Bellone (Free movement of persons) [1998] EUECJ C-215/97 (30 April 1998)
Council Directive 86/653/EEC precludes a national rule which makes the validity of an agency contract conditional upon the commercial agent being entered in the appropriate register, as the Directive exhaustively regulates formal requirements and does not permit such a condition.
- Citation
- [1998] EUECJ C-215/97
- Parties
- Intervener: Commission; Applicant/respondent: Unknown (parties to the main proceedings before the Tribunale, Bologna)
- Jurisdiction
- European Union
- Judgment Date
- 30 April 1998
- Procedural Posture
- Preliminary Ruling (reference for a Preliminary Ruling) / Judgment on Reference From National Court
- Outcome
- Directive 86/653/EEC precludes a national rule making validity of agency contract conditional on agent's registration.
- Legal Topics
- Agency Contracts, Freedom of Establishment, Directive 86/653/eec, Formal Requirements for Contracts
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Commission
Intervener
Unknown (parties to the main proceedings before the Tribunale, Bologna)
Applicant/respondent
Procedural Posture
Preliminary Ruling (reference for a Preliminary Ruling) / Judgment on Reference From National Court
Legal Issues
- 1 Whether Council Directive 86/653/EEC precludes a national rule making the validity of an agency contract conditional upon the commercial agent being entered in a register
Ratio Decidendi
Council Directive 86/653/EEC precludes a national rule which makes the validity of an agency contract conditional upon the commercial agent being entered in the appropriate register, as the Directive exhaustively regulates formal requirements and does not permit such a condition.
Court Disposition
Directive 86/653/EEC precludes a national rule making validity of agency contract conditional on agent's registration.
Orders
- The answer to the question referred is that Directive 86/653/EEC precludes a national rule which makes the validity of an agency contract conditional upon the commercial agent being entered in the appropriate register.
- Costs incurred by the Commission are not recoverable; decision on costs for main parties is for the national court.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment