United States — Utah Act or statute

United States — Utah legislation

Utah Code § 10-20-909, 2014

This section sets rules for municipal building-plan review, inspection timing, and related fees.

application completenessarchitectural/engineering stampingautomated reviewbuilding code compliancebuilding inspectionsbuilding permitsbuilding plan reviewcode complianceconstructionconstruction approvalconstruction complianceconstruction compliance reviewconstruction documentsconstruction permittingconstruction projectconstruction reviewdeferred submittalsdefinitionsdocument productiondocument resubmissiondrainagefeesfire code compliancegeotechnical reportinginspection feesinspection notificationsland developmentland disturbanceland use reviewlodging establishment definitionmunicipal administrationmunicipal approvalmunicipal approval processmunicipal feesmunicipal financemunicipal planning reviewmunicipal screening periodpermit compliancepermit processingplan reviewplan review timingplanningplanning reviewresidential structureresidential structuresscreening periodsewersite developmentsite plan requirementssite specificationsstorm water permitsstorm water protectionstructural calculationssubdivision designthird-party inspection firmsutilitieswater

Professional statute overview

Enactment structure, operative effect and source provenance

Official source

01

Purpose and legislative effect

“This section sets rules for municipal building-plan review, inspection timing, and related fees.”

Use this record to locate individual provisions, understand the instrument’s recorded structure, and move from a research summary to the exact source text.

02

How the instrument operates

  1. 01

    Start with the recorded version

    Enacted 2014. The date shown identifies this source expression and should not be treated as proof that no later change exists.

  2. 02

    Locate the controlling provision

    Use the provision map, part headings and full-text filter to move from the broad subject to the exact legal language.

  3. 03

    Read conditions and exceptions together

    Keep subsections, definitions, provisos and cross-references in context before drawing a legal conclusion.

  4. 04

    Verify currency and official wording

    Confirm later legislation, commencement notices and corrections with the official publisher before advice, filing or reliance.

03

Research entry points

Selected provisions across the instrument. Open any row to continue with the exact stored text.

Subsection 10-20-909(1)(j)

"Structural review" means: a review that verifies that a construction project complies with the following: footing size and bar placement; foundation thickness and bar placement; beam and header sizes; nailing patterns; bearing points;

Section 10-20-909(1)(j)

Subsection 10-20-909(4)(a)

A municipality must finish plan review for certain small residential construction projects within 14 business days after the screening period ends, unless Subsection (7) applies.

Section 10-20-909(4)(a)

Subsection 10-20-909(12)(a)

the name, address, and contact information of: the applicant; and the construction manager/general contractor, as defined in Section 63G-6a-103 , for the construction project;

Section 10-20-909(12)(a)

Subsection 10-20-909(13)

A municipality may choose, at its discretion, to use automated review to help satisfy all or part of its plan-review obligation in this section.

Section 10-20-909(13)

04

Source and current-law status

In force source record

Source record from le.utah.gov · Enacted 2014

In force

This source records the instrument as in force. Confirm subsequent amendments, commencement notices, and judicial treatment before relying on it.

Source-indexed provision map

Sections and provisions

Search by section, heading, part or exact legal wording. Every result remains linked to the stored source record.

Showing 145 of 145 provisions

Provision 145

Part 10-20-9

part 10-20-9 Administration of Land Use, Development, and Management Provisions

§ 10-20-909Fees collected for construction approval -- Approval of plans.Provision

This section sets rules for municipal building-plan review, inspection timing, and related fees.

Fees collected for construction approval -- Approval of plans. As used in this section: "Automated review" means a computerized process used to conduct a plan review, including through the use of software and algorithms to assess compliance with an applicable building code, regulation, or ordinance to ensure that a plan meets all of a municipality's required criteria for approval. "Business day" means the same as that term is defined in Section 10-20-908 . "Construction project" means: the same as that term is defined in Section 38-1a-102 ; or any work requiring a permit for construction of or on a one- or two-family dwelling, a townhome, or other residential structure built under the State Construction Code and State Fire Code. "Lodging establishment" means a place providing temporary sleeping accommodations to the public, including any of the following: a bed and breakfast establishment; a boarding house; a dormitory; a hotel; an inn; a lodging house; a motel; a resort; or a rooming house. "Plan review" means all of the reviews and approvals of a plan that a municipality, including all relevant divisions or departments within a municipality, requires before issuing a building permit, with a scope that may not exceed a review to verify: that the construction project complies with the provisions of the State Construction Code; that the construction project complies with the energy code adopted under Section 15A-2-103 ; that the construction project complies with local ordinances; that the applicant paid any required fees; that the applicant obtained final approvals from any other required reviewing agencies; that the construction project received a structural review; the total square footage for each building level of finished, garage, and unfinished space; and that the plans include a printed statement indicating that, before the disturbance of land and during the actual construction, the applicant will comply with applicable federal, state, and local laws and ordinances, including any storm water protection laws and ordinances. "Plan review" does not mean a review of: a document required to be re-submitted for a construction project other than a construction project for a one-or two-family dwelling or townhome if additional modifications or substantive changes are identified by the plan review; a document submitted as part of a deferred submittal when requested by the applicant and approved by the building official; a document that, due to the document's technical nature or on the request of the applicant, is reviewed by a third party; or a storm water permit. "Screening period" means the three business days following the day on which an applicant submits an application. "State Construction Code" means the same as that term is defined in Section 15A-1-102 . "State Fire Code" means the same as that term is defined in Section 15A-1-102 . "Storm water permit" means the same as that term is defined in Section 19-5-108.5 . "Structural review" means: a review that verifies that a construction project complies with the following: footing size and bar placement; foundation thickness and bar placement; beam and header sizes; nailing patterns; bearing points; structural member size and span; and sheathing; or if the review exceeds the scope of the review described in Subsection (1)(j)(i) , a review that a licensed engineer conducts. "Technical nature" means a characteristic that places an item outside the training and expertise of an individual who regularly performs plan reviews. If a municipality collects a fee for the inspection of a construction project, the municipality shall ensure that the construction project receives a prompt inspection as described in Subsection (2)(b) . If a municipality cannot provide a building inspection within three business days after the day on which the municipality receives the request for the inspection, the building permit applicant may engage a third-party inspection firm from the third-party inspection firm list described in Section 15A-1-105 . Notwithstanding Subsection (2)(b) , if an applicant requests that an inspection take place on a date that is more than three days from the day on which the applicant requests the inspection, the municipality shall conduct the inspection on the date requested. If an inspector identifies one or more violations of the State Construction Code or State Fire Code during an inspection, the inspector shall give the permit holder written notification that: identifies each violation; upon request by the permit holder, includes a reference to each applicable provision of the State Construction Code or State Fire Code; and is delivered: in hardcopy or by electronic means; and the day on which the inspection occurs. A municipality that receives an application for a plan review shall determine if the application is complete, as described in Subsection (12) , within the screening period. If the municipality determines an application for a plan review is complete as described in Subsection (12) within the screening period, the municipality shall begin the plan review process described in Subsection (4) . If the municipality determines that an application for a plan review is not complete as described in Subsection (12) , and if the municipality notifies the applicant of the municipality's determination: before 5 p.m. on the last day of the screening period, the municipality may: pause the screening period until the applicant ensures the application meets the requirements of Subsection (12) ; or reject the incomplete application; or after 5 p.m. on the last day of the screening period, the municipality may not pause the screening period and shall begin the plan review process described in Subsection (4) . If an application is rejected as described in Subsection (3)(b)(i)(B) and an applicant resubmits the application, the resubmission begins a new screening period in which the municipality shall review the resubmitted application to determine if the application is complete as described in Subsection (12) . If the municipality gives notice of an incomplete application after 5 p.m. on the last day of the screening period, the municipality: shall immediately notify the applicant that the municipality has determined the application is not complete and the basis for the determination; may not, except as provided in Subsection (3)(d)(iii) , pause the relevant time period described in Subsection (4) ; and may pause the relevant time period described in Subsection (4)(a) or (b) as described in Subsection (4)(c) . Except as provided in Subsection (7) , once a municipality determines an application is complete, or proceeds to review an incomplete application for plan review under Subsection (3)(b)(ii) , the municipality shall complete a plan review of a construction project for a one-or two-family dwelling or townhome by no later than 14 business days after the day on which the screening period for the application ends. Except as provided in Subsection (7) , once a municipality determines an application is complete, or proceeds to review an incomplete application for plan review under Subsection (3)(b)(ii) , the municipality shall complete a plan review of a construction project for a residential structure built under the State Construction Code that is not a one- or two-family dwelling, townhome, or a lodging establishment, by no later than 21 business days after the day on which the screening period for the application ends. If a municipality gives notice of an incomplete application as described in Subsection (3)(d) , the municipality: may pause the time period described in Subsection (4)(a) or (b) : within the last five days of the relevant time period; and until the applicant provides the municipality with the information necessary to consider the application complete under Subsection (12) ; and shall resume the relevant time period upon receipt of the information necessary to consider the application complete; and may, if necessary, use five additional days beginning the day on which the municipality receives the information described in Subsection (4)(c)(ii) to consider whether the application meets the requirements for a building permit, even if the five additional days extend beyond the relevant time period described in Subsection 4(a) or (b). If, at the conclusion of plan review, the municipality determines the application meets the requirements for a building permit, the municipality shall approve the application and, subject to Subsection (10)(b) , issue the building permit to the applicant. A municipality may utilize another government entity to determine if an application is complete or perform a plan review, in whole or in part. A municipality that utilizes another government entity to determine if an application is complete or perform a plan review, as described in Subsection (5)(a) , shall: notify any other government entities, including water providers, within 24 hours of receiving any building permit application; and provide the government entity all documents necessary to determine if an application is complete or perform a plan review, in whole or in part, as requested by the municipality. A government entity determining if an application is complete or performing a plan review, in whole or in part, as requested by a municipality, shall: comply with the requirements of this chapter; and notify the municipality within the screening period whether the application, or a portion of the application, is complete. An applicant may: waive the plan review time requirements described in Subsection (4) ; or with the municipality's written consent, establish an alternative plan review time requirement. A municipality may not enforce a requirement to have a plan review if: the municipality does not complete the plan review within the relevant time period described in Subsection (4) ; and a licensed architect or structural engineer, or both when required by law, stamps the plan. If a municipality is prohibited from enforcing a requirement to have a plan review under Subsection (8)(a) , the municipality shall return to the applicant the plan review fee. A municipality may attach to a reviewed plan a list that includes: items with which the municipality is concerned and may enforce during construction; and building code violations found in the plan. A municipality may not require an applicant to redraft a plan if the city requests minor changes to the plan that the list described in Subsection (9)(a) identifies. A municipality may only require a single resubmittal of plans for a one- or two-family dwelling or townhome if deficiencies in the plan would affect the site plan interaction or footprint of the design. If a municipality charges a fee for a building permit, the municipality may not refuse payment of the fee at the time the applicant submits an application under Subsection (3) . If a municipality charges a fee for a building permit and does not require the fee for a building permit be included in an application for plan review, upon approval of an application for plan review under Subsection (4)(d) , the municipality may require the applicant to pay the fee for the building permit before the municipality issues the building permit. A municipality may not limit the number of applications submitted under Subsection (3) . For purposes of Subsection (3) , an application for plan review is complete if the application contains: the name, address, and contact information of: the applicant; and the construction manager/general contractor, as defined in Section 63G-6a-103 , for the construction project; a site plan for the construction project that: is drawn to scale; includes a north arrow and legend; and provides specifications for the following: lot size and dimensions; setbacks and overhangs for setbacks; easements; property lines; topographical details, if the slope of the lot is greater than 10%; retaining walls; hard surface areas; curb and gutter elevations as indicated in the subdivision documents; existing and proposed utilities, including water, sewer, and subsurface drainage facilities; street names; driveway locations; defensible space provisions and elevations, if required by the Utah Wildland Urban Interface Code adopted under Section 15A-2-103 ; and the location of the nearest hydrant; construction plans and drawings, including: elevations, only if the construction project is new construction; floor plans for each level, including the location and size of doors, windows, and egress; foundation, structural, and framing detail; electrical, mechanical, and plumbing design; a licensed architect's or structural engineer's stamp, when required by law; and fire suppression details, when required by fire code; documentation of energy code compliance; structural calculations, except for trusses; a geotechnical report, including a slope stability evaluation and retaining wall design, if: the slope of the lot is greater than 15%; and required by the city; a statement indicating: before land disturbance occurs on the subject property, the applicant will obtain a storm water permit; and during actual construction, the applicant shall comply with applicable local ordinances and building codes; and the fees, if any, established by ordinance for the municipality to perform a plan review. A municipality may, at the municipality's discretion, utilize automated review to fulfill, in whole or in part, the municipality's obligation to conduct a plan review described in this section.
Section 10-20-909Verify source
§ 10-20-909(1)Subsection 10-20-909(1)Provision

