Government Code § 2269.256
The construction manager-at-risk must review trade contractor or subcontractor bids or proposals without disclosing their contents during selection, and bids or proposals must later be made available as specified. If the governmental entity requires a different bid to be accepted, it must compensate the construction ma
AI-assisted research synopsis — verify against the official legal text below.
- Jurisdiction
- United States — Texas
- Instrument
- Code
- Version
- Undated source snapshot
- Language
- en
- Official source
- View official record ↗
Citation provenance: source:global:stored-legal-sources · schema StatuteEnrichmentPublicV1.
Statute overview
About this statute
The construction manager-at-risk must review trade contractor or subcontractor bids or proposals without disclosing their contents during selection, and bids or proposals must later be made available as specified. If the governmental entity requires a different bid to be accepted, it must compensate the construction manager-at-risk for added cost and risk.
Ask AI about this statute
Government Code § 2269.256
Sign in to ask AI about this statute
Sign in to start authenticated, citation-grounded statute research.