United States — Utah Act or statute

United States — Utah legislation

Utah Code § 11-13-304

Certain entities must get a public service commission certificate before building an electrical generating plant or transmission line, unless an exception applies.

certificateselectrical generating plantsenergy infrastructureproject permittingtransmission lines

Professional statute overview

Enactment structure, operative effect and source provenance

Official source

01

Purpose and legislative effect

“Certain entities must get a public service commission certificate before building an electrical generating plant or transmission line, unless an exception applies.”

Use this record to locate individual provisions, understand the instrument’s recorded structure, and move from a research summary to the exact source text.

02

How the instrument operates

  1. 01

    Start with the recorded version

    Legal dates not recorded. The date shown identifies this source expression and should not be treated as proof that no later change exists.

  2. 02

    Locate the controlling provision

    Use the provision map, part headings and full-text filter to move from the broad subject to the exact legal language.

  3. 03

    Read conditions and exceptions together

    Keep subsections, definitions, provisos and cross-references in context before drawing a legal conclusion.

  4. 04

    Verify currency and official wording

    Confirm later legislation, commencement notices and corrections with the official publisher before advice, filing or reliance.

03

Research entry points

Selected provisions across the instrument. Open any row to continue with the exact stored text.

Subsection 11-13-304(2)

Projects started after the effective date must obtain a certificate of public convenience and necessity, but several listed projects and facilities are exempt.

Section 11-13-304(2)

Subsection 11-13-304(2)(a)

a project for which a feasibility study was initiated prior to the effective date;

Section 11-13-304(2)(a)

Subsection 11-13-304(2)(d)

transmission lines required for the delivery of electricity from a project described in Subsection (2)(a) , or facilities providing additional project capacity, or facilities providing replacement project capacity within the corridor of a

Section 11-13-304(2)(d)

04

Source and current-law status

In force source record

Source record from le.utah.gov · Legal dates not recorded

In force

This source records the instrument as in force. Confirm subsequent amendments, commencement notices, and judicial treatment before relying on it.

Source-indexed provision map

Sections and provisions

Search by section, heading, part or exact legal wording. Every result remains linked to the stored source record.

Showing 7 of 7 provisions

Provision 7

Part 11-13-3

part 11-13-3 Project Entity Provisions

§ 11-13-304Certificate of public convenience and necessity required -- Exceptions.Provision

Certain entities must get a public service commission certificate before building an electrical generating plant or transmission line, unless an exception applies.

Certificate of public convenience and necessity required -- Exceptions. Before proceeding with the construction of any electrical generating plant or transmission line, each interlocal entity and each out-of-state public agency shall first obtain from the public service commission a certificate, after hearing, that public convenience and necessity requires such construction and in addition that such construction will in no way impair the public convenience and necessity of electrical consumers of the state of Utah at the present time or in the future. The requirement to obtain a certificate of public convenience and necessity applies to each project initiated after the section's effective date but does not apply to: a project for which a feasibility study was initiated prior to the effective date; any facilities providing additional project capacity; any facilities providing replacement project capacity; or transmission lines required for the delivery of electricity from a project described in Subsection (2)(a) , or facilities providing additional project capacity, or facilities providing replacement project capacity within the corridor of a transmission line, with reasonable deviation, of a project producing as of April 21, 1987.
Section 11-13-304Verify source
§ 11-13-304(1)Subsection 11-13-304(1)Provision

Before proceeding with the construction of any electrical generating plant or transmission line, each interlocal entity and each out-of-state public agency shall first obtain from the public service commission a certificate, after hearing,

Before proceeding with the construction of any electrical generating plant or transmission line, each interlocal entity and each out-of-state public agency shall first obtain from the public service commission a certificate, after hearing, that public convenience and necessity requires such construction and in addition that such construction will in no way impair the public convenience and necessity of electrical consumers of the state of Utah at the present time or in the future.
Section 11-13-304(1)Verify source
§ 11-13-304(2)Subsection 11-13-304(2)Provision

Projects started after the effective date must obtain a certificate of public convenience and necessity, but several listed projects and facilities are exempt.

The requirement to obtain a certificate of public convenience and necessity applies to each project initiated after the section's effective date but does not apply to: a project for which a feasibility study was initiated prior to the effective date; any facilities providing additional project capacity; any facilities providing replacement project capacity; or transmission lines required for the delivery of electricity from a project described in Subsection (2)(a) , or facilities providing additional project capacity, or facilities providing replacement project capacity within the corridor of a transmission line, with reasonable deviation, of a project producing as of April 21, 1987.
Section 11-13-304(2)Verify source
§ 11-13-304(2)(a)Subsection 11-13-304(2)(a)Provision

a project for which a feasibility study was initiated prior to the effective date;

a project for which a feasibility study was initiated prior to the effective date;
Section 11-13-304(2)(a)Verify source
§ 11-13-304(2)(b)Subsection 11-13-304(2)(b)Provision

any facilities providing additional project capacity;

any facilities providing additional project capacity;
Section 11-13-304(2)(b)Verify source
§ 11-13-304(2)(c)Subsection 11-13-304(2)(c)Provision

any facilities providing replacement project capacity; or

any facilities providing replacement project capacity; or
Section 11-13-304(2)(c)Verify source
§ 11-13-304(2)(d)Subsection 11-13-304(2)(d)Provision

transmission lines required for the delivery of electricity from a project described in Subsection (2)(a) , or facilities providing additional project capacity, or facilities providing replacement project capacity within the corridor of a

transmission lines required for the delivery of electricity from a project described in Subsection (2)(a) , or facilities providing additional project capacity, or facilities providing replacement project capacity within the corridor of a transmission line, with reasonable deviation, of a project producing as of April 21, 1987.
Section 11-13-304(2)(d)Verify source

Legislative relationships

0 referenced instruments

Names are derived from the stored provision headings and citation-enrichment layer. Treat this as a research index and verify each relationship against the source text.

No structured legislative relationships were detected

The statute remains fully searchable by provision. Consult the source text for amendments and cross-references that have not yet been indexed.

Recorded versions and source checkpoint

1 version available in this collection

Current-law checkpoint
  • Undated version · currentEnglish · In force

Source-linked research

Ask AI about this statute

The overview, provisions, and source records above are public. Continue in a separate conversation with this statute’s jurisdiction and source version attached.

About this LexChat collection

Statute information is organised from identified legislative sources for professional research. Corrections can be reported to hello@esheria.ai.