This subsection defines several terms used in the section, including automated review, construction project, lodging establishment, plan review, screening period, state codes, storm water permit, structural review, and technical nature.

As used in this section: "Automated review" means a computerized process used to conduct a plan review, including through the use of software and algorithms to assess compliance with an applicable building code, regulation, or ordinance to ensure that a plan meets all of a municipality's required criteria for approval. "Business day" means the same as that term is defined in Section 10-20-908 . "Construction project" means: the same as that term is defined in Section 38-1a-102 ; or any work requiring a permit for construction of or on a one- or two-family dwelling, a townhome, or other residential structure built under the State Construction Code and State Fire Code. "Lodging establishment" means a place providing temporary sleeping accommodations to the public, including any of the following: a bed and breakfast establishment; a boarding house; a dormitory; a hotel; an inn; a lodging house; a motel; a resort; or a rooming house. "Plan review" means all of the reviews and approvals of a plan that a municipality, including all relevant divisions or departments within a municipality, requires before issuing a building permit, with a scope that may not exceed a review to verify: that the construction project complies with the provisions of the State Construction Code; that the construction project complies with the energy code adopted under Section 15A-2-103 ; that the construction project complies with local ordinances; that the applicant paid any required fees; that the applicant obtained final approvals from any other required reviewing agencies; that the construction project received a structural review; the total square footage for each building level of finished, garage, and unfinished space; and that the plans include a printed statement indicating that, before the disturbance of land and during the actual construction, the applicant will comply with applicable federal, state, and local laws and ordinances, including any storm water protection laws and ordinances. "Plan review" does not mean a review of: a document required to be re-submitted for a construction project other than a construction project for a one-or two-family dwelling or townhome if additional modifications or substantive changes are identified by the plan review; a document submitted as part of a deferred submittal when requested by the applicant and approved by the building official; a document that, due to the document's technical nature or on the request of the applicant, is reviewed by a third party; or a storm water permit. "Screening period" means the three business days following the day on which an applicant submits an application. "State Construction Code" means the same as that term is defined in Section 15A-1-102 . "State Fire Code" means the same as that term is defined in Section 15A-1-102 . "Storm water permit" means the same as that term is defined in Section 19-5-108.5 . "Structural review" means: a review that verifies that a construction project complies with the following: footing size and bar placement; foundation thickness and bar placement; beam and header sizes; nailing patterns; bearing points; structural member size and span; and sheathing; or if the review exceeds the scope of the review described in Subsection (1)(j)(i) , a review that a licensed engineer conducts. "Technical nature" means a characteristic that places an item outside the training and expertise of an individual who regularly performs plan reviews.
Section 10-20-909(1)Verify source
§ 10-20-909(1)(a)Subsection 10-20-909(1)(a)Provision

"Automated review" means a computerized process used to conduct plan review and assess compliance with applicable building rules so a plan meets a municipality's required approval criteria.

"Automated review" means a computerized process used to conduct a plan review, including through the use of software and algorithms to assess compliance with an applicable building code, regulation, or ordinance to ensure that a plan meets all of a municipality's required criteria for approval.
Section 10-20-909(1)(a)Verify source
§ 10-20-909(1)(b)Subsection 10-20-909(1)(b)Provision

“Business day” has the same meaning as in Section 10-20-908.

"Business day" means the same as that term is defined in Section 10-20-908 .
Section 10-20-909(1)(b)Verify source
§ 10-20-909(1)(c)Subsection 10-20-909(1)(c)Provision

Defines “construction project” to include the term’s meaning in Section 38-1a-102 and certain work requiring a construction permit for residential structures.

"Construction project" means: the same as that term is defined in Section 38-1a-102 ; or any work requiring a permit for construction of or on a one- or two-family dwelling, a townhome, or other residential structure built under the State Construction Code and State Fire Code.
Section 10-20-909(1)(c)Verify source
§ 10-20-909(1)(c)(i)Subsection 10-20-909(1)(c)(i)Provision

This phrase says the term has the same meaning as in Section 38-1a-102.

the same as that term is defined in Section 38-1a-102 ; or
Section 10-20-909(1)(c)(i)Verify source
§ 10-20-909(1)(c)(ii)Subsection 10-20-909(1)(c)(ii)Provision

any work requiring a permit for construction of or on a one- or two-family dwelling, a townhome, or other residential structure built under the State Construction Code and State Fire Code.

any work requiring a permit for construction of or on a one- or two-family dwelling, a townhome, or other residential structure built under the State Construction Code and State Fire Code.
Section 10-20-909(1)(c)(ii)Verify source
§ 10-20-909(1)(d)Subsection 10-20-909(1)(d)Provision

"Lodging establishment" means a place providing temporary sleeping accommodations to the public, including any of the following: a bed and breakfast establishment; a boarding house; a dormitory; a hotel; an inn; a lodging house; a motel; a

