ry’igipimo cy’ingaruka
AI-assisted research summary: A risk level is determined when all the criteria for that level are met.
Ingingo ya 6: Igenwa ry’igipimo cy’ingaruka Article 6: Determination of risk level Article 6: Détermination du niveau de risque Ingingo ya 6: Igenwa ry’igipimo cy’ingaruka Article 6: Determination of risk level Article 6: Détermination du niveau de risque Igipimo cy’ingaruka kigenwa iyo ibisabwa ku rwego runaka byujujwe. A risk level is determined if all the criteria under a particular level are met. Un niveau de risque est déterminé si tous les critères d'un niveau donné sont remplis. Inyubako ifatwa ko ifite igipimo cy’ingaruka kiri hasi igihe iba yujuje ibisabwa kandi itarengeje urugero rw’ingaruka isabwa kuri urwo rwego A building is considered to have a low level of risk if it meets the required criteria and does not exceed the level of the risk required at that level. Un bâtiment est considéré comme présentant un niveau de risque faible s'il satisfait et ne dépasse aucun critère du facteur de risque pour ce niveau. Igihe urugero rwo hasi rw’ingaruka rurenze kimwe bipimo by’ingaruka ziri hasi, icyo gihe urwego rw’ingaruka rushyirwa ku rwego rukurikiyeho. byinshi mu cyangwa If the low-risk level exceeds one or more low level risk factors, the building’s risk level is placed at the next relevant level. Si le niveau de risque faible est supérieur à un ou plusieurs facteurs de risque faible, le niveau de risque du bâtiment est porté au niveau approprié suivant. - 7 Verify source ↗
Inspection of classes of buildings not
AI-assisted research summary: Buildings not covered by the risk-based matrix must undergo random inspection for compliance with the master plan.
Ingingo ya 7: by’inyubako rw’ingaruka Igenzurwa bitarebwa ry’ibyiciro n’urwunge Article 7: Inspection of classes of buildings not covered by risk based matrix Article 7: Inspection de catégories de bâtiments non couverts par une matrice à risque Ingingo ya 7: bw’inyubako rw’ingaruka Igenzurwa butarebwa ry’ubwoko n’urwunge Article 7: Inspection of classes of buildings not covered by risk based matrix Article 7: Inspection de catégories de bâtiments non couverts par une matrice à risque Ibyiciro by’inyubako bitarebwa n’urwunge rw’ingaruka ubugenzuzi bikorerwa bw’imyubakire mu buryo busanzwe kugira ngo harebwe ibiteganywa n’ibishushanyombonera byubahirizwa. ko The classes of buildings that are not covered by the risk based matrix are subjected to random inspection to ensure that the provisions of master plan are complied with. Les catégories de bâtiments qui ne sont pas couvertes par la matrice à risque sont soumis à une inspection aléatoire pour s'assurer qu'ils sont conformes aux dispositions du plan directeur. 39 Official Gazette n°19 of 08/05/2017 - 8 Verify source ↗
Igenzura ry’inyubako zo
AI-assisted research summary: All residential buildings for aged persons must be inspected using a high-risk matrix.
Ingingo ya 8: Igenzura ry’inyubako zo guturamo ku bantu basheshe akanguhe Article 8: Inspection of residential buildings for aged persons Article 8: Inspection de bâtiments résidentiels pour les personnes âgées Ingingo ya 8: Igenzura ry’inyubako zo guturamo ku bantu basheshe akanguhe Article 8: Inspection of residential buildings for aged persons Article 8: Inspection de bâtiments résidentiels pour les personnes âgées Igenzura ry’inyubako zose zo guturamo ku bantu basheshe akanguhe rigomba gukorwa hashingiwe ku rwunge rw’ingaruka ziri hejuru. Inspection of all residential buildings for aged persons must be conducted basing on the high risk matrix. L’inspection de tous les bâtiments résidentiels pour les personnes âgées doit être conduite en fonction de la matrice à risque élevé. - 9 Verify source ↗
Random and compulsory inspection
AI-assisted research summary: Inspections are conducted randomly and compulsorily, based on the building categories listed in Annex IV.
Ingingo ya 9: n’iritegetswe Igenzura ritunguranye Article 9: Random and compulsory inspection Article 9: Inspection aléatoire et obligatoire Ingingo ya 9: n’iritegetswe Igenzura ritunguranye Article 9: Random and compulsory inspection Article 9: Inspection aléatoire et obligatoire Igenzura ritunguranye n’iritegetswe akorwa hashingiwe ku byiciro by’inyubako nk’uko bigaragara ku mugereka wa IV w’aya mabwiriza. - 10 Verify source ↗
Ifishi zikoreshwa mu igenzura
AI-assisted research summary: Building inspections use six forms, chosen based on the building’s category.
