EULEX-KOSOVO (Common Foreign and Security Policy - European Union Rule of Law Mission in Kosovo - Judgment) [2022] EUECJ C-283/20 (24 February 2022)

EULEX-KOSOVO (Common Foreign and Security Policy - European Union Rule of Law Mission in Kosovo - Judgment) [2022] EUECJ C-283/20 (24 February 2022)

Article 16(5) of Council Joint Action 2008/124/CFSP, as amended by Council Decision 2014/349/CFSP, must be interpreted as meaning that, starting from 15 June 2014, Eulex Kosovo is responsible and therefore the proper defendant in any action relating to the consequences of the implementation of its mission,...

Source-derived case information.

Citation
[2022] EUECJ C-283/20
Parties
Applicant: CO and Others (45 members or former members of the international civilian staff of Eulex Kosovo); Respondent: MJ (Head of Mission); Respondent: European Commission; Respondent: European External Action Service (EEAS); Respondent: Council of the European Union
Jurisdiction
European Union
Procedural Posture
Preliminary Ruling (reference for Interpretation) / Judgment on Preliminary Reference
Outcome
Preliminary ruling issued; Article 16(5) of Joint Action 2008/124, as amended, interpreted as transferring responsibility to Eulex Kosovo from 15 June 2014 for all relevant claims, regardless of when the underlying facts occurred.
Legal Topics
Interpretation of Council Joint Action 2008/124/cfsp, Responsibility for Employment Claims in EU Missions, Legal Personality and Liability of Eulex Kosovo, Jurisdiction Over Employment Disputes, Temporal Application of Amendments to EU Legal Acts
European Union Law Employment Law International Administrative Law Interpretation of Council Joint Action 2008/124/cfsp Responsibility for Employment Claims in EU Missions Legal Personality and Liability of Eulex Kosovo Jurisdiction Over Employment Disputes Temporal Application of Amendments to EU Legal Acts

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 10 Party arguments 2
Sign in to unlock

Parties

CO and Others (45 members or former members of the international civilian staff of Eulex Kosovo)

Applicant

MJ (Head of Mission)

Respondent

European Commission

Respondent

European External Action Service (EEAS)

Respondent

Council of the European Union

Respondent

Procedural Posture

Preliminary Ruling (reference for Interpretation) / Judgment on Preliminary Reference

  1. 1 Who is the responsible employer for international civilian staff of Eulex Kosovo prior to 12 June 2014?
  2. 2 Does Article 16(5) of Joint Action 2008/124, as amended, transfer responsibility for claims arising before 12 June 2014 to Eulex Kosovo?
  3. 3 What is the temporal scope of Eulex Kosovo's legal responsibility under the amended Joint Action?

Ratio Decidendi

Article 16(5) of Council Joint Action 2008/124/CFSP, as amended by Council Decision 2014/349/CFSP, must be interpreted as meaning that, starting from 15 June 2014, Eulex Kosovo is responsible and therefore the proper defendant in any action relating to the consequences of the implementation of its mission, irrespective of whether the underlying facts occurred before 12 June 2014.

Court Disposition

Preliminary ruling issued; Article 16(5) of Joint Action 2008/124, as amended, interpreted as transferring responsibility to Eulex Kosovo from 15 June 2014 for all relevant claims, regardless of when the underlying facts occurred.

Orders

  • Article 16(5) of Council Joint Action 2008/124/CFSP, as amended by Council Decision 2014/349/CFSP, designates Eulex Kosovo as responsible and as defendant in any action relating to the consequences of the implementation of its mission, irrespective of whether the facts occurred before 12 June 2014.