"Lodging establishment" means a place providing temporary sleeping accommodations to the public, including any of the following: a bed and breakfast establishment; a boarding house; a dormitory; a hotel; an inn; a lodging house; a motel; a resort; or a rooming house.
Section 10-20-909(1)(d)Verify source
§ 10-20-909(1)(d)(i)Subsection 10-20-909(1)(d)(i)Provision

a bed and breakfast establishment;

a bed and breakfast establishment;
Section 10-20-909(1)(d)(i)Verify source
§ 10-20-909(1)(d)(ii)Subsection 10-20-909(1)(d)(ii)Provision

a boarding house;

a boarding house;
Section 10-20-909(1)(d)(ii)Verify source
§ 10-20-909(1)(d)(iii)Subsection 10-20-909(1)(d)(iii)Provision

a dormitory;

a dormitory;
Section 10-20-909(1)(d)(iii)Verify source
§ 10-20-909(1)(d)(iv)Subsection 10-20-909(1)(d)(iv)Provision

Refers to a hotel.

a hotel;
Section 10-20-909(1)(d)(iv)Verify source
§ 10-20-909(1)(d)(v)Subsection 10-20-909(1)(d)(v)Provision

an inn;

an inn;
Section 10-20-909(1)(d)(v)Verify source
§ 10-20-909(1)(d)(vi)Subsection 10-20-909(1)(d)(vi)Provision

a lodging house;

a lodging house;
Section 10-20-909(1)(d)(vi)Verify source
§ 10-20-909(1)(d)(vii)Subsection 10-20-909(1)(d)(vii)Provision

a motel;

a motel;
Section 10-20-909(1)(d)(vii)Verify source
§ 10-20-909(1)(d)(viii)Subsection 10-20-909(1)(d)(viii)Provision

a resort; or

a resort; or
Section 10-20-909(1)(d)(viii)Verify source
§ 10-20-909(1)(d)(ix)Subsection 10-20-909(1)(d)(ix)Provision

a rooming house.

a rooming house.
Section 10-20-909(1)(d)(ix)Verify source
§ 10-20-909(1)(e)Subsection 10-20-909(1)(e)Provision

The term “plan review” means the municipality’s pre-permit review and approvals for a plan, limited to checking specified compliance items.

"Plan review" means all of the reviews and approvals of a plan that a municipality, including all relevant divisions or departments within a municipality, requires before issuing a building permit, with a scope that may not exceed a review to verify: that the construction project complies with the provisions of the State Construction Code; that the construction project complies with the energy code adopted under Section 15A-2-103 ; that the construction project complies with local ordinances; that the applicant paid any required fees; that the applicant obtained final approvals from any other required reviewing agencies; that the construction project received a structural review; the total square footage for each building level of finished, garage, and unfinished space; and that the plans include a printed statement indicating that, before the disturbance of land and during the actual construction, the applicant will comply with applicable federal, state, and local laws and ordinances, including any storm water protection laws and ordinances. "Plan review" does not mean a review of: a document required to be re-submitted for a construction project other than a construction project for a one-or two-family dwelling or townhome if additional modifications or substantive changes are identified by the plan review; a document submitted as part of a deferred submittal when requested by the applicant and approved by the building official; a document that, due to the document's technical nature or on the request of the applicant, is reviewed by a third party; or a storm water permit.
Section 10-20-909(1)(e)Verify source
§ 10-20-909(1)(e)(i)Subsection 10-20-909(1)(e)(i)Provision

"Plan review" means the reviews and approvals a municipality requires before issuing a building permit.

"Plan review" means all of the reviews and approvals of a plan that a municipality, including all relevant divisions or departments within a municipality, requires before issuing a building permit, with a scope that may not exceed a review to verify: that the construction project complies with the provisions of the State Construction Code; that the construction project complies with the energy code adopted under Section 15A-2-103 ; that the construction project complies with local ordinances; that the applicant paid any required fees; that the applicant obtained final approvals from any other required reviewing agencies; that the construction project received a structural review; the total square footage for each building level of finished, garage, and unfinished space; and that the plans include a printed statement indicating that, before the disturbance of land and during the actual construction, the applicant will comply with applicable federal, state, and local laws and ordinances, including any storm water protection laws and ordinances.
Section 10-20-909(1)(e)(i)Verify source
§ 10-20-909(1)(e)(i)(A)Subsection 10-20-909(1)(e)(i)(A)Provision

that the construction project complies with the provisions of the State Construction Code;

that the construction project complies with the provisions of the State Construction Code;
Section 10-20-909(1)(e)(i)(A)Verify source
§ 10-20-909(1)(e)(i)(B)Subsection 10-20-909(1)(e)(i)(B)Provision

that the construction project complies with the energy code adopted under Section 15A-2-103 ;

that the construction project complies with the energy code adopted under Section 15A-2-103 ;
Section 10-20-909(1)(e)(i)(B)Verify source
§ 10-20-909(1)(e)(i)(C)Subsection 10-20-909(1)(e)(i)(C)Provision

that the construction project complies with local ordinances;

that the construction project complies with local ordinances;
Section 10-20-909(1)(e)(i)(C)Verify source
§ 10-20-909(1)(e)(i)(D)Subsection 10-20-909(1)(e)(i)(D)Provision

that the applicant paid any required fees;

that the applicant paid any required fees;
Section 10-20-909(1)(e)(i)(D)Verify source
§ 10-20-909(1)(e)(i)(E)Subsection 10-20-909(1)(e)(i)(E)Provision

The applicant must have obtained final approvals from any other required reviewing agencies.

that the applicant obtained final approvals from any other required reviewing agencies;
Section 10-20-909(1)(e)(i)(E)Verify source
§ 10-20-909(1)(e)(i)(F)Subsection 10-20-909(1)(e)(i)(F)Provision

that the construction project received a structural review;

that the construction project received a structural review;
Section 10-20-909(1)(e)(i)(F)Verify source
§ 10-20-909(1)(e)(i)(G)Subsection 10-20-909(1)(e)(i)(G)Provision

the total square footage for each building level of finished, garage, and unfinished space; and

the total square footage for each building level of finished, garage, and unfinished space; and
Section 10-20-909(1)(e)(i)(G)Verify source
§ 10-20-909(1)(e)(i)(H)Subsection 10-20-909(1)(e)(i)(H)Provision

The applicant must comply with applicable federal, state, and local laws and ordinances before land is disturbed and during construction, including storm water protection laws and ordinances.

that the plans include a printed statement indicating that, before the disturbance of land and during the actual construction, the applicant will comply with applicable federal, state, and local laws and ordinances, including any storm water protection laws and ordinances.
Section 10-20-909(1)(e)(i)(H)Verify source
§ 10-20-909(1)(e)(ii)Subsection 10-20-909(1)(e)(ii)Provision

"Plan review" does not mean a review of: a document required to be re-submitted for a construction project other than a construction project for a one-or two-family dwelling or townhome if additional modifications or substantive changes

"Plan review" does not mean a review of: a document required to be re-submitted for a construction project other than a construction project for a one-or two-family dwelling or townhome if additional modifications or substantive changes are identified by the plan review; a document submitted as part of a deferred submittal when requested by the applicant and approved by the building official; a document that, due to the document's technical nature or on the request of the applicant, is reviewed by a third party; or a storm water permit.
Section 10-20-909(1)(e)(ii)Verify source
§ 10-20-909(1)(e)(ii)(A)Subsection 10-20-909(1)(e)(ii)(A)Provision

a document required to be re-submitted for a construction project other than a construction project for a one-or two-family dwelling or townhome if additional modifications or substantive changes are identified by the plan review;

a document required to be re-submitted for a construction project other than a construction project for a one-or two-family dwelling or townhome if additional modifications or substantive changes are identified by the plan review;
Section 10-20-909(1)(e)(ii)(A)Verify source
§ 10-20-909(1)(e)(ii)(B)Subsection 10-20-909(1)(e)(ii)(B)Provision

This provision describes a document that may be submitted as part of a deferred submittal when requested by the applicant and approved by the building official.

a document submitted as part of a deferred submittal when requested by the applicant and approved by the building official;
Section 10-20-909(1)(e)(ii)(B)Verify source
§ 10-20-909(1)(e)(ii)(C)Subsection 10-20-909(1)(e)(ii)(C)Provision

a document that, due to the document's technical nature or on the request of the applicant, is reviewed by a third party; or

a document that, due to the document's technical nature or on the request of the applicant, is reviewed by a third party; or
Section 10-20-909(1)(e)(ii)(C)Verify source
§ 10-20-909(1)(e)(ii)(D)Subsection 10-20-909(1)(e)(ii)(D)Provision

a storm water permit.

a storm water permit.
Section 10-20-909(1)(e)(ii)(D)Verify source
§ 10-20-909(1)(f)Subsection 10-20-909(1)(f)Provision

"Screening period" means the three business days after an applicant submits an application.

"Screening period" means the three business days following the day on which an applicant submits an application.
Section 10-20-909(1)(f)Verify source
§ 10-20-909(1)(g)Subsection 10-20-909(1)(g)Provision

“State Construction Code” is defined by reference to Section 15A-1-102.

"State Construction Code" means the same as that term is defined in Section 15A-1-102 .
Section 10-20-909(1)(g)Verify source
§ 10-20-909(1)(h)Subsection 10-20-909(1)(h)Provision

“State Fire Code” has the meaning given in Section 15A-1-102.

"State Fire Code" means the same as that term is defined in Section 15A-1-102 .
Section 10-20-909(1)(h)Verify source
§ 10-20-909(1)(i)Subsection 10-20-909(1)(i)Provision

“Storm water permit” has the same meaning as in Section 19-5-108.5.

"Storm water permit" means the same as that term is defined in Section 19-5-108.5 .
Section 10-20-909(1)(i)Verify source
§ 10-20-909(1)(j)Subsection 10-20-909(1)(j)Provision

"Structural review" means: a review that verifies that a construction project complies with the following: footing size and bar placement; foundation thickness and bar placement; beam and header sizes; nailing patterns; bearing points;

"Structural review" means: a review that verifies that a construction project complies with the following: footing size and bar placement; foundation thickness and bar placement; beam and header sizes; nailing patterns; bearing points; structural member size and span; and sheathing; or if the review exceeds the scope of the review described in Subsection (1)(j)(i) , a review that a licensed engineer conducts.
Section 10-20-909(1)(j)Verify source
§ 10-20-909(1)(j)(i)Subsection 10-20-909(1)(j)(i)Provision

a review that verifies that a construction project complies with the following: footing size and bar placement; foundation thickness and bar placement; beam and header sizes; nailing patterns; bearing points; structural member size and

a review that verifies that a construction project complies with the following: footing size and bar placement; foundation thickness and bar placement; beam and header sizes; nailing patterns; bearing points; structural member size and span; and sheathing; or
Section 10-20-909(1)(j)(i)Verify source
§ 10-20-909(1)(j)(i)(A)Subsection 10-20-909(1)(j)(i)(A)Provision

footing size and bar placement;

footing size and bar placement;
Section 10-20-909(1)(j)(i)(A)Verify source
§ 10-20-909(1)(j)(i)(B)Subsection 10-20-909(1)(j)(i)(B)Provision

foundation thickness and bar placement;

foundation thickness and bar placement;
Section 10-20-909(1)(j)(i)(B)Verify source
§ 10-20-909(1)(j)(i)(C)Subsection 10-20-909(1)(j)(i)(C)Provision

beam and header sizes;

beam and header sizes;
Section 10-20-909(1)(j)(i)(C)Verify source
§ 10-20-909(1)(j)(i)(D)Subsection 10-20-909(1)(j)(i)(D)Provision

nailing patterns;

nailing patterns;
Section 10-20-909(1)(j)(i)(D)Verify source
§ 10-20-909(1)(j)(i)(E)Subsection 10-20-909(1)(j)(i)(E)Provision

bearing points;

bearing points;
Section 10-20-909(1)(j)(i)(E)Verify source
§ 10-20-909(1)(j)(i)(F)Subsection 10-20-909(1)(j)(i)(F)Provision

structural member size and span; and

structural member size and span; and
Section 10-20-909(1)(j)(i)(F)Verify source
§ 10-20-909(1)(j)(i)(G)Subsection 10-20-909(1)(j)(i)(G)Provision

sheathing; or

sheathing; or
Section 10-20-909(1)(j)(i)(G)Verify source
§ 10-20-909(1)(j)(ii)Subsection 10-20-909(1)(j)(ii)Provision

if the review exceeds the scope of the review described in Subsection (1)(j)(i) , a review that a licensed engineer conducts.

if the review exceeds the scope of the review described in Subsection (1)(j)(i) , a review that a licensed engineer conducts.
Section 10-20-909(1)(j)(ii)Verify source
§ 10-20-909(1)(k)Subsection 10-20-909(1)(k)Provision

“Technical nature” means a characteristic outside the training and expertise of a person who regularly performs plan reviews.

"Technical nature" means a characteristic that places an item outside the training and expertise of an individual who regularly performs plan reviews.
Section 10-20-909(1)(k)Verify source
§ 10-20-909(2)Subsection 10-20-909(2)Provision

The municipality must provide a prompt inspection if it charges an inspection fee, and the applicant may use a third-party inspection firm if the municipality cannot inspect within three business days. If the applicant asks for a date more than three days out, the municipality must inspect on that date. Inspectors must give written notice of any code violations found.

If a municipality collects a fee for the inspection of a construction project, the municipality shall ensure that the construction project receives a prompt inspection as described in Subsection (2)(b) . If a municipality cannot provide a building inspection within three business days after the day on which the municipality receives the request for the inspection, the building permit applicant may engage a third-party inspection firm from the third-party inspection firm list described in Section 15A-1-105 . Notwithstanding Subsection (2)(b) , if an applicant requests that an inspection take place on a date that is more than three days from the day on which the applicant requests the inspection, the municipality shall conduct the inspection on the date requested. If an inspector identifies one or more violations of the State Construction Code or State Fire Code during an inspection, the inspector shall give the permit holder written notification that: identifies each violation; upon request by the permit holder, includes a reference to each applicable provision of the State Construction Code or State Fire Code; and is delivered: in hardcopy or by electronic means; and the day on which the inspection occurs.
Section 10-20-909(2)Verify source
§ 10-20-909(2)(a)Subsection 10-20-909(2)(a)Provision

If a municipality charges a construction-inspection fee, it must ensure the project gets a prompt inspection.

If a municipality collects a fee for the inspection of a construction project, the municipality shall ensure that the construction project receives a prompt inspection as described in Subsection (2)(b) .
Section 10-20-909(2)(a)Verify source
§ 10-20-909(2)(b)Subsection 10-20-909(2)(b)Provision

If the municipality cannot provide a building inspection within three business days after receiving the request, the building permit applicant may hire a third-party inspection firm from the listed firms.

If a municipality cannot provide a building inspection within three business days after the day on which the municipality receives the request for the inspection, the building permit applicant may engage a third-party inspection firm from the third-party inspection firm list described in Section 15A-1-105 .
Section 10-20-909(2)(b)Verify source
§ 10-20-909(2)(c)Subsection 10-20-909(2)(c)Provision

If an applicant asks for an inspection date more than three days after the request, the municipality must conduct the inspection on that requested date.

Notwithstanding Subsection (2)(b) , if an applicant requests that an inspection take place on a date that is more than three days from the day on which the applicant requests the inspection, the municipality shall conduct the inspection on the date requested.
Section 10-20-909(2)(c)Verify source
§ 10-20-909(2)(d)Subsection 10-20-909(2)(d)Provision

If an inspector finds violations of the State Construction Code or State Fire Code during an inspection, the inspector must give the permit holder written notice.

If an inspector identifies one or more violations of the State Construction Code or State Fire Code during an inspection, the inspector shall give the permit holder written notification that: identifies each violation; upon request by the permit holder, includes a reference to each applicable provision of the State Construction Code or State Fire Code; and is delivered: in hardcopy or by electronic means; and the day on which the inspection occurs.
Section 10-20-909(2)(d)Verify source
§ 10-20-909(2)(d)(i)Subsection 10-20-909(2)(d)(i)Provision

identifies each violation;

identifies each violation;
Section 10-20-909(2)(d)(i)Verify source
§ 10-20-909(2)(d)(ii)Subsection 10-20-909(2)(d)(ii)Provision

upon request by the permit holder, includes a reference to each applicable provision of the State Construction Code or State Fire Code; and

upon request by the permit holder, includes a reference to each applicable provision of the State Construction Code or State Fire Code; and
Section 10-20-909(2)(d)(ii)Verify source
§ 10-20-909(2)(d)(iii)Subsection 10-20-909(2)(d)(iii)Provision

is delivered: in hardcopy or by electronic means; and the day on which the inspection occurs.

is delivered: in hardcopy or by electronic means; and the day on which the inspection occurs.
Section 10-20-909(2)(d)(iii)Verify source
§ 10-20-909(2)(d)(iii)(A)Subsection 10-20-909(2)(d)(iii)(A)Provision

in hardcopy or by electronic means; and

in hardcopy or by electronic means; and
Section 10-20-909(2)(d)(iii)(A)Verify source
§ 10-20-909(2)(d)(iii)(B)Subsection 10-20-909(2)(d)(iii)(B)Provision

the day on which the inspection occurs.

the day on which the inspection occurs.
Section 10-20-909(2)(d)(iii)(B)Verify source
§ 10-20-909(3)Subsection 10-20-909(3)Provision

A municipality must determine whether a plan review application is complete within the screening period, and then either start plan review, pause screening, or reject the application depending on timing and completeness.