Ingingo ya 10: Ifishi zikoreshwa mu igenzura ry’inyubako Article 10: Forms used in inspection of buildings Article 10: Formulaires utilisés dans l'inspection de bâtiments 34 Official Gazette n°19 of 08/05/2017 Ingingo ya 10: Ifishi zikoreshwa mu igenzura ry’inyubako Mu igenzura ry’inyubako, hakoreshwa ubwoko butandatu (6) bw’ifishi hagendewe ku cyiciro inyubako iherereyemo nk’uko biri ku mugereka wa V w’aya mabwiriza. Random and compulsory inspection are conducted basing on categories of the buildings as indicated on Annex IV of these Instructions. Article 10: Forms used in inspection of buildings During the inspection of buildings, six (6) types of forms are used depending on the category of the building as these Instructions. in Annex V of indicated L’inspection aléatoire et celle obligatoire sont conduites en fonction des catégories de bâtiments comme indiquées à l'annexe IV des présentes instructions. Article 10: Formulaires utilisés dans l’inspection de bâtiments Lors de l’inspection, six (6) types de formulaires sont utilisés en fonction de la catégorie du bâtiment comme indiqués à l'annexe V des présentes instructions. - 11 Verify source ↗
Repealing provision
AI-assisted research summary: Prior instructions that conflict with these instructions are repealed.
Ingingo ya 11: Ivanwaho zinyuranyije n’aya mabwiriza ry’ingingo Article 11: Repealing provision Article 11: Disposition abrogatoire Ingingo ya 11: Ivanwaho zinyuranyije n’aya mabwiriza ry’ingingo Article 11: Repealing provision Article 11: Disposition abrogatoire Ingingo zose z’amabwiriza abanziriza aya kandi zinyuranye na yo zivanyweho. All prior Instructions contrary to these Instructions are repealed. Toutes les dispositions antérieures contraires aux présentes instructions sont abrogées. - 12 Verify source ↗
Igihe aya mabwiriza atangira
AI-assisted research summary: These Instructions start to apply when they are published in the Official Gazette of Rwanda.
Ingingo ya 12: Igihe aya mabwiriza atangira gukurikizwa Article 12: Commencement Article 12: Entrée en vigueur 35 Official Gazette n°19 of 08/05/2017 YA AMABWIRIZA MINISITIRI NO01/CAB.M/017 YO KU WA 28/04/2017 AGENGA IGENZURWA RY’UBWOKO BW’INYUBAKO HAKURIKIJWE INGARUKA ZATEZA INSTRUCTIONS MINISTERIAL NO01/CAB.M/017 28/04/2017 DETERMINING INSPECTION OF TYPES OF BUILDINGS IN RELATION TO THEIR ANTICIPATED RISKS OF MINISTERIELLES INSTRUCTIONS NO01/CAB.M/017 28/04/2017 DETERMINANT L’INSPECTION DES TYPES DE BATIMENTS EN RAPPORT AVEC LEURS RISQUES POTENTIELS DU Minisitiri w’Ibikorwaremezo; The Minister of Infrastructure; Le Ministre des Infrastructures; Ashingiye ku Itegeko n°10/2012 ryo ku wa 02/05/2012 rigena imitunganyirize y’imijyi n’imyubakire mu Rwanda; Pursuant to Law n°10/2012 of 02/05/2012 governing urban planning and building in Rwanda; Vu la Loi n° 10/2012 du 05/02/2012 portant code de l’urbanisme et de la construction au Rwanda; Iteka Ashingiye ku rya Minisitiri n°06/Cab.M/015 ryo ku wa 08/06/2015 ibyiciro rishyiraho amabwiriza akubiyemo by’inyubako, ibisabwa n’uburyo bukurikizwa mu gusaba no gutanga impushya zo kubaka; Pursuant to Ministerial Order n°06/Cab.M/015 of instructions of 08/06/2015 determining the and conditions categorization of buildings, procedure for application for and issuance of building permits; Vu l’Arrêté Ministériel n° 06/Cab.M/015 du 08/06/2015 déterminant les instructions sur la catégorisation de bâtiments, les conditions et les procédures de demande et d'octroi des autorisations de bâtir; Mu rwego rwo gutanga serivise nziza kandi inoze mu myubakire no mu bugenzuzi bw’inyubako muri rusange; For purposes of effective and delivery of good service in construction and inspection of a building in general; Dans le cadre d’une meilleure prestation de services dans le domaine de la construction et l’inspection en général; ASHYIZEHO AKURIKIRA: AMABWIRIZA GIVES THE FOLLOWING INSTRUCTIONS: DONNE LES INSTRUCTIONS SUIVANTES: Ingingo ya 12: Igihe aya mabwiriza atangira gukurikizwa Article 12: Commencement Article 12: Entrée en vigueur Aya mabwiriza atangira gukurikizwa ku munsi Igazeti ya Leta ya yatangarijweho mu Repubulika y’u Rwanda. These Instructions come into force on the date of their publication in the Official Gazette of the Republic of Rwanda. Les présentes instructions entrent en vigueur le jour de leur publication au Journal Officiel de la République du Rwanda. 40 Kigali, ku wa 28/04/2017 Kigali, on 28/04/2017 Kigali, le 28/04/2017 Official Gazette n°19 of 08/05/2017 (sé) MUSONI James Minisitiri w’Ibikorwaremezo (sé) MUSONI James Minister of Infrastructure (sé) MUSONI James Ministre des Infrastructures 41
Provision text is displayed from LexChat’s stored statute record. Use the official source links to verify amendments, commencement, and current legal force.
Ask AI about this statute
MINISTERIAL INSTRUCTIONS Nº 01/CAB.M/017 OF 28/04/2017 DETERMINING INSPECTION OF TYPES OF BUILDINGS IN RELATION TO THEIR ANTICIPATED RISKS
Sign in to ask AI about this statute
Sign in to start authenticated, citation-grounded statute research.
Sign in