Commission v Italy (Environment & consumers) [2005] EUECJ C-83/03 (02 June 2005)

Commission v Italy (Environment & consumers) [2005] EUECJ C-83/03 (02 June 2005)

The Italian Republic failed to fulfil its obligations under Article 4(2) of Directive 85/337/EEC by not properly determining whether the Fossacesia marina project required an environmental assessment prior to granting consent.

Source-derived case information.

Citation
[2005] EUECJ C-83/03
Parties
Applicant: Commission of the European Communities; Respondent: Italian Republic
Jurisdiction
European Union
Procedural Posture
Infringement Proceedings / Final Judgment
Outcome
application upheld
Legal Topics
Environmental Impact Assessment, Failure to Fulfil Obligations, Development Consent Procedures
Environmental Law European Union Law Environmental Impact Assessment Failure to Fulfil Obligations Development Consent Procedures

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 5 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

Commission of the European Communities

Applicant

Italian Republic

Respondent

Procedural Posture

Infringement Proceedings / Final Judgment

  1. 1 Whether the Italian Republic failed to fulfil its obligations under Article 4(2) of Directive 85/337/EEC by not properly determining if the Fossacesia marina project required an environmental assessment

Ratio Decidendi

The Italian Republic failed to fulfil its obligations under Article 4(2) of Directive 85/337/EEC by not properly determining whether the Fossacesia marina project required an environmental assessment prior to granting consent.

Court Disposition

application upheld

Orders

  • Italian Republic declared to have failed to fulfil its obligations under Article 4(2) of Directive 85/337/EEC
  • Italian Republic ordered to pay the costs