A municipality that receives an application for a plan review shall determine if the application is complete, as described in Subsection (12) , within the screening period. If the municipality determines an application for a plan review is complete as described in Subsection (12) within the screening period, the municipality shall begin the plan review process described in Subsection (4) . If the municipality determines that an application for a plan review is not complete as described in Subsection (12) , and if the municipality notifies the applicant of the municipality's determination: before 5 p.m. on the last day of the screening period, the municipality may: pause the screening period until the applicant ensures the application meets the requirements of Subsection (12) ; or reject the incomplete application; or after 5 p.m. on the last day of the screening period, the municipality may not pause the screening period and shall begin the plan review process described in Subsection (4) . If an application is rejected as described in Subsection (3)(b)(i)(B) and an applicant resubmits the application, the resubmission begins a new screening period in which the municipality shall review the resubmitted application to determine if the application is complete as described in Subsection (12) . If the municipality gives notice of an incomplete application after 5 p.m. on the last day of the screening period, the municipality: shall immediately notify the applicant that the municipality has determined the application is not complete and the basis for the determination; may not, except as provided in Subsection (3)(d)(iii) , pause the relevant time period described in Subsection (4) ; and may pause the relevant time period described in Subsection (4)(a) or (b) as described in Subsection (4)(c) .
Section 10-20-909(3)Verify source
§ 10-20-909(3)(a)Subsection 10-20-909(3)(a)Provision

A municipality that gets a plan review application must decide whether it is complete within the screening period.

A municipality that receives an application for a plan review shall determine if the application is complete, as described in Subsection (12) , within the screening period. If the municipality determines an application for a plan review is complete as described in Subsection (12) within the screening period, the municipality shall begin the plan review process described in Subsection (4) .
Section 10-20-909(3)(a)Verify source
§ 10-20-909(3)(a)(i)Subsection 10-20-909(3)(a)(i)Provision

A municipality that gets a plan review application must decide whether it is complete within the screening period.

A municipality that receives an application for a plan review shall determine if the application is complete, as described in Subsection (12) , within the screening period.
Section 10-20-909(3)(a)(i)Verify source
§ 10-20-909(3)(a)(ii)Subsection 10-20-909(3)(a)(ii)Provision

If the municipality determines a plan review application is complete within the screening period, it must begin the plan review process described in Subsection (4).

If the municipality determines an application for a plan review is complete as described in Subsection (12) within the screening period, the municipality shall begin the plan review process described in Subsection (4) .
Section 10-20-909(3)(a)(ii)Verify source
§ 10-20-909(3)(b)Subsection 10-20-909(3)(b)Provision

If the municipality finds a plan review application incomplete and notifies the applicant, it may pause the screening period or reject the application before 5 p.m. on the last day of the screening period; after that time, it may not pause and must begin plan review.

If the municipality determines that an application for a plan review is not complete as described in Subsection (12) , and if the municipality notifies the applicant of the municipality's determination: before 5 p.m. on the last day of the screening period, the municipality may: pause the screening period until the applicant ensures the application meets the requirements of Subsection (12) ; or reject the incomplete application; or after 5 p.m. on the last day of the screening period, the municipality may not pause the screening period and shall begin the plan review process described in Subsection (4) .
Section 10-20-909(3)(b)Verify source
§ 10-20-909(3)(b)(i)Subsection 10-20-909(3)(b)(i)Provision

Before 5 p.m. on the last day of the screening period, the municipality may pause the screening period until the applicant fixes the application, or reject an incomplete application.

before 5 p.m. on the last day of the screening period, the municipality may: pause the screening period until the applicant ensures the application meets the requirements of Subsection (12) ; or reject the incomplete application; or
Section 10-20-909(3)(b)(i)Verify source
§ 10-20-909(3)(b)(i)(A)Subsection 10-20-909(3)(b)(i)(A)Provision

The applicant must ensure the application meets the requirements of Subsection (12) before the screening period is paused.

pause the screening period until the applicant ensures the application meets the requirements of Subsection (12) ; or
Section 10-20-909(3)(b)(i)(A)Verify source
§ 10-20-909(3)(b)(i)(B)Subsection 10-20-909(3)(b)(i)(B)Provision

Do not reject the incomplete application.

reject the incomplete application; or
Section 10-20-909(3)(b)(i)(B)Verify source
§ 10-20-909(3)(b)(ii)Subsection 10-20-909(3)(b)(ii)Provision

After 5 p.m. on the last day of the screening period, the municipality must not pause the screening period and must begin the plan review process described in Subsection (4).

after 5 p.m. on the last day of the screening period, the municipality may not pause the screening period and shall begin the plan review process described in Subsection (4) .
Section 10-20-909(3)(b)(ii)Verify source
§ 10-20-909(3)(c)Subsection 10-20-909(3)(c)Provision

If a rejected application is resubmitted, the municipality must review it again to decide whether it is complete.

If an application is rejected as described in Subsection (3)(b)(i)(B) and an applicant resubmits the application, the resubmission begins a new screening period in which the municipality shall review the resubmitted application to determine if the application is complete as described in Subsection (12) .
Section 10-20-909(3)(c)Verify source
§ 10-20-909(3)(d)Subsection 10-20-909(3)(d)Provision

If the municipality gives late notice that an application is incomplete, it must immediately tell the applicant the application is incomplete and why, and it generally may not pause the relevant time period except as allowed by the cited exception.

If the municipality gives notice of an incomplete application after 5 p.m. on the last day of the screening period, the municipality: shall immediately notify the applicant that the municipality has determined the application is not complete and the basis for the determination; may not, except as provided in Subsection (3)(d)(iii) , pause the relevant time period described in Subsection (4) ; and may pause the relevant time period described in Subsection (4)(a) or (b) as described in Subsection (4)(c) .
Section 10-20-909(3)(d)Verify source
§ 10-20-909(3)(d)(i)Subsection 10-20-909(3)(d)(i)Provision

The municipality must immediately notify the applicant that the application is incomplete and explain the basis for that determination.

shall immediately notify the applicant that the municipality has determined the application is not complete and the basis for the determination;
Section 10-20-909(3)(d)(i)Verify source
§ 10-20-909(3)(d)(ii)Subsection 10-20-909(3)(d)(ii)Provision

A person may not pause the relevant time period described in Subsection (4), except as provided in Subsection (3)(d)(iii).

may not, except as provided in Subsection (3)(d)(iii) , pause the relevant time period described in Subsection (4) ; and
Section 10-20-909(3)(d)(ii)Verify source
§ 10-20-909(3)(d)(iii)Subsection 10-20-909(3)(d)(iii)Provision

An unspecified actor may pause the relevant time period described in Subsection (4)(a) or (b), as provided in Subsection (4)(c).

may pause the relevant time period described in Subsection (4)(a) or (b) as described in Subsection (4)(c) .
Section 10-20-909(3)(d)(iii)Verify source
§ 10-20-909(4)Subsection 10-20-909(4)Provision

A municipality must finish plan review within 14 business days for one- or two-family dwellings and townhomes, or within 21 business days for certain other residential structures, subject to stated exceptions.

Except as provided in Subsection (7) , once a municipality determines an application is complete, or proceeds to review an incomplete application for plan review under Subsection (3)(b)(ii) , the municipality shall complete a plan review of a construction project for a one-or two-family dwelling or townhome by no later than 14 business days after the day on which the screening period for the application ends. Except as provided in Subsection (7) , once a municipality determines an application is complete, or proceeds to review an incomplete application for plan review under Subsection (3)(b)(ii) , the municipality shall complete a plan review of a construction project for a residential structure built under the State Construction Code that is not a one- or two-family dwelling, townhome, or a lodging establishment, by no later than 21 business days after the day on which the screening period for the application ends. If a municipality gives notice of an incomplete application as described in Subsection (3)(d) , the municipality: may pause the time period described in Subsection (4)(a) or (b) : within the last five days of the relevant time period; and until the applicant provides the municipality with the information necessary to consider the application complete under Subsection (12) ; and shall resume the relevant time period upon receipt of the information necessary to consider the application complete; and may, if necessary, use five additional days beginning the day on which the municipality receives the information described in Subsection (4)(c)(ii) to consider whether the application meets the requirements for a building permit, even if the five additional days extend beyond the relevant time period described in Subsection 4(a) or (b). If, at the conclusion of plan review, the municipality determines the application meets the requirements for a building permit, the municipality shall approve the application and, subject to Subsection (10)(b) , issue the building permit to the applicant.
Section 10-20-909(4)Verify source
§ 10-20-909(4)(a)Subsection 10-20-909(4)(a)Provision

A municipality must finish plan review for certain small residential construction projects within 14 business days after the screening period ends, unless Subsection (7) applies.

Except as provided in Subsection (7) , once a municipality determines an application is complete, or proceeds to review an incomplete application for plan review under Subsection (3)(b)(ii) , the municipality shall complete a plan review of a construction project for a one-or two-family dwelling or townhome by no later than 14 business days after the day on which the screening period for the application ends.
Section 10-20-909(4)(a)Verify source
§ 10-20-909(4)(b)Subsection 10-20-909(4)(b)Provision

A municipality must finish plan review within 21 business days after the screening period ends, if the application is complete or if it reviews an incomplete application under Subsection (3)(b)(ii), unless Subsection (7) applies.

