Commission v Italy (Law relating to undertakings) [2004] EUECJ C-385/02 (14 September 2004)

Commission v Italy (Law relating to undertakings) [2004] EUECJ C-385/02 (14 September 2004)

Italy failed to fulfil its obligations under Directive 93/37/EEC by awarding public works contracts by negotiated procedure without prior publication of a contract notice, as none of the exceptions in Article 7(3) applied: technical necessity and urgency were not established, and the repetition of works exception...

Source-derived case information.

Citation
[2004] EUECJ C-385/02
Parties
Applicant: Commission of the European Communities; Respondent: Italian Republic
Jurisdiction
European Union
Procedural Posture
Infringement Proceedings / Final Judgment
Outcome
Application granted. Declaration of infringement issued.
Legal Topics
Failure to Fulfil Obligations, Public Works Contracts, Negotiated Procedure Without Prior Publication, Interpretation of Directive 93/37/eec
European Union Law Public Procurement Failure to Fulfil Obligations Public Works Contracts Negotiated Procedure Without Prior Publication Interpretation of Directive 93/37/eec

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 5 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

Commission of the European Communities

Applicant

Italian Republic

Respondent

Procedural Posture

Infringement Proceedings / Final Judgment

  1. 1 Whether Italy failed to fulfil obligations under Directive 93/37/EEC by awarding public works contracts by negotiated procedure without prior publication of a contract notice when conditions were not satisfied

Ratio Decidendi

Italy failed to fulfil its obligations under Directive 93/37/EEC by awarding public works contracts by negotiated procedure without prior publication of a contract notice, as none of the exceptions in Article 7(3) applied: technical necessity and urgency were not established, and the repetition of works exception was time-barred since the contracts were awarded more than three years after the original contracts were entered into.

Court Disposition

Application granted. Declaration of infringement issued.

Orders

  • Italian Republic declared to have failed to fulfil obligations under Directive 93/37/EEC.
  • Italian Republic ordered to pay the costs.