The Office of Energy Development must study continued operation of a project entity’s existing coal-powered generation facility, and a project entity must cooperate and provide information. The of…

coal-powered electrical generationcoal-powered generationcontinued operationeconomic developmentelectric power generationenergy developmentenvironmental complianceenvironmental controlsenvironmental permittingenvironmental regulationfinancial reportingpower generation operationsproject financereporting

Professional statute overview

Enactment structure, operative effect and source provenance

Official source

01

Purpose and legislative effect

“The Office of Energy Development must study continued operation of a project entity’s existing coal-powered generation facility, and a project entity must cooperate and provide information. The office must then report by the specified 2023 interim committee meeting.”

Use this record to locate individual provisions, understand the instrument’s recorded structure, and move from a research summary to the exact source text.

02

How the instrument operates

  1. 01

    Start with the recorded version

    Enacted 2023. The date shown identifies this source expression and should not be treated as proof that no later change exists.

  2. 02

    Locate the controlling provision

    Use the provision map, part headings and full-text filter to move from the broad subject to the exact legal language.

  3. 03

    Read conditions and exceptions together

    Keep subsections, definitions, provisos and cross-references in context before drawing a legal conclusion.

  4. 04

    Verify currency and official wording

    Confirm later legislation, commencement notices and corrections with the official publisher before advice, filing or reliance.

03

Research entry points

Selected provisions across the instrument. Open any row to continue with the exact stored text.

Project entity continued operation study.

The Office of Energy Development must study continued operation of a project entity’s existing coal-powered generation facility, and a project entity must cooperate and provide information. The office must then report by the specified 2…

Section 11-13-319

Subsection 11-13-319(1)(d)

coordinate with state and local economic development agencies to evaluate economic opportunities for continued use of a project entity's existing coal-powered electrical generation facility;

Section 11-13-319(1)(d)

Subsection 11-13-319(4)

The report described in Subsection (3) shall include: the results of the study described in Subsection (1) ; recommendations for continued operation of a project entity's existing coal-powered electrical generation facility; environmental

Section 11-13-319(4)

Subsection 11-13-319(4)(e)

recommendations for legislation to be introduced in the 2024 General Session to enable the continued operation of a project entity's existing coal-powered electrical generation facility.

Section 11-13-319(4)(e)

04

Source and current-law status

In force source record

Source record from le.utah.gov · Enacted 2023

In force

This source records the instrument as in force. Confirm subsequent amendments, commencement notices, and judicial treatment before relying on it.

Source-indexed provision map

Sections and provisions

Search by section, heading, part or exact legal wording. Every result remains linked to the stored source record.

Showing 20 of 20 provisions

Provision 20

Part 11-13-3

part 11-13-3 Project Entity Provisions

§ 11-13-319Project entity continued operation study.Provision

The Office of Energy Development must study continued operation of a project entity’s existing coal-powered generation facility, and a project entity must cooperate and provide information. The office must then report by the specified 2023 interim committee meeting.

Project entity continued operation study. The Office of Energy Development shall conduct a study to: evaluate all environmental regulations and permits to be filed to continue operation of a project entity's existing coal-powered electrical generation facility; identify best available technology to implement additional environmental controls for continued operation of a project entity's existing coal-powered electrical generation facility; identify the transmission capacity of the project entity; coordinate with state and local economic development agencies to evaluate economic opportunities for continued use of a project entity's existing coal-powered electrical generation facility; analyze the financial assets and liabilities of a project entity; identify the best interests of the local economies, local tax base, and the state in relation to a project entity; evaluate the viability of the continued operation of a project entity's existing coal-powered electrical generation facility: under ownership of the state; or in a public private partnership; and identify the steps necessary for the state to obtain first right of refusal for ownership of a project entity's existing coal-powered electrical generation facility. A project entity shall cooperate and provide timely assistance and information to the Office of Energy Development in the preparation of the study described in Subsection (1) . The Office of Energy Development shall report to the Public Utilities, Energy, and Technology Interim Committee and the Legislative Management Committee on or before the Public Utilities, Energy, and Technology Interim Committee's September 2023 interim committee meeting. The report described in Subsection (3) shall include: the results of the study described in Subsection (1) ; recommendations for continued operation of a project entity's existing coal-powered electrical generation facility; environmental controls that need to be implemented for the continued operation of a project entity's existing coal-powered electrical generation facility; recommendations to increase local and state tax revenue through the continued operation of a project entity's existing coal-powered electrical generation facility; and recommendations for legislation to be introduced in the 2024 General Session to enable the continued operation of a project entity's existing coal-powered electrical generation facility.
Section 11-13-319Verify source
§ 11-13-319(1)Subsection 11-13-319(1)Provision