Except as provided in Subsection (7) , once a municipality determines an application is complete, or proceeds to review an incomplete application for plan review under Subsection (3)(b)(ii) , the municipality shall complete a plan review of a construction project for a residential structure built under the State Construction Code that is not a one- or two-family dwelling, townhome, or a lodging establishment, by no later than 21 business days after the day on which the screening period for the application ends.
Section 10-20-909(4)(b)Verify source
§ 10-20-909(4)(c)Subsection 10-20-909(4)(c)Provision

If a municipality gives notice of an incomplete application as described in Subsection (3)(d) , the municipality: may pause the time period described in Subsection (4)(a) or (b) : within the last five days of the relevant time period; and

If a municipality gives notice of an incomplete application as described in Subsection (3)(d) , the municipality: may pause the time period described in Subsection (4)(a) or (b) : within the last five days of the relevant time period; and until the applicant provides the municipality with the information necessary to consider the application complete under Subsection (12) ; and shall resume the relevant time period upon receipt of the information necessary to consider the application complete; and may, if necessary, use five additional days beginning the day on which the municipality receives the information described in Subsection (4)(c)(ii) to consider whether the application meets the requirements for a building permit, even if the five additional days extend beyond the relevant time period described in Subsection 4(a) or (b).
Section 10-20-909(4)(c)Verify source
§ 10-20-909(4)(c)(i)Subsection 10-20-909(4)(c)(i)Provision

The applicant may pause the time period described in Subsection (4)(a) or (b) during the last five days of that period, and only until the applicant gives the municipality the information needed to treat the application as complete under Subsection (12).

may pause the time period described in Subsection (4)(a) or (b) : within the last five days of the relevant time period; and until the applicant provides the municipality with the information necessary to consider the application complete under Subsection (12) ; and
Section 10-20-909(4)(c)(i)Verify source
§ 10-20-909(4)(c)(i)(A)Subsection 10-20-909(4)(c)(i)(A)Provision

Something must occur within the last five days of the relevant time period.

within the last five days of the relevant time period; and
Section 10-20-909(4)(c)(i)(A)Verify source
§ 10-20-909(4)(c)(i)(B)Subsection 10-20-909(4)(c)(i)(B)Provision

until the applicant provides the municipality with the information necessary to consider the application complete under Subsection (12) ; and

until the applicant provides the municipality with the information necessary to consider the application complete under Subsection (12) ; and
Section 10-20-909(4)(c)(i)(B)Verify source
§ 10-20-909(4)(c)(ii)Subsection 10-20-909(4)(c)(ii)Provision

The relevant time period must resume when the information needed to treat the application as complete is received.

shall resume the relevant time period upon receipt of the information necessary to consider the application complete; and
Section 10-20-909(4)(c)(ii)Verify source
§ 10-20-909(4)(c)(iii)Subsection 10-20-909(4)(c)(iii)Provision

may, if necessary, use five additional days beginning the day on which the municipality receives the information described in Subsection (4)(c)(ii) to consider whether the application meets the requirements for a building permit, even if

may, if necessary, use five additional days beginning the day on which the municipality receives the information described in Subsection (4)(c)(ii) to consider whether the application meets the requirements for a building permit, even if the five additional days extend beyond the relevant time period described in Subsection 4(a) or (b).
Section 10-20-909(4)(c)(iii)Verify source
§ 10-20-909(4)(d)Subsection 10-20-909(4)(d)Provision

If plan review ends and the application meets building-permit requirements, the municipality must approve the application and issue the permit to the applicant, subject to Subsection (10)(b).

If, at the conclusion of plan review, the municipality determines the application meets the requirements for a building permit, the municipality shall approve the application and, subject to Subsection (10)(b) , issue the building permit to the applicant.
Section 10-20-909(4)(d)Verify source
§ 10-20-909(5)Subsection 10-20-909(5)Provision

A municipality may utilize another government entity to determine if an application is complete or perform a plan review, in whole or in part. A municipality that utilizes another government entity to determine if an application is

A municipality may utilize another government entity to determine if an application is complete or perform a plan review, in whole or in part. A municipality that utilizes another government entity to determine if an application is complete or perform a plan review, as described in Subsection (5)(a) , shall: notify any other government entities, including water providers, within 24 hours of receiving any building permit application; and provide the government entity all documents necessary to determine if an application is complete or perform a plan review, in whole or in part, as requested by the municipality.
Section 10-20-909(5)Verify source
§ 10-20-909(5)(a)Subsection 10-20-909(5)(a)Provision

A municipality may use another government entity to check whether an application is complete or to do a plan review, in whole or in part.

A municipality may utilize another government entity to determine if an application is complete or perform a plan review, in whole or in part.
Section 10-20-909(5)(a)Verify source
§ 10-20-909(5)(b)Subsection 10-20-909(5)(b)Provision

A municipality using another government entity for completeness review or plan review must notify other government entities, including water providers, within 24 hours after receiving a building permit application, and must provide the government entity the documents it needs for that review when requested.

A municipality that utilizes another government entity to determine if an application is complete or perform a plan review, as described in Subsection (5)(a) , shall: notify any other government entities, including water providers, within 24 hours of receiving any building permit application; and provide the government entity all documents necessary to determine if an application is complete or perform a plan review, in whole or in part, as requested by the municipality.
Section 10-20-909(5)(b)Verify source
§ 10-20-909(5)(b)(i)Subsection 10-20-909(5)(b)(i)Provision

Notify other government entities, including water providers, within 24 hours after receiving a building permit application.

notify any other government entities, including water providers, within 24 hours of receiving any building permit application; and
Section 10-20-909(5)(b)(i)Verify source
§ 10-20-909(5)(b)(ii)Subsection 10-20-909(5)(b)(ii)Provision

provide the government entity all documents necessary to determine if an application is complete or perform a plan review, in whole or in part, as requested by the municipality.

provide the government entity all documents necessary to determine if an application is complete or perform a plan review, in whole or in part, as requested by the municipality.
Section 10-20-909(5)(b)(ii)Verify source
§ 10-20-909(6)Subsection 10-20-909(6)Provision

A government entity doing an application completeness check or plan review requested by a municipality must follow this chapter and tell the municipality within the screening period whether the application, or part of it, is complete.

A government entity determining if an application is complete or performing a plan review, in whole or in part, as requested by a municipality, shall: comply with the requirements of this chapter; and notify the municipality within the screening period whether the application, or a portion of the application, is complete.
Section 10-20-909(6)Verify source
§ 10-20-909(6)(a)Subsection 10-20-909(6)(a)Provision

A person must comply with the requirements of this chapter.

comply with the requirements of this chapter; and
Section 10-20-909(6)(a)Verify source
§ 10-20-909(6)(b)Subsection 10-20-909(6)(b)Provision

The application submitter must notify the municipality within the screening period whether the application, or part of it, is complete.

notify the municipality within the screening period whether the application, or a portion of the application, is complete.
Section 10-20-909(6)(b)Verify source
§ 10-20-909(7)Subsection 10-20-909(7)Provision

An applicant may waive the plan review time requirements in Subsection (4), or with the municipality’s written consent set an alternative plan review time requirement.

An applicant may: waive the plan review time requirements described in Subsection (4) ; or with the municipality's written consent, establish an alternative plan review time requirement.
Section 10-20-909(7)Verify source
§ 10-20-909(7)(a)Subsection 10-20-909(7)(a)Provision

An unspecified actor may waive the plan review time requirements described in Subsection (4).

waive the plan review time requirements described in Subsection (4) ; or
Section 10-20-909(7)(a)Verify source
§ 10-20-909(7)(b)Subsection 10-20-909(7)(b)Provision

With the municipality’s written consent, an alternative plan review time requirement may be established.

with the municipality's written consent, establish an alternative plan review time requirement.
Section 10-20-909(7)(b)Verify source
§ 10-20-909(8)Subsection 10-20-909(8)Provision

A municipality may not enforce a plan-review requirement if it misses the applicable review deadline and the plan is stamped by a licensed architect or structural engineer, when required by law. If that happens, the municipality must return the plan review fee to the applicant.

A municipality may not enforce a requirement to have a plan review if: the municipality does not complete the plan review within the relevant time period described in Subsection (4) ; and a licensed architect or structural engineer, or both when required by law, stamps the plan. If a municipality is prohibited from enforcing a requirement to have a plan review under Subsection (8)(a) , the municipality shall return to the applicant the plan review fee.
Section 10-20-909(8)Verify source
§ 10-20-909(8)(a)Subsection 10-20-909(8)(a)Provision

A municipality may not enforce a plan review requirement if it misses the relevant time period in Subsection (4) and a licensed architect or structural engineer stamps the plan.

A municipality may not enforce a requirement to have a plan review if: the municipality does not complete the plan review within the relevant time period described in Subsection (4) ; and a licensed architect or structural engineer, or both when required by law, stamps the plan.
Section 10-20-909(8)(a)Verify source
§ 10-20-909(8)(a)(i)Subsection 10-20-909(8)(a)(i)Provision

This text refers to a municipality not completing a plan review within the time period in Subsection (4).

the municipality does not complete the plan review within the relevant time period described in Subsection (4) ; and
Section 10-20-909(8)(a)(i)Verify source
§ 10-20-909(8)(a)(ii)Subsection 10-20-909(8)(a)(ii)Provision

A licensed architect or structural engineer, or both when required by law, stamps the plan.

a licensed architect or structural engineer, or both when required by law, stamps the plan.
Section 10-20-909(8)(a)(ii)Verify source
§ 10-20-909(8)(b)Subsection 10-20-909(8)(b)Provision

If a municipality cannot enforce the plan review requirement under Subsection (8)(a), it must return the plan review fee to the applicant.

