Missouri Revised Statutes § 8.962 - Public works contract defined — certain contract clauses against public policy, exceptions — United States — Missouri law | Esheria

Missouri Revised Statutes § 8.962 - Public works contract defined — certain contract clauses against public policy, exceptions

The section defines “public works contract” and voids clauses that make contractors give up delay-related recovery rights when the delay is caused by the public entity or its agents.

Jurisdiction
United States — Missouri
Instrument
Act or statute
Version
Undated source snapshot
Language
en
Updated
Official source
View official record ↗
contract clauses delay damages public works contracts

Statute overview

About this statute

This page preserves the statute’s identified version, provision structure, official source link, and stored legal text for reading and research.

LexChat organizes source-backed legal information for research. Verify amendments, commencement, and current legal force with the official publisher before relying on it.