The Office of Energy Development must conduct a study on an existing coal-powered electrical generation facility, including regulations, technology, transmission capacity, economic impacts, finances, viability, and steps for first right of refusal.

The Office of Energy Development shall conduct a study to: evaluate all environmental regulations and permits to be filed to continue operation of a project entity's existing coal-powered electrical generation facility; identify best available technology to implement additional environmental controls for continued operation of a project entity's existing coal-powered electrical generation facility; identify the transmission capacity of the project entity; coordinate with state and local economic development agencies to evaluate economic opportunities for continued use of a project entity's existing coal-powered electrical generation facility; analyze the financial assets and liabilities of a project entity; identify the best interests of the local economies, local tax base, and the state in relation to a project entity; evaluate the viability of the continued operation of a project entity's existing coal-powered electrical generation facility: under ownership of the state; or in a public private partnership; and identify the steps necessary for the state to obtain first right of refusal for ownership of a project entity's existing coal-powered electrical generation facility.
Section 11-13-319(1)Verify source
§ 11-13-319(1)(a)Subsection 11-13-319(1)(a)Provision

A project entity must evaluate all environmental regulations and permits to be filed in order to continue operating its existing coal-powered electrical generation facility.

evaluate all environmental regulations and permits to be filed to continue operation of a project entity's existing coal-powered electrical generation facility;
Section 11-13-319(1)(a)Verify source
§ 11-13-319(1)(b)Subsection 11-13-319(1)(b)Provision

identify best available technology to implement additional environmental controls for continued operation of a project entity's existing coal-powered electrical generation facility;

identify best available technology to implement additional environmental controls for continued operation of a project entity's existing coal-powered electrical generation facility;
Section 11-13-319(1)(b)Verify source
§ 11-13-319(1)(c)Subsection 11-13-319(1)(c)Provision

identify the transmission capacity of the project entity;

identify the transmission capacity of the project entity;
Section 11-13-319(1)(c)Verify source
§ 11-13-319(1)(d)Subsection 11-13-319(1)(d)Provision

coordinate with state and local economic development agencies to evaluate economic opportunities for continued use of a project entity's existing coal-powered electrical generation facility;

coordinate with state and local economic development agencies to evaluate economic opportunities for continued use of a project entity's existing coal-powered electrical generation facility;
Section 11-13-319(1)(d)Verify source
§ 11-13-319(1)(e)Subsection 11-13-319(1)(e)Provision

analyze the financial assets and liabilities of a project entity;

analyze the financial assets and liabilities of a project entity;
Section 11-13-319(1)(e)Verify source
§ 11-13-319(1)(f)Subsection 11-13-319(1)(f)Provision

identify the best interests of the local economies, local tax base, and the state in relation to a project entity;

identify the best interests of the local economies, local tax base, and the state in relation to a project entity;
Section 11-13-319(1)(f)Verify source
§ 11-13-319(1)(g)Subsection 11-13-319(1)(g)Provision

evaluate the viability of the continued operation of a project entity's existing coal-powered electrical generation facility: under ownership of the state; or in a public private partnership; and

evaluate the viability of the continued operation of a project entity's existing coal-powered electrical generation facility: under ownership of the state; or in a public private partnership; and
Section 11-13-319(1)(g)Verify source
§ 11-13-319(1)(g)(i)Subsection 11-13-319(1)(g)(i)Provision

under ownership of the state; or

under ownership of the state; or
Section 11-13-319(1)(g)(i)Verify source
§ 11-13-319(1)(g)(ii)Subsection 11-13-319(1)(g)(ii)Provision

in a public private partnership; and

in a public private partnership; and
Section 11-13-319(1)(g)(ii)Verify source
§ 11-13-319(1)(h)Subsection 11-13-319(1)(h)Provision

The state’s first right of refusal for a project entity’s existing coal-powered electrical generation facility must be obtained by following the required steps.

identify the steps necessary for the state to obtain first right of refusal for ownership of a project entity's existing coal-powered electrical generation facility.
Section 11-13-319(1)(h)Verify source
§ 11-13-319(2)Subsection 11-13-319(2)Provision

A project entity must cooperate with the Office of Energy Development and provide timely assistance and information for the study in Subsection (1).