If a municipality is prohibited from enforcing a requirement to have a plan review under Subsection (8)(a) , the municipality shall return to the applicant the plan review fee.
Section 10-20-909(8)(b)Verify source
§ 10-20-909(9)Subsection 10-20-909(9)Provision

A municipality may attach a concern-and-violations list to a reviewed plan, may not require redrafting for identified minor changes, and may require only one resubmittal for certain small residential plans when specified deficiencies affect site plan interaction or footprint.

A municipality may attach to a reviewed plan a list that includes: items with which the municipality is concerned and may enforce during construction; and building code violations found in the plan. A municipality may not require an applicant to redraft a plan if the city requests minor changes to the plan that the list described in Subsection (9)(a) identifies. A municipality may only require a single resubmittal of plans for a one- or two-family dwelling or townhome if deficiencies in the plan would affect the site plan interaction or footprint of the design.
Section 10-20-909(9)Verify source
§ 10-20-909(9)(a)Subsection 10-20-909(9)(a)Provision

A municipality may attach a list to a reviewed plan.

A municipality may attach to a reviewed plan a list that includes: items with which the municipality is concerned and may enforce during construction; and building code violations found in the plan.
Section 10-20-909(9)(a)Verify source
§ 10-20-909(9)(a)(i)Subsection 10-20-909(9)(a)(i)Provision

The municipality may enforce items it is concerned with during construction.

items with which the municipality is concerned and may enforce during construction; and
Section 10-20-909(9)(a)(i)Verify source
§ 10-20-909(9)(a)(ii)Subsection 10-20-909(9)(a)(ii)Provision

building code violations found in the plan.

building code violations found in the plan.
Section 10-20-909(9)(a)(ii)Verify source
§ 10-20-909(9)(b)Subsection 10-20-909(9)(b)Provision

A municipality may not require an applicant to redraft a plan when the city only requests minor changes identified by the list in Subsection (9)(a).

A municipality may not require an applicant to redraft a plan if the city requests minor changes to the plan that the list described in Subsection (9)(a) identifies.
Section 10-20-909(9)(b)Verify source
§ 10-20-909(9)(c)Subsection 10-20-909(9)(c)Provision

A municipality may require only one resubmittal of plans for a one- or two-family dwelling or townhome, and only when plan deficiencies affect site plan interaction or the design footprint.

A municipality may only require a single resubmittal of plans for a one- or two-family dwelling or townhome if deficiencies in the plan would affect the site plan interaction or footprint of the design.
Section 10-20-909(9)(c)Verify source
§ 10-20-909(10)Subsection 10-20-909(10)Provision

A municipality charging a building-permit fee may not refuse that payment when the applicant submits the application under Subsection (3).

If a municipality charges a fee for a building permit, the municipality may not refuse payment of the fee at the time the applicant submits an application under Subsection (3) . If a municipality charges a fee for a building permit and does not require the fee for a building permit be included in an application for plan review, upon approval of an application for plan review under Subsection (4)(d) , the municipality may require the applicant to pay the fee for the building permit before the municipality issues the building permit.
Section 10-20-909(10)Verify source
§ 10-20-909(10)(a)Subsection 10-20-909(10)(a)Provision

A municipality that charges a building-permit fee may not refuse payment when the applicant submits the application under Subsection (3).

If a municipality charges a fee for a building permit, the municipality may not refuse payment of the fee at the time the applicant submits an application under Subsection (3) .
Section 10-20-909(10)(a)Verify source
§ 10-20-909(10)(b)Subsection 10-20-909(10)(b)Provision

A municipality may require payment of a building-permit fee before issuing the permit, if it charges that fee and does not require the fee to be included in the plan-review application.

If a municipality charges a fee for a building permit and does not require the fee for a building permit be included in an application for plan review, upon approval of an application for plan review under Subsection (4)(d) , the municipality may require the applicant to pay the fee for the building permit before the municipality issues the building permit.
Section 10-20-909(10)(b)Verify source
§ 10-20-909(11)Subsection 10-20-909(11)Provision

A municipality may not limit the number of applications submitted under Subsection (3).

A municipality may not limit the number of applications submitted under Subsection (3) .
Section 10-20-909(11)Verify source
§ 10-20-909(12)Subsection 10-20-909(12)Provision

For purposes of Subsection (3) , an application for plan review is complete if the application contains: the name, address, and contact information of: the applicant; and the construction manager/general contractor, as defined in Section

For purposes of Subsection (3) , an application for plan review is complete if the application contains: the name, address, and contact information of: the applicant; and the construction manager/general contractor, as defined in Section 63G-6a-103 , for the construction project; a site plan for the construction project that: is drawn to scale; includes a north arrow and legend; and provides specifications for the following: lot size and dimensions; setbacks and overhangs for setbacks; easements; property lines; topographical details, if the slope of the lot is greater than 10%; retaining walls; hard surface areas; curb and gutter elevations as indicated in the subdivision documents; existing and proposed utilities, including water, sewer, and subsurface drainage facilities; street names; driveway locations; defensible space provisions and elevations, if required by the Utah Wildland Urban Interface Code adopted under Section 15A-2-103 ; and the location of the nearest hydrant; construction plans and drawings, including: elevations, only if the construction project is new construction; floor plans for each level, including the location and size of doors, windows, and egress; foundation, structural, and framing detail; electrical, mechanical, and plumbing design; a licensed architect's or structural engineer's stamp, when required by law; and fire suppression details, when required by fire code; documentation of energy code compliance; structural calculations, except for trusses; a geotechnical report, including a slope stability evaluation and retaining wall design, if: the slope of the lot is greater than 15%; and required by the city; a statement indicating: before land disturbance occurs on the subject property, the applicant will obtain a storm water permit; and during actual construction, the applicant shall comply with applicable local ordinances and building codes; and the fees, if any, established by ordinance for the municipality to perform a plan review.
Section 10-20-909(12)Verify source
§ 10-20-909(12)(a)Subsection 10-20-909(12)(a)Provision

the name, address, and contact information of: the applicant; and the construction manager/general contractor, as defined in Section 63G-6a-103 , for the construction project;

the name, address, and contact information of: the applicant; and the construction manager/general contractor, as defined in Section 63G-6a-103 , for the construction project;
Section 10-20-909(12)(a)Verify source
§ 10-20-909(12)(a)(i)Subsection 10-20-909(12)(a)(i)Provision

the applicant; and

the applicant; and
Section 10-20-909(12)(a)(i)Verify source
§ 10-20-909(12)(a)(ii)Subsection 10-20-909(12)(a)(ii)Provision

Refers to the construction manager/general contractor for the construction project.

the construction manager/general contractor, as defined in Section 63G-6a-103 , for the construction project;
Section 10-20-909(12)(a)(ii)Verify source
§ 10-20-909(12)(b)Subsection 10-20-909(12)(b)Provision

The site plan must be drawn to scale and include a north arrow, legend, and specified project details.

a site plan for the construction project that: is drawn to scale; includes a north arrow and legend; and provides specifications for the following: lot size and dimensions; setbacks and overhangs for setbacks; easements; property lines; topographical details, if the slope of the lot is greater than 10%; retaining walls; hard surface areas; curb and gutter elevations as indicated in the subdivision documents; existing and proposed utilities, including water, sewer, and subsurface drainage facilities; street names; driveway locations; defensible space provisions and elevations, if required by the Utah Wildland Urban Interface Code adopted under Section 15A-2-103 ; and the location of the nearest hydrant;
Section 10-20-909(12)(b)Verify source
§ 10-20-909(12)(b)(i)Subsection 10-20-909(12)(b)(i)Provision

is drawn to scale;

is drawn to scale;
Section 10-20-909(12)(b)(i)Verify source
§ 10-20-909(12)(b)(ii)Subsection 10-20-909(12)(b)(ii)Provision

includes a north arrow and legend; and

includes a north arrow and legend; and
Section 10-20-909(12)(b)(ii)Verify source
§ 10-20-909(12)(b)(iii)Subsection 10-20-909(12)(b)(iii)Provision

provides specifications for the following: lot size and dimensions; setbacks and overhangs for setbacks; easements; property lines; topographical details, if the slope of the lot is greater than 10%; retaining walls; hard surface areas;

provides specifications for the following: lot size and dimensions; setbacks and overhangs for setbacks; easements; property lines; topographical details, if the slope of the lot is greater than 10%; retaining walls; hard surface areas; curb and gutter elevations as indicated in the subdivision documents; existing and proposed utilities, including water, sewer, and subsurface drainage facilities; street names; driveway locations; defensible space provisions and elevations, if required by the Utah Wildland Urban Interface Code adopted under Section 15A-2-103 ; and the location of the nearest hydrant;
Section 10-20-909(12)(b)(iii)Verify source
§ 10-20-909(12)(b)(iii)(A)Subsection 10-20-909(12)(b)(iii)(A)Provision

