Commission v France (Environment and consumers) [2002] EUECJ C-177/01 (06 June 2002)

Commission v France (Environment and consumers) [2002] EUECJ C-177/01 (06 June 2002)

The French Republic failed to communicate the required summary of inventories, plan, and outline within the period specified in the reasoned opinion, thereby breaching its obligations under Articles 4 and 11 of Directive 96/59/EC.

Source-derived case information.

Citation
[2002] EUECJ C-177/01
Parties
Applicant: Commission of the European Communities; Respondent: French Republic
Jurisdiction
European Union
Procedural Posture
Infringement Proceedings Under Article 226 EC / Final Judgment
Outcome
Declaration of infringement and order to pay costs
Legal Topics
Failure to Fulfil Obligations, Directive 96/59/ec, Polychlorinated Biphenyls (pcbs), Member State Obligations
European Union Law Environmental Law Failure to Fulfil Obligations Directive 96/59/ec Polychlorinated Biphenyls (pcbs) Member State Obligations

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 1 Authorities cited 7 Party arguments 2
Sign in to unlock

Parties

Commission of the European Communities

Applicant

French Republic

Respondent

Procedural Posture

Infringement Proceedings Under Article 226 EC / Final Judgment

  1. 1 Whether the French Republic failed to communicate to the Commission a summary of inventories, a decontamination/disposal plan, and an outline for collection/disposal of PCB equipment as required by Directive 96/59/EC

Ratio Decidendi

The French Republic failed to communicate the required summary of inventories, plan, and outline within the period specified in the reasoned opinion, thereby breaching its obligations under Articles 4 and 11 of Directive 96/59/EC.

Court Disposition

Declaration of infringement and order to pay costs

Orders

  • The French Republic has failed to fulfil its obligations under Articles 4 and 11 of Directive 96/59/EC.
  • The French Republic is ordered to pay the costs.