A project entity shall cooperate and provide timely assistance and information to the Office of Energy Development in the preparation of the study described in Subsection (1) .
Section 11-13-319(2)Verify source
§ 11-13-319(3)Subsection 11-13-319(3)Provision

The Office of Energy Development must report to two legislative committees by the Public Utilities, Energy, and Technology Interim Committee’s September 2023 interim committee meeting.

The Office of Energy Development shall report to the Public Utilities, Energy, and Technology Interim Committee and the Legislative Management Committee on or before the Public Utilities, Energy, and Technology Interim Committee's September 2023 interim committee meeting.
Section 11-13-319(3)Verify source
§ 11-13-319(4)Subsection 11-13-319(4)Provision

The report described in Subsection (3) shall include: the results of the study described in Subsection (1) ; recommendations for continued operation of a project entity's existing coal-powered electrical generation facility; environmental

The report described in Subsection (3) shall include: the results of the study described in Subsection (1) ; recommendations for continued operation of a project entity's existing coal-powered electrical generation facility; environmental controls that need to be implemented for the continued operation of a project entity's existing coal-powered electrical generation facility; recommendations to increase local and state tax revenue through the continued operation of a project entity's existing coal-powered electrical generation facility; and recommendations for legislation to be introduced in the 2024 General Session to enable the continued operation of a project entity's existing coal-powered electrical generation facility.
Section 11-13-319(4)Verify source
§ 11-13-319(4)(a)Subsection 11-13-319(4)(a)Provision

the results of the study described in Subsection (1) ;

the results of the study described in Subsection (1) ;
Section 11-13-319(4)(a)Verify source
§ 11-13-319(4)(b)Subsection 11-13-319(4)(b)Provision

Recommendations for the continued operation of a project entity's existing coal-powered electrical generation facility.

recommendations for continued operation of a project entity's existing coal-powered electrical generation facility;
Section 11-13-319(4)(b)Verify source
§ 11-13-319(4)(c)Subsection 11-13-319(4)(c)Provision

environmental controls that need to be implemented for the continued operation of a project entity's existing coal-powered electrical generation facility;

environmental controls that need to be implemented for the continued operation of a project entity's existing coal-powered electrical generation facility;
Section 11-13-319(4)(c)Verify source
§ 11-13-319(4)(d)Subsection 11-13-319(4)(d)Provision

recommendations to increase local and state tax revenue through the continued operation of a project entity's existing coal-powered electrical generation facility; and

recommendations to increase local and state tax revenue through the continued operation of a project entity's existing coal-powered electrical generation facility; and
Section 11-13-319(4)(d)Verify source
§ 11-13-319(4)(e)Subsection 11-13-319(4)(e)Provision

recommendations for legislation to be introduced in the 2024 General Session to enable the continued operation of a project entity's existing coal-powered electrical generation facility.

recommendations for legislation to be introduced in the 2024 General Session to enable the continued operation of a project entity's existing coal-powered electrical generation facility.
Section 11-13-319(4)(e)Verify source

Legislative relationships

0 referenced instruments

Names are derived from the stored provision headings and citation-enrichment layer. Treat this as a research index and verify each relationship against the source text.

No structured legislative relationships were detected

The statute remains fully searchable by provision. Consult the source text for amendments and cross-references that have not yet been indexed.

Recorded versions and source checkpoint

1 version available in this collection

Current-law checkpoint
  • Undated version · currentEnglish · In force

Source-linked research

Ask AI about this statute

The overview, provisions, and source records above are public. Continue in a separate conversation with this statute’s jurisdiction and source version attached.

About this LexChat collection

Statute information is organised from identified legislative sources for professional research. Corrections can be reported to hello@esheria.ai.