lot size and dimensions;

lot size and dimensions;
Section 10-20-909(12)(b)(iii)(A)Verify source
§ 10-20-909(12)(b)(iii)(B)Subsection 10-20-909(12)(b)(iii)(B)Provision

setbacks and overhangs for setbacks;

setbacks and overhangs for setbacks;
Section 10-20-909(12)(b)(iii)(B)Verify source
§ 10-20-909(12)(b)(iii)(C)Subsection 10-20-909(12)(b)(iii)(C)Provision

easements;

easements;
Section 10-20-909(12)(b)(iii)(C)Verify source
§ 10-20-909(12)(b)(iii)(D)Subsection 10-20-909(12)(b)(iii)(D)Provision

property lines;

property lines;
Section 10-20-909(12)(b)(iii)(D)Verify source
§ 10-20-909(12)(b)(iii)(E)Subsection 10-20-909(12)(b)(iii)(E)Provision

topographical details, if the slope of the lot is greater than 10%;

topographical details, if the slope of the lot is greater than 10%;
Section 10-20-909(12)(b)(iii)(E)Verify source
§ 10-20-909(12)(b)(iii)(F)Subsection 10-20-909(12)(b)(iii)(F)Provision

retaining walls;

retaining walls;
Section 10-20-909(12)(b)(iii)(F)Verify source
§ 10-20-909(12)(b)(iii)(G)Subsection 10-20-909(12)(b)(iii)(G)Provision

hard surface areas;

hard surface areas;
Section 10-20-909(12)(b)(iii)(G)Verify source
§ 10-20-909(12)(b)(iii)(H)Subsection 10-20-909(12)(b)(iii)(H)Provision

curb and gutter elevations as indicated in the subdivision documents;

curb and gutter elevations as indicated in the subdivision documents;
Section 10-20-909(12)(b)(iii)(H)Verify source
§ 10-20-909(12)(b)(iii)(I)Subsection 10-20-909(12)(b)(iii)(I)Provision

existing and proposed utilities, including water, sewer, and subsurface drainage facilities;

existing and proposed utilities, including water, sewer, and subsurface drainage facilities;
Section 10-20-909(12)(b)(iii)(I)Verify source
§ 10-20-909(12)(b)(iii)(J)Subsection 10-20-909(12)(b)(iii)(J)Provision

street names;

street names;
Section 10-20-909(12)(b)(iii)(J)Verify source
§ 10-20-909(12)(b)(iii)(K)Subsection 10-20-909(12)(b)(iii)(K)Provision

driveway locations;

driveway locations;
Section 10-20-909(12)(b)(iii)(K)Verify source
§ 10-20-909(12)(b)(iii)(L)Subsection 10-20-909(12)(b)(iii)(L)Provision

defensible space provisions and elevations, if required by the Utah Wildland Urban Interface Code adopted under Section 15A-2-103 ; and

defensible space provisions and elevations, if required by the Utah Wildland Urban Interface Code adopted under Section 15A-2-103 ; and
Section 10-20-909(12)(b)(iii)(L)Verify source
§ 10-20-909(12)(b)(iii)(M)Subsection 10-20-909(12)(b)(iii)(M)Provision

the location of the nearest hydrant;

the location of the nearest hydrant;
Section 10-20-909(12)(b)(iii)(M)Verify source
§ 10-20-909(12)(c)Subsection 10-20-909(12)(c)Provision

construction plans and drawings, including: elevations, only if the construction project is new construction; floor plans for each level, including the location and size of doors, windows, and egress; foundation, structural, and framing

construction plans and drawings, including: elevations, only if the construction project is new construction; floor plans for each level, including the location and size of doors, windows, and egress; foundation, structural, and framing detail; electrical, mechanical, and plumbing design; a licensed architect's or structural engineer's stamp, when required by law; and fire suppression details, when required by fire code;
Section 10-20-909(12)(c)Verify source
§ 10-20-909(12)(c)(i)Subsection 10-20-909(12)(c)(i)Provision

elevations, only if the construction project is new construction;

elevations, only if the construction project is new construction;
Section 10-20-909(12)(c)(i)Verify source
§ 10-20-909(12)(c)(ii)Subsection 10-20-909(12)(c)(ii)Provision

floor plans for each level, including the location and size of doors, windows, and egress;

floor plans for each level, including the location and size of doors, windows, and egress;
Section 10-20-909(12)(c)(ii)Verify source
§ 10-20-909(12)(c)(iii)Subsection 10-20-909(12)(c)(iii)Provision

foundation, structural, and framing detail;

foundation, structural, and framing detail;
Section 10-20-909(12)(c)(iii)Verify source
§ 10-20-909(12)(c)(iv)Subsection 10-20-909(12)(c)(iv)Provision

electrical, mechanical, and plumbing design;

electrical, mechanical, and plumbing design;
Section 10-20-909(12)(c)(iv)Verify source
§ 10-20-909(12)(c)(v)Subsection 10-20-909(12)(c)(v)Provision

a licensed architect's or structural engineer's stamp, when required by law; and

a licensed architect's or structural engineer's stamp, when required by law; and
Section 10-20-909(12)(c)(v)Verify source
§ 10-20-909(12)(c)(vi)Subsection 10-20-909(12)(c)(vi)Provision

fire suppression details, when required by fire code;

fire suppression details, when required by fire code;
Section 10-20-909(12)(c)(vi)Verify source
§ 10-20-909(12)(d)Subsection 10-20-909(12)(d)Provision

documentation of energy code compliance;

documentation of energy code compliance;
Section 10-20-909(12)(d)Verify source
§ 10-20-909(12)(e)Subsection 10-20-909(12)(e)Provision

structural calculations, except for trusses;

structural calculations, except for trusses;
Section 10-20-909(12)(e)Verify source
§ 10-20-909(12)(f)Subsection 10-20-909(12)(f)Provision

a geotechnical report, including a slope stability evaluation and retaining wall design, if: the slope of the lot is greater than 15%; and required by the city;

a geotechnical report, including a slope stability evaluation and retaining wall design, if: the slope of the lot is greater than 15%; and required by the city;
Section 10-20-909(12)(f)Verify source
§ 10-20-909(12)(f)(i)Subsection 10-20-909(12)(f)(i)Provision

the slope of the lot is greater than 15%; and

the slope of the lot is greater than 15%; and
Section 10-20-909(12)(f)(i)Verify source
§ 10-20-909(12)(f)(ii)Subsection 10-20-909(12)(f)(ii)Provision

required by the city;

required by the city;
Section 10-20-909(12)(f)(ii)Verify source
§ 10-20-909(12)(g)Subsection 10-20-909(12)(g)Provision

The applicant must obtain a storm water permit before land disturbance and must comply with applicable local ordinances and building codes during construction.

a statement indicating: before land disturbance occurs on the subject property, the applicant will obtain a storm water permit; and during actual construction, the applicant shall comply with applicable local ordinances and building codes; and
Section 10-20-909(12)(g)Verify source
§ 10-20-909(12)(g)(i)Subsection 10-20-909(12)(g)(i)Provision

Before land disturbance occurs on the subject property, the applicant must obtain a storm water permit.

before land disturbance occurs on the subject property, the applicant will obtain a storm water permit; and
Section 10-20-909(12)(g)(i)Verify source
§ 10-20-909(12)(g)(ii)Subsection 10-20-909(12)(g)(ii)Provision

During actual construction, the applicant must comply with applicable local ordinances and building codes.

during actual construction, the applicant shall comply with applicable local ordinances and building codes; and
Section 10-20-909(12)(g)(ii)Verify source
§ 10-20-909(12)(h)Subsection 10-20-909(12)(h)Provision

the fees, if any, established by ordinance for the municipality to perform a plan review.

the fees, if any, established by ordinance for the municipality to perform a plan review.
Section 10-20-909(12)(h)Verify source
§ 10-20-909(13)Subsection 10-20-909(13)Provision

A municipality may choose, at its discretion, to use automated review to help satisfy all or part of its plan-review obligation in this section.

A municipality may, at the municipality's discretion, utilize automated review to fulfill, in whole or in part, the municipality's obligation to conduct a plan review described in this section.
Section 10-20-909(13)Verify source

Legislative relationships

1 referenced instrument

Names are derived from the stored provision headings and citation-enrichment layer. Treat this as a research index and verify each relationship against the source text.

N–S

1 instrument

  • State Construction Code

    Sections 10-20-909, 10-20-909(1), 10-20-909(1)(e), 10-20-909(1)(e)(i), 10-20-909(1)(e)(i)(A), 10-20-909(2), 10-20-909(2)(d), 10-20-909(2)(d)(ii)

Recorded versions and source checkpoint

1 version available in this collection

Current-law checkpoint
  • Undated version · currentEnglish · In force

Source-linked research

Ask AI about this statute

The overview, provisions, and source records above are public. Continue in a separate conversation with this statute’s jurisdiction and source version attached.

About this LexChat collection

Statute information is organised from identified legislative sources for professional research. Corrections can be reported to hello@esheria.ai.